Project overview

Sequoia is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800032970. Sequoia is located at C.T.S. No. 624/6 Of Village Bandra. This is a New being developed by Aum Prima Llp.

Sequoia has 1RK, 2 BHK, 3 BHK & 4 BHK Apartments with carpet areas ranging from 1146 to 960 Sq.ft. Carpet. The Project has total 32 of which 10 are currently available for sale.

Sequoia is being developed on a total land area of 16119 Sq.ft. Sequoia has 1 Wings / Towers Sequoia

ProjectDeveloperLocationPossession
Redevelopment Of Loita Kunj Chs LtdOrra Realtors Private LimitedE 18430-12-2024 00:00:00
Pearl 2Pearl Building No -2 Co -Operative Housing Society LimitedG/346-19, Plot No 83- C/B-231-07-2019 00:00:00
Redevelopment Of Shalaka Chs LtdDinaco Resorts Private LimitedCts No G-156 To 158 Plot No 32 Tps Ii Santacruz West31-12-2018 00:00:00
Rustomjee Paramount - Wing DKeystone Realtors LimitedCts Nos G/626 G/164-A Pt30-11-2020 00:00:00
Florence A P PropertiesE 195 A30-09-2018 00:00:00
Disha Co-Op Housing Society LtdPritesh SanghviPlot No 586 F.P. No 153831-12-2018 00:00:00
Pllatinum AuraG.S. DevelopersE/82531-03-2018 00:00:00
Santacruz Prakash Chs Ltd RedevelopmentPtr Corporations142 A -131-12-2018 00:00:00
Dlh OrnateDev Land & Housing Pvt Ltd598, 599 Village Khar West At Junction Of Rd 9 And 11, Cts No E 59731-12-2018 00:00:00
Unicore AuraUnicore RealtyMumbai Suburban, 40005230-12-2023 00:00:00
RamkrishnaShreeji Lifespace400052, Mumbai Suburban31-07-2020 00:00:00
SudeshAnkur Premises Developers LlpG/396/624-02-2021 00:00:00
AaryaRaja BuildersE/67930-12-2021 00:00:00
Jaswant HeightsL Nagpal DevelopersF/16731-12-2018 00:00:00
K Mordani CelynK Mordani Constructions LlpF/9130-04-2021 00:00:00
Rustomjee Paramount - Wing EKeystone Realtors LimitedCts Nos G/626 G/164-A Pt30-11-2020 00:00:00
SpentaSvk Projects LlpCts No E 85531-12-2017 00:00:00
LiliumJayshree BuildersCts No 171 B And 171 C Final Plot No 8230-12-2021 00:00:00
New Laxmi ChhayaParmar And Sm Construction1660, 166131-07-2019 00:00:00
N SquareParthesh Developers Private LimitedF/11831-12-2019 00:00:00
Mantri ParijatPentagon Premises Private LimitedG32131-12-2018 00:00:00
Kismet ChslMidcity Landmarks LlpPlot No 63 Cts No G 43031-12-2019 00:00:00
La MaisonParamvir Real Estates Llp619, 62030-12-2023 00:00:00
NavratnamalaElegant Constructions694627-02-2020 00:00:00
Sheel Apartments By MayfairMayfair Housing Private LimitedFinal Plot Nos 598 And 599 Of Tps Iii 1St Variation Final Bearing Cts No F40 And F41 Of Village Bandra31-12-2024 00:00:00
TritonJade Constructions Private LimitedG/399/D, G/399/E, G/399/C01-07-2025 00:00:00
Khar Yamuna Bhuvan Co.Op.Hsg. Soc. Ltd.Aum AssociatesC.T.S. No. E/21030-03-2019 00:00:00
Unique ElitaAnkur Shubham DevelopersCts No.I/241, I/241/1 To 531-12-2018 00:00:00
Ratnadeep Ankur Premises Developers LlpH 167 E25-05-2022 00:00:00
PremsagarAnkur Premises Developers LlpG/397/315-06-2021 00:00:00
Emerene HeightsRangoli Realtors & DevelopersCts No. H44331-05-2019 00:00:00
Two RosesPrakash EstatesPlot No 5 Cts No F/86631-12-2019 00:00:00
Avenue 54Sumer Radius Realty Pvt Ltd40005431-12-2022 00:00:00
Bhaveshwar Smriti Chs LtdSeasons Bachher Properties40005431-12-2022 00:00:00
Rajkamal Raj ConstructionsF.P. No 91 Of T.P.I. Of Santacruz28-11-2021 00:00:00
M.K HeritageShaista Khan400054, Mumbai Suburban30-12-2022 00:00:00
PlatinaG F Reality Private LimitedE/79831-12-2019 00:00:00
Supreme ElysiaSupreme Mega Constructions Llp415C31-05-2025 00:00:00
PanoramaS Raheja Residency LlpPlot No J-6 Cts No G/428-A31-12-2025 00:00:00
Nine Aces Chs LtdJmj Maxrich Buildcon625/831-12-2023 00:00:00
Khar Hira Premises Co Op Society LtdL Nagpal DevelopersE/25029-02-2024 00:00:00
Pushp-VatikaAnish Shah & Manish ShahCts No E/550 Of Village Bandra - E31-12-2024 00:00:00
52 Park AvenueDan Kutir ChslE/495 Of Village Bandra E31-08-2024 00:00:00
VirajblissVijay Raj EstatesE/86/1831-12-2018 00:00:00
Shapoorji Pallonji The DesignateBehold Space Developers Private LimitedH/463, Mumbai, St Francis Rd30-06-2021 00:00:00
Ekta MaplewoodEkta Housing Private LimitedCts No. G/625/130-06-2018 00:00:00
Om PalaceUmiya BuildersMumbai Suburban, 40005415-07-2020 00:00:00
Pearl PalaceChandiwala Enterprises39/1 To 5, 285, 40/1 To 37, 40, 28430-12-2021 00:00:00
Redevelopment Of The Roopkala Chs LtdOrra Realtors Private Limited400054, Mumbai Suburban31-12-2017 00:00:00
Project Details
  • Project:
    Sequoia
  • Location:
  • C.T.S. No. 624/6 Of Village Bandra
  • Const. Stage:
    New
  • Possession:
    31 Dec 2024
Developer Details

  • Developer:
    Aum Prima Llp
  • Phone:
  • Address:
  • 110 Sidrah
Project RERA Details
MAHA REARA No: P51800032970
Project Type Residential / Group Housing
RERA Project Status New
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 02 Feb 2022
Last Retrived 26 Jul 2025
Sequoia QR Code
Sequoia
MahaRERA - P51800032970
Apartment Details & Configuration
TypeArea
1RK38.75 Sq.mts. ( 417 Sq.ft. )
2 BHK81.95 Sq.mts. ( 882 Sq.ft. )
2 BHK182.56 Sq.mts. ( 1965 Sq.ft. )
3 BHK89.18 Sq.mts. ( 960 Sq.ft. )
3 BHK106.51 Sq.mts. ( 1146 Sq.ft. )
4 BHK119.51 Sq.mts. ( 1286 Sq.ft. )
4 BHK127.12 Sq.mts. ( 1368 Sq.ft. )
4 BHK131.22 Sq.mts. ( 1412 Sq.ft. )
4 BHK241.5 Sq.mts. ( 2600 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sequoialast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Ground /Stilt
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking100% completed
95% Complete
Completed
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Sequoia
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sequoia by Aum Prima Llplast updated on 26 Jul 2025 as per information obtained from MARA RERA.

16119 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

32 apartments in total
Total
32
Booked
22
Available
10

Saleable Area Statistics (Sq. ft.)

43402 Total
Total
43402
Booked
25327
Available
18075
Total 32 apartments in project. 22 apartments booked. 68% apartments booked.
Total 43402 Sq.ft. saleable area. 25327 saleable area booked.
58% area booked.

Sequoia

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
SequoiaDec 20241912101371
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK38.75 Sq.mts. ( 417 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK81.95 Sq.mts. ( 882 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK182.56 Sq.mts. ( 1965 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK89.18 Sq.mts. ( 960 Sq.ft. )9
9 Booked100% Booked
100% Booked
3 BHK106.51 Sq.mts. ( 1146 Sq.ft. )4
1 Booked25% Booked
25% Booked
4 BHK119.51 Sq.mts. ( 1286 Sq.ft. )1
1 Booked100% Booked
100% Booked
4 BHK127.12 Sq.mts. ( 1368 Sq.ft. )7
7 Booked100% Booked
100% Booked
4 BHK131.22 Sq.mts. ( 1412 Sq.ft. )4
1 Booked25% Booked
25% Booked
4 BHK241.5 Sq.mts. ( 2600 Sq.ft. )4
None Booked0% Booked
0% Booked
32 total apartments / 22 apartments booked. 68% apartments booked.
Work Description in Building SequoiaCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Aum Prima Llp
for Project
Sequoia
last updated on 26 Jul 2025 as per information obtained from MARA RERA.