Project overview

Shree Township Phase 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000035083. Shree Township Phase 2 is located at 401501, Palghar, Kambalgaon. This is a New Project being developed by Shree Shivbali Builders Private Limited.

Shree Township Phase 2 has 1 BHK, 2 BHK & Shop Apartments with carpet areas ranging from 108 to 487 Sq.ft. Carpet. The Project has total 144 of which 144 are currently available for sale.

Shree Township Phase 2 is being developed on a total land area of 52936 Sq.ft. out of which 529 Sq.ft. i.e 1% is reserved for recreational purposes. Shree Township Phase 2 has 5 Wings / Towers Building No 3 Wing A,Building No 3 Wing B,Building No 4 Wing A,Building No 4 Wing B,Building No 4 Wing C

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Shree Township Phase 2
  • Location:
  • 401501, Palghar, Kambalgaon
  • Const. Stage:
    New Project
  • Possession:
    31 Dec 2028
Developer Details

  • Developer:
    Shree Shivbali Builders Private Limited
  • Phone:
  • Address:
  • B-102, Jay Vijay Green Building No 2, -, -, Achole, 401209
Project RERA Details
MAHA REARA No: P99000035083
Project Type Others
RERA Project Status New Project
Architect Oaa
Funding Bank ICICI BANK
Proposed Possession 31 Dec 2028
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 29 Apr 2022
Last Retrived 28 Jul 2025
Shree Township Phase 2 QR Code
Shree Township Phase 2
MahaRERA - P99000035083
Apartment Details & Configuration
TypeArea
1 BHK30.92 Sq.mts. ( 333 Sq.ft. )
1 BHK31.1 Sq.mts. ( 335 Sq.ft. )
1 BHK31.23 Sq.mts. ( 336 Sq.ft. )
2 BHK46.87 Sq.mts. ( 505 Sq.ft. )
Shop8.64 Sq.mts. ( 93 Sq.ft. )
Shop11.02 Sq.mts. ( 119 Sq.ft. )
Shop11.35 Sq.mts. ( 122 Sq.ft. )
Shop11.88 Sq.mts. ( 128 Sq.ft. )
Shop14.54 Sq.mts. ( 157 Sq.ft. )
Shop23 Sq.mts. ( 248 Sq.ft. )
1 BHK31.28 Sq.mts. ( 337 Sq.ft. )
Shop8.51 Sq.mts. ( 92 Sq.ft. )
Shop10.41 Sq.mts. ( 112 Sq.ft. )
1 BHK27.57 Sq.mts. ( 297 Sq.ft. )
1 BHK30.91 Sq.mts. ( 333 Sq.ft. )
1 BHK45.27 Sq.mts. ( 487 Sq.ft. )
Shop11.75 Sq.mts. ( 126 Sq.ft. )
Shop12.88 Sq.mts. ( 139 Sq.ft. )
Shop16.8 Sq.mts. ( 181 Sq.ft. )
Shop10.06 Sq.mts. ( 108 Sq.ft. )
Shop12.16 Sq.mts. ( 131 Sq.ft. )
Shop16.6 Sq.mts. ( 179 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shree Township Phase 2last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Not Yet Started
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Not Yet Started
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Not Yet Started
Open Parking
Not Yet Started
Sewerage (Chamber, Lines, Septic Tank , STP)
Not Yet Started
Solid Waste Management And Disposal
Na
Storm Water Drains
Not Yet Started
Street Lighting
Not Yet Started
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply
Not Yet Started
Buildings / Wings in Shree Township Phase 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shree Township Phase 2 by Shree Shivbali Builders Private Limitedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

52936 Sq. ft.

Project Area

529 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

144 apartments in total
Total
144
Booked
0
Available
144

Saleable Area Statistics (Sq. ft.)

42151 Total
Total
42151
Booked
0
Available
42151
Total 144 apartments in project. 0 apartments booked. 0% apartments booked.
Total 42151 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Building No 3 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3 Wing ADec 20285101040
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.92 Sq.mts. ( 333 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK31.1 Sq.mts. ( 335 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK31.23 Sq.mts. ( 336 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK46.87 Sq.mts. ( 505 Sq.ft. )4
None Booked0% Booked
0% Booked
Shop8.64 Sq.mts. ( 93 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.02 Sq.mts. ( 119 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.35 Sq.mts. ( 122 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.88 Sq.mts. ( 128 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop14.54 Sq.mts. ( 157 Sq.ft. )7
None Booked0% Booked
0% Booked
Shop23 Sq.mts. ( 248 Sq.ft. )1
None Booked0% Booked
0% Booked
29 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 3 Wing ACompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No 3 Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3 Wing BDec 20285101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.28 Sq.mts. ( 337 Sq.ft. )16
None Booked0% Booked
0% Booked
Shop8.51 Sq.mts. ( 92 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop10.41 Sq.mts. ( 112 Sq.ft. )4
None Booked0% Booked
0% Booked
22 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 3 Wing BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No 4 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4 Wing ADec 20285101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.57 Sq.mts. ( 297 Sq.ft. )19
None Booked0% Booked
0% Booked
1 BHK30.91 Sq.mts. ( 333 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK45.27 Sq.mts. ( 487 Sq.ft. )4
None Booked0% Booked
0% Booked
Shop11.75 Sq.mts. ( 126 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.88 Sq.mts. ( 139 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.8 Sq.mts. ( 181 Sq.ft. )1
None Booked0% Booked
0% Booked
30 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 4 Wing ACompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress33% done
33% Booked
X number of Podiums
X number of Slabs of Super Structure

Building No 4 Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4 Wing BDec 20285101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.57 Sq.mts. ( 297 Sq.ft. )18
None Booked0% Booked
0% Booked
1 BHK30.91 Sq.mts. ( 333 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK45.27 Sq.mts. ( 487 Sq.ft. )4
None Booked0% Booked
0% Booked
Shop10.06 Sq.mts. ( 108 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.16 Sq.mts. ( 131 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.88 Sq.mts. ( 139 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.6 Sq.mts. ( 179 Sq.ft. )1
None Booked0% Booked
0% Booked
30 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 4 Wing BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress33% done
33% Booked
X number of Podiums
X number of Slabs of Super Structure

Building No 4 Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4 Wing CDec 20285101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.57 Sq.mts. ( 297 Sq.ft. )18
None Booked0% Booked
0% Booked
1 BHK30.91 Sq.mts. ( 333 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK45.27 Sq.mts. ( 487 Sq.ft. )4
None Booked0% Booked
0% Booked
Shop10.06 Sq.mts. ( 108 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.75 Sq.mts. ( 126 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.16 Sq.mts. ( 131 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.88 Sq.mts. ( 139 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop16.6 Sq.mts. ( 179 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.8 Sq.mts. ( 181 Sq.ft. )1
None Booked0% Booked
0% Booked
33 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 4 Wing CCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress33% done
33% Booked
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Shree Shivbali Builders Private Limited
for Project
Shree Township Phase 2
last updated on 28 Jul 2025 as per information obtained from MARA RERA.