Project overview

Shree Siddhivinayak Park C1,C2,C3 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700024653. Shree Siddhivinayak Park C1,C2,C3 is located at 421401. This is a New Project being developed by Satyashiv Developers.

Shree Siddhivinayak Park C1,C2,C3 has 1 BHK Apartments with carpet areas ranging from 370 to 404 Sq.ft. Carpet. The Project has total 73 of which 36 are currently available for sale.

Shree Siddhivinayak Park C1,C2,C3 is being developed on a total land area of 31434 Sq.ft. Shree Siddhivinayak Park C1,C2,C3 has 3 Wings / Towers Shree Siddhivinayak Park C1,Shree Siddhivinayak Park C2,Shree Siddhivinayak Park C3

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Shree Siddhivinayak Park C1,C2,C3
  • Location:
  • 421401
  • Const. Stage:
    New Project
  • Possession:
    30 Dec 2026
Developer Details

  • Developer:
    Satyashiv Developers
  • Phone:
  • Address:
  • Shop No. 2, Hasti Navjeevandeep Chs, Pandurang Wadi, Model English School Road, Dombivli East, 421201
Project RERA Details
MAHA REARA No: P51700024653
Project Type Residential
RERA Project Status New Project
Funding Bank ICICI BANKLIMITED
Proposed Possession 30 Dec 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 12 Feb 2024
Last Retrived 28 Jul 2025
Shree Siddhivinayak Park C1,C2,C3 QR Code
Shree Siddhivinayak Park C1,C2,C3
MahaRERA - P51700024653
Apartment Details & Configuration
TypeArea
1 BHK35.38 Sq.mts. ( 381 Sq.ft. )
1 BHK35.52 Sq.mts. ( 382 Sq.ft. )
1 BHK35.91 Sq.mts. ( 387 Sq.ft. )
1 BHK36.62 Sq.mts. ( 394 Sq.ft. )
1 BHK40.12 Sq.mts. ( 432 Sq.ft. )
1 BHK40.21 Sq.mts. ( 433 Sq.ft. )
1 BHK41.03 Sq.mts. ( 442 Sq.ft. )
2 BHK46.1 Sq.mts. ( 496 Sq.ft. )
2 BHK60.06 Sq.mts. ( 646 Sq.ft. )
1 BHK34.53 Sq.mts. ( 372 Sq.ft. )
1 BHK34.57 Sq.mts. ( 372 Sq.ft. )
1 BHK35.63 Sq.mts. ( 384 Sq.ft. )
1 BHK35.67 Sq.mts. ( 384 Sq.ft. )
1 BHK36.84 Sq.mts. ( 397 Sq.ft. )
1 BHK38.07 Sq.mts. ( 410 Sq.ft. )
2 BHK45.67 Sq.mts. ( 492 Sq.ft. )
2 BHK52.42 Sq.mts. ( 564 Sq.ft. )
1 BHK34.37 Sq.mts. ( 370 Sq.ft. )
1 BHK35.32 Sq.mts. ( 380 Sq.ft. )
1 BHK35.8 Sq.mts. ( 385 Sq.ft. )
1 BHK37.05 Sq.mts. ( 399 Sq.ft. )
1 BHK37.5 Sq.mts. ( 404 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shree Siddhivinayak Park C1,C2,C3last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
All Done
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
All Done
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
All Done
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
All Done
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
All Done
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply
N P Will Provide Water Connection After Oc
Buildings / Wings in Shree Siddhivinayak Park C1,C2,C3
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shree Siddhivinayak Park C1,C2,C3 by Satyashiv Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

31434 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

73 apartments in total
Total
73
Booked
37
Available
36

Saleable Area Statistics (Sq. ft.)

32119 Total
Total
32119
Booked
15353
Available
16766
Total 73 apartments in project. 37 apartments booked. 50% apartments booked.
Total 32119 Sq.ft. saleable area. 15353 saleable area booked.
48% area booked.

Shree Siddhivinayak Park C1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shree Siddhivinayak Park C1Dec 20258101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK35.38 Sq.mts. ( 381 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK35.52 Sq.mts. ( 382 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK35.91 Sq.mts. ( 387 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK36.62 Sq.mts. ( 394 Sq.ft. )7
1 BHK40.12 Sq.mts. ( 432 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK40.21 Sq.mts. ( 433 Sq.ft. )7
3 Booked42% Booked
42% Booked
1 BHK41.03 Sq.mts. ( 442 Sq.ft. )7
None Booked0% Booked
0% Booked
2 BHK46.1 Sq.mts. ( 496 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK60.06 Sq.mts. ( 646 Sq.ft. )7
None Booked0% Booked
0% Booked
39 total apartments / 4 apartments booked. 10% apartments booked.
Work Description in Building Shree Siddhivinayak Park C1Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Shree Siddhivinayak Park C2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shree Siddhivinayak Park C2Dec 20255101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.53 Sq.mts. ( 372 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK34.57 Sq.mts. ( 372 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK35.63 Sq.mts. ( 384 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK35.67 Sq.mts. ( 384 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK36.84 Sq.mts. ( 397 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK38.07 Sq.mts. ( 410 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK45.67 Sq.mts. ( 492 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK52.42 Sq.mts. ( 564 Sq.ft. )4
4 Booked100% Booked
100% Booked
20 total apartments / 19 apartments booked. 95% apartments booked.
Work Description in Building Shree Siddhivinayak Park C2Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Shree Siddhivinayak Park C3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shree Siddhivinayak Park C3Dec 20255101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.37 Sq.mts. ( 370 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK35.32 Sq.mts. ( 380 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK35.8 Sq.mts. ( 385 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK37.05 Sq.mts. ( 399 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK37.5 Sq.mts. ( 404 Sq.ft. )4
4 Booked100% Booked
100% Booked
14 total apartments / 14 apartments booked. 100% apartments booked.
Work Description in Building Shree Siddhivinayak Park C3Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Satyashiv Developers
for Project
Shree Siddhivinayak Park C1,C2,C3
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation