Project overview

Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700008430. Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H is located at S No 78/1, 79, 80/3. This is a Ongoing being developed by Shashwat Homes.

Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H has 1 BHK & 1RK Apartments with carpet areas ranging from 215 to 312 Sq.ft. Carpet. The Project has total 256 of which 30 are currently available for sale.

Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H is being developed on a total land area of 83744 Sq.ft. out of which 16279 Sq.ft. i.e 19% is reserved for recreational purposes. Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H has 3 Wings / Towers Building 4 Gh Laxman Dayare Apartment,Building No 2 Cd Vithabai Dayare Apartment,Building No 3 Ef Ramachandra Dayare Apartment

ProjectDeveloperLocationPossession
Aarsh Avenue - Saal Wood And Silver WoodSatyam ConstructionS. No. 56 H. No. 10/131-12-2019 00:00:00
Vastu ShilpVastu HomesS No 105A Hissa No 4231-03-2018 00:00:00
Umiya Complex Phase IiUmiya Associates12 P30-11-2020 00:00:00
Shashwat Park - Phase I - Wing PShashwat HomesGut No 761131-12-2018 00:00:00
Murlidhar PlazaSaipoojan EnterprisesGut No 40 Hissa No 1619-12-2021 00:00:00
Shashwat ParkModern ConstructionGat No. 65 Hissa No. 2V31-12-2018 00:00:00
Sadguru Harmony Ph-1 Wing ASadguru AssociateGut No 219/1/2 21831-12-2019 00:00:00
Shashwat Park -Phase Ii -Z4bShashwat HomesGut No 65/1A31-12-2018 00:00:00
Shashwat Park 1-AbShashwat HomesGut No 78 1, 80 3, 7930-03-2022 00:00:00
Saurabh ArcadeM/S Krishna Builders & DevelopersS No 7A H No 4A Plot No 1 230-12-2021 00:00:00
Shivam GreensM.K.DevelopersGut No 5 Hissa No 6, 11 And 1330-12-2023 00:00:00
Parshva Residency Wing CParshva Realtors2, 331-12-2019 00:00:00
Shree Krishna ResidencyPanchala Builders & DevelopersPlot Gut No.69 30-12-2023 00:00:00
Divya Jyot ComplexShree Aditi DevelopersGut No 76 Hissa No 4 And 930-12-2021 00:00:00
Deep AanganParekh InfraprojectsGut No 133 And Gut No 145/131-12-2019 00:00:00
Mohan Waters Edge IMohan Lifespaces Llp79/1,80/130-12-2021 00:00:00
Sadguru Symphony, Wing - D Of Phase - IiSadguru InfraBadlapur (W), Barvi Dam Road, Thane30-12-2022 00:00:00
Shrushti Aarambh, Wing - C Of Phase - IShrushti DevelopersGut No 123, 1730-12-2022 00:00:00
Datar HeightsSaleem Abdul ShaikhS.No 7A31-10-2019 00:00:00
Mohan Waters Edge IiMohan Lifespaces Llp79/1,80/130-12-2021 00:00:00
Ravi DarshanRavi DevelopersS.N0-105A25-05-2018 00:00:00
Mohan Greenwoods Building 1Mohan Lifespaces LlpGut No 1Pt And 5Pt31-12-2019 00:00:00
Sanveg HillsSanveg HomesGut No 47/50 And 47/1130-12-2021 00:00:00
Shrushti PrarambhShrushti DevelopersSurvey No.5 Hissa No.3/330-12-2022 00:00:00
Trimurti ResidencyTrimurti Construction CoPlot No. 107, Sector 21, Ulwe31-12-2018 00:00:00
Vedant Imperial Abc Phase 1Mohan Hardasmal TharwaniS No 56/3 57/1P 57/330-11-2019 00:00:00
Umiya DhamShree Mangalmurti DevelopersValivli31-07-2019 00:00:00
Maruti Prakruti DhamAvishkar DevelopersGut No 13 Hissa No 1 231-12-2018 00:00:00
Sadguru ResidencySadguru InfraGut No. 331-03-2018 00:00:00
Heramb Park Phase IiSai Samruddhi Construction CoGut No 61/2, Gut No 63/1,231-07-2019 00:00:00
Vedant Imperial Bunglow 1 To 8 Phase 2Mohan Hardasmal TharwaniS No 56/3 57/1P 57/330-12-2024 00:00:00
Dbr ClassicDbr Constructions Pvt Ltd330-12-2021 00:00:00
Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G HShashwat HomesS No 78/1, 79, 80/330-03-2022 00:00:00
Precious SolitaireShubh LifespacesGut No 90/2, 90/2A31-08-2026 00:00:00
Shashwat Park Z-5 A And B Wing ApartmentShashwat HomesGut No. 105, H. No. 5/1/A/130-06-2025 00:00:00
Pinnacle AdarshPinnacle EnterprisesSurvey No 5 Hiss No 4 Plot No 930-06-2025 00:00:00
Pine ViewSatya Developers153/6/131-03-2028 00:00:00
Sadguru Harmony Phase - 3 Wing CSadguru AssociateBadlapur30-06-2025 00:00:00
Sadguru Harmony Phase 4 Wing DSadguru AssociateGut No.218, Gut No. 219, H.No.1/230-06-2025 00:00:00
Project Details
  • Project:
    Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H
  • Location:
  • S No 78/1, 79, 80/3
  • Const. Stage:
    Ongoing
  • Possession:
    30 Mar 2022
Developer Details

  • Developer:
    Shashwat Homes
  • Phone:
  • Address:
  • Tulsishyam Soc
Project RERA Details
MAHA REARA No: P51700008430
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Space Designers
Funding Bank STATE BANK OF INDIA
Proposed Possession 30 Mar 2022
Revised Possession 30 Mar 2022
Extended Possession
Litigations No Litigations
Last Modified 18 Aug 2017
Last Retrived 26 Jul 2025
Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H QR Code
Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H
MahaRERA - P51700008430
Apartment Details & Configuration
TypeArea
1 BHK24.5 Sq.mts. ( 264 Sq.ft. )
1 BHK25 Sq.mts. ( 269 Sq.ft. )
1 BHK26 Sq.mts. ( 280 Sq.ft. )
1 BHK27.5 Sq.mts. ( 296 Sq.ft. )
1 BHK28 Sq.mts. ( 301 Sq.ft. )
1 BHK28.2 Sq.mts. ( 304 Sq.ft. )
1 BHK28.5 Sq.mts. ( 307 Sq.ft. )
1 BHK29 Sq.mts. ( 312 Sq.ft. )
1RK20 Sq.mts. ( 215 Sq.ft. )
1RK20.5 Sq.mts. ( 221 Sq.ft. )
1RK21 Sq.mts. ( 226 Sq.ft. )
2 BHK31 Sq.mts. ( 334 Sq.ft. )
SHOP7 Sq.mts. ( 75 Sq.ft. )
SHOP10 Sq.mts. ( 108 Sq.ft. )
SHOP10.5 Sq.mts. ( 113 Sq.ft. )
SHOP12.5 Sq.mts. ( 135 Sq.ft. )
SHOP16.5 Sq.mts. ( 178 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G Hlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
In Progress
Community Buildings100% completed
95% Complete
Club House Is Ready
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Work Completed
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Work Completed
Landscaping & Tree Planting50% completed
50% Complete
In Progress
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Work Completed
Solid Waste Management And Disposal
Na
Storm Water Drains
In Progress
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Work Completed
Water Supply100% completed
95% Complete
Mjp Connection After Oc
Buildings / Wings in Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H by Shashwat Homeslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

83744 Sq. ft.

Project Area

16279 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

256 apartments in total
Total
256
Booked
226
Available
30

Saleable Area Statistics (Sq. ft.)

74775 Total
Total
74775
Booked
66165
Available
8610
Total 256 apartments in project. 226 apartments booked. 88% apartments booked.
Total 74775 Sq.ft. saleable area. 66165 saleable area booked.
88% area booked.

Building 4 Gh Laxman Dayare Apartment

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 4 Gh Laxman Dayare ApartmentMar 20218100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.5 Sq.mts. ( 264 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK25 Sq.mts. ( 269 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK26 Sq.mts. ( 280 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK27.5 Sq.mts. ( 296 Sq.ft. )14
12 Booked85% Booked
85% Booked
1 BHK28 Sq.mts. ( 301 Sq.ft. )21
19 Booked90% Booked
90% Booked
1 BHK28.2 Sq.mts. ( 304 Sq.ft. )14
12 Booked85% Booked
85% Booked
1 BHK28.5 Sq.mts. ( 307 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 BHK29 Sq.mts. ( 312 Sq.ft. )14
12 Booked85% Booked
85% Booked
1RK20 Sq.mts. ( 215 Sq.ft. )7
6 Booked85% Booked
85% Booked
1RK20.5 Sq.mts. ( 221 Sq.ft. )1
1 Booked100% Booked
100% Booked
1RK21 Sq.mts. ( 226 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK31 Sq.mts. ( 334 Sq.ft. )7
7 Booked100% Booked
100% Booked
94 total apartments / 84 apartments booked. 89% apartments booked.
Work Description in Building Building 4 Gh Laxman Dayare ApartmentCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 2 Cd Vithabai Dayare Apartment

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2 Cd Vithabai Dayare ApartmentMar 20218100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.5 Sq.mts. ( 264 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK26 Sq.mts. ( 280 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK27.5 Sq.mts. ( 296 Sq.ft. )14
12 Booked85% Booked
85% Booked
1 BHK28 Sq.mts. ( 301 Sq.ft. )35
32 Booked91% Booked
91% Booked
1 BHK28.5 Sq.mts. ( 307 Sq.ft. )14
13 Booked92% Booked
92% Booked
1 BHK29 Sq.mts. ( 312 Sq.ft. )7
7 Booked100% Booked
100% Booked
SHOP7 Sq.mts. ( 75 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP10 Sq.mts. ( 108 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP10.5 Sq.mts. ( 113 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP12.5 Sq.mts. ( 135 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP16.5 Sq.mts. ( 178 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP20.5 Sq.mts. ( 221 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP21 Sq.mts. ( 226 Sq.ft. )1
1 Booked100% Booked
100% Booked
84 total apartments / 76 apartments booked. 90% apartments booked.
Work Description in Building Building No 2 Cd Vithabai Dayare ApartmentCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress79% done
79% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress90% done
90% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 3 Ef Ramachandra Dayare Apartment

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3 Ef Ramachandra Dayare ApartmentMar 20218100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.5 Sq.mts. ( 264 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK26 Sq.mts. ( 280 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK27.5 Sq.mts. ( 296 Sq.ft. )14
12 Booked85% Booked
85% Booked
1 BHK28 Sq.mts. ( 301 Sq.ft. )28
19 Booked67% Booked
67% Booked
1 BHK28.5 Sq.mts. ( 307 Sq.ft. )14
13 Booked92% Booked
92% Booked
1 BHK29 Sq.mts. ( 312 Sq.ft. )14
14 Booked100% Booked
100% Booked
1RK20 Sq.mts. ( 215 Sq.ft. )2
2 Booked100% Booked
100% Booked
78 total apartments / 66 apartments booked. 84% apartments booked.
Work Description in Building Building No 3 Ef Ramachandra Dayare ApartmentCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shashwat Homes
for Project
Shashwat Park - Phase I- Building 2 Wing C D,Building 3 Wing E F, Building 4 Wing G H
last updated on 26 Jul 2025 as per information obtained from MARA RERA.