Project overview

Shreeji Iconic Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700013918. Shreeji Iconic Phase I is located at 137B, 148 Hn1 And 2B, 145 Hn 1. This is a New being developed by Raj Laxmi Developers.

Shreeji Iconic Phase I has 1 BHK & 2 BHK Apartments with carpet areas ranging from 307 to 524 Sq.ft. Carpet. The Project has total 175 of which 97 are currently available for sale.

Shreeji Iconic Phase I is being developed on a total land area of 52525 Sq.ft. out of which 5090 Sq.ft. i.e 10% is reserved for recreational purposes. Shreeji Iconic Phase I has 2 Wings / Towers Building No 1,Building No 3

ProjectDeveloperLocationPossession
Jeevan LifestylesJeevan EnterprisesS N 148 / 13/1531-03-2019 00:00:00
Marathon Nagari Nx Vigo DMarathon Realty Pvt Ltd79/3Pt. 83/10Pt.30-06-2019 00:00:00
Marathon Nagari Nx Vitoria DMarathon Realty Pvt Ltd79/3Pt. 83/10Pt.31-12-2019 00:00:00
Saishyam ArcadeShubh BuildspaceSurvey No 20, Hissa No 2,431-12-2025 00:00:00
Shreeji IconicRaj Laxmi DevelopersSr No 137B And Sr No 9 H No 1031-12-2028 00:00:00
Samarth Shivani Co-Operative Housing Society LimitedGururaj Enterprises Builders And DevelopersS.No. 31, H. No. 2/A, Plot No. 8 & 931-08-2025 00:00:00
Surval HeightsGayatri DevelopersSurvey No 46 H No 11/12 And S No 83 H No 7/831-12-2023 00:00:00
Shubh Vastu Wing B And CShubh HomesSurvey No.143, Hissa No.3, 4 And 731-12-2025 00:00:00
Sarveshwar Co-Op Hsg SocDalal BuildscapeTaluka Ambernath30-06-2024 00:00:00
Project Details
  • Project:
    Shreeji Iconic Phase I
  • Location:
  • 137B, 148 Hn1 And 2B, 145 Hn 1
  • Const. Stage:
    New
  • Possession:
    30 May 2022
Developer Details

  • Developer:
    Raj Laxmi Developers
  • Phone:
  • Address:
  • Shreeji Iconic
Project RERA Details
MAHA REARA No: P51700013918
Project Type Residential / Group Housing
RERA Project Status New
Architect Urban Architects
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 30 May 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 02 Nov 2017
Last Retrived 26 Jul 2025
Shreeji Iconic Phase I QR Code
Shreeji Iconic Phase I
MahaRERA - P51700013918
Apartment Details & Configuration
TypeArea
1 BHK29.7 Sq.mts. ( 320 Sq.ft. )
1 BHK30.13 Sq.mts. ( 324 Sq.ft. )
1 BHK30.62 Sq.mts. ( 330 Sq.ft. )
1 BHK30.67 Sq.mts. ( 330 Sq.ft. )
1 BHK31.05 Sq.mts. ( 334 Sq.ft. )
1 BHK31.1 Sq.mts. ( 335 Sq.ft. )
1 BHK31.12 Sq.mts. ( 335 Sq.ft. )
1 BHK31.16 Sq.mts. ( 335 Sq.ft. )
1 BHK31.36 Sq.mts. ( 338 Sq.ft. )
1 BHK31.72 Sq.mts. ( 341 Sq.ft. )
1 BHK32.15 Sq.mts. ( 346 Sq.ft. )
1 BHK33.53 Sq.mts. ( 361 Sq.ft. )
1 BHK33.96 Sq.mts. ( 366 Sq.ft. )
1 BHK33.97 Sq.mts. ( 366 Sq.ft. )
1 BHK28.54 Sq.mts. ( 307 Sq.ft. )
1 BHK29.11 Sq.mts. ( 313 Sq.ft. )
1 BHK30.49 Sq.mts. ( 328 Sq.ft. )
1 BHK31.39 Sq.mts. ( 338 Sq.ft. )
1 BHK32 Sq.mts. ( 344 Sq.ft. )
1 BHK32.35 Sq.mts. ( 348 Sq.ft. )
1 BHK32.71 Sq.mts. ( 352 Sq.ft. )
1 BHK33.38 Sq.mts. ( 359 Sq.ft. )
1 BHK33.82 Sq.mts. ( 364 Sq.ft. )
2 BHK46.9 Sq.mts. ( 505 Sq.ft. )
2 BHK47.36 Sq.mts. ( 510 Sq.ft. )
2 BHK47.45 Sq.mts. ( 511 Sq.ft. )
2 BHK48.11 Sq.mts. ( 518 Sq.ft. )
2 BHK48.58 Sq.mts. ( 523 Sq.ft. )
2 BHK48.67 Sq.mts. ( 524 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shreeji Iconic Phase Ilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completed
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting
In Progress
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Stp Not Proposed. Only Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply
In Progress
Buildings / Wings in Shreeji Iconic Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shreeji Iconic Phase I by Raj Laxmi Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

52525 Sq. ft.

Project Area

5090 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

175 apartments in total
Total
175
Booked
78
Available
97

Saleable Area Statistics (Sq. ft.)

66348 Total
Total
66348
Booked
28552
Available
37796
Total 175 apartments in project. 78 apartments booked. 44% apartments booked.
Total 66348 Sq.ft. saleable area. 28552 saleable area booked.
43% area booked.

Building No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1May 202191010011
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.7 Sq.mts. ( 320 Sq.ft. )5
2 Booked40% Booked
40% Booked
1 BHK30.13 Sq.mts. ( 324 Sq.ft. )4
2 Booked50% Booked
50% Booked
1 BHK30.62 Sq.mts. ( 330 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK30.67 Sq.mts. ( 330 Sq.ft. )3
1 Booked33% Booked
33% Booked
1 BHK31.05 Sq.mts. ( 334 Sq.ft. )8
6 Booked75% Booked
75% Booked
1 BHK31.1 Sq.mts. ( 335 Sq.ft. )28
14 Booked50% Booked
50% Booked
1 BHK31.12 Sq.mts. ( 335 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK31.16 Sq.mts. ( 335 Sq.ft. )8
5 Booked62% Booked
62% Booked
1 BHK31.36 Sq.mts. ( 338 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK31.72 Sq.mts. ( 341 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK32.15 Sq.mts. ( 346 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK33.53 Sq.mts. ( 361 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK33.96 Sq.mts. ( 366 Sq.ft. )8
4 Booked50% Booked
50% Booked
1 BHK33.97 Sq.mts. ( 366 Sq.ft. )8
5 Booked62% Booked
62% Booked
88 total apartments / 51 apartments booked. 57% apartments booked.
Work Description in Building Building No 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3May 2021101010016
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.54 Sq.mts. ( 307 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK29.11 Sq.mts. ( 313 Sq.ft. )5
1 Booked20% Booked
20% Booked
1 BHK30.49 Sq.mts. ( 328 Sq.ft. )4
2 Booked50% Booked
50% Booked
1 BHK31.05 Sq.mts. ( 334 Sq.ft. )5
1 Booked20% Booked
20% Booked
1 BHK31.39 Sq.mts. ( 338 Sq.ft. )8
3 Booked37% Booked
37% Booked
1 BHK32 Sq.mts. ( 344 Sq.ft. )10
4 Booked40% Booked
40% Booked
1 BHK32.35 Sq.mts. ( 348 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK32.71 Sq.mts. ( 352 Sq.ft. )4
1 Booked25% Booked
25% Booked
1 BHK33.38 Sq.mts. ( 359 Sq.ft. )5
1 Booked20% Booked
20% Booked
1 BHK33.82 Sq.mts. ( 364 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK46.9 Sq.mts. ( 505 Sq.ft. )3
None Booked0% Booked
0% Booked
2 BHK47.36 Sq.mts. ( 510 Sq.ft. )15
6 Booked40% Booked
40% Booked
2 BHK47.45 Sq.mts. ( 511 Sq.ft. )12
3 Booked25% Booked
25% Booked
2 BHK48.11 Sq.mts. ( 518 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK48.58 Sq.mts. ( 523 Sq.ft. )5
2 Booked40% Booked
40% Booked
2 BHK48.67 Sq.mts. ( 524 Sq.ft. )4
1 Booked25% Booked
25% Booked
87 total apartments / 27 apartments booked. 31% apartments booked.
Work Description in Building Building No 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Raj Laxmi Developers
for Project
Shreeji Iconic Phase I
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation