Project overview

Shiv Shahi Complex is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700015735. Shiv Shahi Complex is located at 234/4/1,237. This is a New being developed by Shalini Shivaji Pawar.

Shiv Shahi Complex has Hall, Shop 1, Shop 2, Shop 3, Shop 4, Shop 5, Store 1, Store 2 & Store 3 Apartments with carpet areas ranging from 246 to 5033 Sq.ft. Carpet. The Project has total 92 of which 24 are currently available for sale.

Shiv Shahi Complex is being developed on a total land area of 42970 Sq.ft. out of which 10034 Sq.ft. i.e 23% is reserved for recreational purposes. Shiv Shahi Complex has 2 Wings / Towers Building C,Building D

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Shiv Shahi Complex
  • Location:
  • 234/4/1,237
  • Const. Stage:
    New
  • Possession:
    30 Jun 2019
Developer Details

  • Developer:
    Shalini Shivaji Pawar
  • Phone:
  • Address:
  • Gurukripa Building
Project RERA Details
MAHA REARA No: P51700015735
Project Type Residential / Group Housing
RERA Project Status New
Architect Shailaja Vaidya
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Jun 2019
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 18 Jan 2024
Last Retrived 26 Jul 2025
Shiv Shahi Complex QR Code
Shiv Shahi Complex
MahaRERA - P51700015735
Apartment Details & Configuration
TypeArea
1 BHK33.94 Sq.mts. ( 365 Sq.ft. )
1 BHK33.95 Sq.mts. ( 365 Sq.ft. )
1 BHK34.65 Sq.mts. ( 373 Sq.ft. )
1 BHK34.83 Sq.mts. ( 375 Sq.ft. )
2 BHK46.87 Sq.mts. ( 505 Sq.ft. )
Hall467.6 Sq.mts. ( 5033 Sq.ft. )
Shop 123.4 Sq.mts. ( 252 Sq.ft. )
Shop 224 Sq.mts. ( 258 Sq.ft. )
Shop 338.62 Sq.mts. ( 416 Sq.ft. )
Shop 422.84 Sq.mts. ( 246 Sq.ft. )
Shop 538.65 Sq.mts. ( 416 Sq.ft. )
Store 123.09 Sq.mts. ( 249 Sq.ft. )
Store 223.68 Sq.mts. ( 255 Sq.ft. )
Store 330.12 Sq.mts. ( 324 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shiv Shahi Complexlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Work In Progress
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Only Meter Room
Energy management
Work Yet Not Started
Fire Protection And Fire Safety Requirements95% completed
95% Complete
Work Yet Not Started
Landscaping & Tree Planting
Work In Progress
Open Parking
Work In Progress
Sewerage (Chamber, Lines, Septic Tank , STP)
Work In Progress
Solid Waste Management And Disposal
Work Yet Not Started
Storm Water Drains
Work In Progress
Street Lighting
Work Yet Not Started
Treatment And Disposal Of Sewage And Sullage Water
Work Yet Not Started
Water Conservation, Rain water Harvesting
Work In Progress
Water Supply
Work In Progress
Buildings / Wings in Shiv Shahi Complex
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shiv Shahi Complex by Shalini Shivaji Pawarlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

42970 Sq. ft.

Project Area

10034 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

92 apartments in total
Total
92
Booked
68
Available
24

Saleable Area Statistics (Sq. ft.)

42725 Total
Total
42725
Booked
24764
Available
17962
Total 92 apartments in project. 68 apartments booked. 73% apartments booked.
Total 42725 Sq.ft. saleable area. 24764 saleable area booked.
58% area booked.

Building C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building CJun 20199101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.94 Sq.mts. ( 365 Sq.ft. )24
17 Booked70% Booked
70% Booked
1 BHK33.95 Sq.mts. ( 365 Sq.ft. )16
10 Booked62% Booked
62% Booked
1 BHK34.65 Sq.mts. ( 373 Sq.ft. )8
7 Booked87% Booked
87% Booked
1 BHK34.83 Sq.mts. ( 375 Sq.ft. )16
14 Booked87% Booked
87% Booked
2 BHK46.87 Sq.mts. ( 505 Sq.ft. )8
6 Booked75% Booked
75% Booked
72 total apartments / 54 apartments booked. 75% apartments booked.
Work Description in Building Building CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building DJul 20183100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Hall467.6 Sq.mts. ( 5033 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop 123.4 Sq.mts. ( 252 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop 224 Sq.mts. ( 258 Sq.ft. )4
3 Booked75% Booked
75% Booked
Shop 338.62 Sq.mts. ( 416 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 422.84 Sq.mts. ( 246 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop 538.65 Sq.mts. ( 416 Sq.ft. )1
1 Booked100% Booked
100% Booked
Store 123.09 Sq.mts. ( 249 Sq.ft. )2
1 Booked50% Booked
50% Booked
Store 223.68 Sq.mts. ( 255 Sq.ft. )4
3 Booked75% Booked
75% Booked
Store 330.12 Sq.mts. ( 324 Sq.ft. )2
2 Booked100% Booked
100% Booked
20 total apartments / 14 apartments booked. 70% apartments booked.
Work Description in Building Building DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shalini Shivaji Pawar
for Project
Shiv Shahi Complex
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation