Project overview

Shree Anandi Heritage is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700021914. Shree Anandi Heritage is located at Survey No 28 Hissa No 1/2 Part And Survey No 35 Hissa No 6. This is a New being developed by Jai Malhar Builders & Developers.

Shree Anandi Heritage has ONE BHK & TWO BHK Apartments with carpet areas ranging from 327 to 466 Sq.ft. Carpet. The Project has total 132 of which 3 are currently available for sale.

Shree Anandi Heritage is being developed on a total land area of 24757 Sq.ft. out of which 1829 Sq.ft. i.e 7% is reserved for recreational purposes. Shree Anandi Heritage has 3 Wings / Towers Wing A,Wing B,Wing C

ProjectDeveloperLocationPossession
Tycoons Square Avenue I Tower BTycoons Avanti Projects LlpThane, 42130130-09-2021 00:00:00
Sarvoday Patwardhan BaugSarvoday DeveloperS No 35 Hissa No 2/1 2/2A 2/2C 2/3 2/4 2/531-01-2021 00:00:00
V Ten ResidencyV Ten Realty Private LimitedSurvey No 105 Hissa No 1 Village Chikanghar Kalyan 30-12-2020 00:00:00
Project Details
  • Project:
    Shree Anandi Heritage
  • Location:
  • Survey No 28 Hissa No 1/2 Part And Survey No 35 Hissa No 6
  • Const. Stage:
    New
  • Possession:
    30 May 2023
Developer Details

  • Developer:
    Jai Malhar Builders & Developers
  • Phone:
  • Address:
  • Anandibai Apts
Project RERA Details
MAHA REARA No: P51700021914
Project Type Residential / Group Housing
RERA Project Status New
Architect Dilip Tambay And Associates
Funding Bank YES BANK
Proposed Possession 30 May 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 23 Jun 2023
Last Retrived 26 Jul 2025
Shree Anandi Heritage QR Code
Shree Anandi Heritage
MahaRERA - P51700021914
Apartment Details & Configuration
TypeArea
1 BHK37.8 Sq.mts. ( 407 Sq.ft. )
2 BHK51.45 Sq.mts. ( 554 Sq.ft. )
1 BHK29.74 Sq.mts. ( 320 Sq.ft. )
2 BHK42.75 Sq.mts. ( 460 Sq.ft. )
2 BHK57.62 Sq.mts. ( 620 Sq.ft. )
Shop9.29 Sq.mts. ( 100 Sq.ft. )
ONE BHK30.36 Sq.mts. ( 327 Sq.ft. )
TWO BHK43.29 Sq.mts. ( 466 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shree Anandi Heritagelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
As Per Kdmc Plan
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
As Per Approved Plan
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Approved Plan
Landscaping & Tree Planting
Na
Open Parking
As Per Approved Plan
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
As Per Approved Plan
Solid Waste Management And Disposal
Na
Storm Water Drains
As Per Approved Plan
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
As Per Approved Plan
Water Supply100% completed
95% Complete
By Kdmc
Buildings / Wings in Shree Anandi Heritage
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shree Anandi Heritage by Jai Malhar Builders & Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

24757 Sq. ft.

Project Area

1829 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

132 apartments in total
Total
132
Booked
129
Available
3

Saleable Area Statistics (Sq. ft.)

62806 Total
Total
62806
Booked
61946
Available
860
Total 132 apartments in project. 129 apartments booked. 97% apartments booked.
Total 62806 Sq.ft. saleable area. 61946 saleable area booked.
99% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AMay 20227100080
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.8 Sq.mts. ( 407 Sq.ft. )28
28 Booked100% Booked
100% Booked
2 BHK51.45 Sq.mts. ( 554 Sq.ft. )7
7 Booked100% Booked
100% Booked
35 total apartments / 35 apartments booked. 100% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BMay 202212100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.74 Sq.mts. ( 320 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK42.75 Sq.mts. ( 460 Sq.ft. )70
67 Booked95% Booked
95% Booked
2 BHK57.62 Sq.mts. ( 620 Sq.ft. )23
24 Booked104% Booked
104% Booked
Shop9.29 Sq.mts. ( 100 Sq.ft. )1
None Booked0% Booked
0% Booked
97 total apartments / 94 apartments booked. 96% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CMay 20220000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
ONE BHK30.36 Sq.mts. ( 327 Sq.ft. )0
None Booked0% Booked
0% Booked
TWO BHK43.29 Sq.mts. ( 466 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Jai Malhar Builders & Developers
for Project
Shree Anandi Heritage
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation