Project overview

Satra Park is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800007235. Satra Park is located at Fp 179. This is a Ongoing being developed by Shreenivas Developers.

Satra Park has 2 BHK, 3 BHK, 4 BHK & 5 BHK Apartments with carpet areas ranging from 1152 to 843 Sq.ft. Carpet. The Project has total 248 of which 0 are currently available for sale.

Satra Park is being developed on a total land area of 178252 Sq.ft. out of which 14726 Sq.ft. i.e 8% is reserved for recreational purposes. Satra Park has 3 Wings / Towers Wing A,Wing B,Wing C

ProjectDeveloperLocationPossession
Om Sarjan ChslGlasswood Realty Private Limited777/9 149A Fp No 680/A/1/231-12-2019 00:00:00
Soham RegencyLaxmikant Ramchandra SawantCts No 195B31-12-2017 00:00:00
Madhuban HeightsWadhwana Housing Development And Infrastructure Co740/4131-08-2018 00:00:00
Sakshat NavkarNavkar Infra ProjectsFinal Plot No 4930-09-2019 00:00:00
Navkar ParadiseNavkar Infra Projects65415-06-2021 00:00:00
Sajag ChsNavkar Infra ProjectsFp No 719/324-06-2019 00:00:00
Target The MallMahendra Jamnadas Kara590/1 To 6 F P No 33, Cts No 59031-12-2017 00:00:00
The ZoneMs Amann Raj Housing And Development CorporationCts No 655, 663, 664, 656Pt, 659, 662, 665Pt31-01-2021 00:00:00
Redevlopment Of Rajendra Nagar - Shree Ganesh Chs Ltd.Kaustubh Construction Private Limited88 Pt31-12-2018 00:00:00
Rite AspireRite Developers Pvt. Ltd.Cts No 4/A30-06-2021 00:00:00
VrindavanRight Channel Construction Pvt LtdCarter Road No 331-12-2017 00:00:00
Kcd RidgewoodKcd Heritage Pvt LtdBorivali, 400092, Mumbai Suburban29-02-2020 00:00:00
Sai Laxmi ChslShreejani Developers136/A 1To6, 136/A31-12-2017 00:00:00
Kaveri HeightsKaveri GoldCts No 607/A30-12-2021 00:00:00
Avenue 641Dimple CreationsFinal Plot No 64130-09-2020 00:00:00
Komal Kounteya ChslRander Bandhu Corporation Llp37030-06-2026 00:00:00
Ashirwad ChslKranvis Realty Llp21901-08-2025 00:00:00
Vir EnclaveJkd Engineers And Infrastructure Private Limited27530-06-2025 00:00:00
Pushp Vinod-3Vas Infrastructure Ltd.Mumbai Suburban, 40009215-12-2015 00:00:00
Paarijat Chs LtdMaan Housing Development94531-12-2018 00:00:00
Modispaces AmazonModispaces Real Estate Pvt LtdFp No. 628 Of Village Borivali31-12-2019 00:00:00
DhanrajAneisha Livings LlpFp No.31128-02-2025 00:00:00
MahirrShree Balaji EnterpriseFinal Plot No -3731-12-2026 00:00:00
Kedar DarshanKosmos Developer275/811-04-2027 00:00:00
Avyukta RajhansShivoham Infrahomes Llp31-A/231-12-2024 00:00:00
Rishabraj RameshwarH Rishabraj Realty275 Part31-08-2024 00:00:00
Manusmruti ChslGoyal Wedevelopment Pvt LtdFp36131-03-2024 00:00:00
Ipsit Anand MangalNavkar Developers111/1 To 17, Cts No 111, Fp No 70 Of Village Kanheri31-12-2027 00:00:00
The Jambli Galli Chs LtdMahavir CorporationsFp No 8331-03-2024 00:00:00
Maya MamtaGreenbuilding Lifescapes Llp15907-10-2025 00:00:00
Soham ResidencyLaxmikant Ramchandra SawantFp-41531-12-2017 00:00:00
Helicon HeightsSahakar Realtors439 - 445 Part30-06-2018 00:00:00
Borivali Ranjee ChsAditya Developers400092, Mumbai Suburban27-12-2018 00:00:00
Fortune Avirahi Wing AFortune ConstructionsPlot No 1 & Cts No 10430-12-2022 00:00:00
Parag - Reserve Co-Op Hsg SocSadguru Buildspacespvt. Ltd.536/C30-12-2020 00:00:00
Redevelopment Of Ulka ChslPranav Constructions LimitedCts No 116 Village Eksar Tps Borivali Iii Fp 32031-12-2019 00:00:00
Adinath ChsAditya Developers400092, Mumbai Suburban22-04-2020 00:00:00
Satra ParkShreenivas DevelopersFp 17930-12-2021 00:00:00
Redevlopment Of Sun And Moon Chs Ltd. Bldg No. 12 And 13Kaustubh Construction Private Limited88 Part31-12-2019 00:00:00
Ananda ResidencyParadigm Ambit BuildconFp No-383, Tps-Iii31-12-2019 00:00:00
SwastikReliance Corporation55 /A30-09-2026 00:00:00
Muktangan ResidencyRaaz Mohammed Abdul Samad Pathan1062 ,1061 ,1061/131-10-2027 00:00:00
Neelkamal HeightsOsho Developers620/1031-12-2017 00:00:00
New Anamika Triveni FortuneTriveni DevelopersMumbai Suburban, 40009230-09-2017 00:00:00
Ankur PalaceOsho Developers719/815-08-2019 00:00:00
Om Satyam Niwas Chs LtdGreenfield Developers & Realtors LlpF. P. No. 680/A/1/3 Of T.P.S. Iii Village Borivali31-07-2020 00:00:00
Dlh KesleyDlh Pansn Developers LlpCts No 4 C31-03-2019 00:00:00
Mahalaxmi Prasad BuildingSudheer Dadarkar565-569-57031-12-2018 00:00:00
Jay KrishnaThe Green Venturez31331-12-2025 00:00:00
Preesha ParadiseVastu Realtors And Developers784, 783, 78231-12-2025 00:00:00
Rishabraj MangaleshRishabraj Infra Llp275A31-12-2026 00:00:00
TreviAshirwad Nice Developers72131-12-2025 00:00:00
New Abhiram Chs LtdPeerless Constructions Pvt. Ltd.62030-06-2025 00:00:00
Garden ViewSmlife Shreeji Developers Llp30-05-2025 00:00:00
Project Details
  • Project:
    Satra Park
  • Location:
  • Fp 179
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Shreenivas Developers
  • Phone:
  • Address:
  • Sagar Complex Chs Ltd
Project RERA Details
MAHA REARA No: P51800007235
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Vivek J Bhole
Funding Bank RBL Bank Limited
Proposed Possession 30 Dec 2021
Revised Possession 30 Dec 2021
Extended Possession
Litigations No Litigations
Last Modified 17 Aug 2017
Last Retrived 26 Jul 2025
Satra Park QR Code
Satra Park
MahaRERA - P51800007235
Apartment Details & Configuration
TypeArea
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )
2 BHK78.32 Sq.mts. ( 843 Sq.ft. )
3 BHK107.02 Sq.mts. ( 1152 Sq.ft. )
3 BHK119.19 Sq.mts. ( 1283 Sq.ft. )
4 BHK146.79 Sq.mts. ( 1580 Sq.ft. )
4 BHK147.25 Sq.mts. ( 1585 Sq.ft. )
4 BHK158.77 Sq.mts. ( 1709 Sq.ft. )
5 bhk208.01 Sq.mts. ( 2239 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Satra Parklast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space50% completed
50% Complete
00
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
0
Energy management90% completed
90% Complete
0
Fire Protection And Fire Safety Requirements100% completed
95% Complete
0
Landscaping & Tree Planting40% completed
40% Complete
0
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
0
Solid Waste Management And Disposal50% completed
50% Complete
0
Storm Water Drains100% completed
95% Complete
0
Street Lighting
Na
SWIMMING POOL75% completed
75% Complete
0
Treatment And Disposal Of Sewage And Sullage Water20% completed
20% Complete
0
Water Conservation, Rain water Harvesting100% completed
95% Complete
0
Water Supply100% completed
95% Complete
0
Buildings / Wings in Satra Park
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Satra Park by Shreenivas Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

178252 Sq. ft.

Project Area

14726 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

248 apartments in total
Total
248
Booked
248
Available
0

Saleable Area Statistics (Sq. ft.)

243239 Total
Total
243239
Booked
243239
Available
0
Total 248 apartments in project. 248 apartments booked. 100% apartments booked.
Total 243239 Sq.ft. saleable area. 243239 saleable area booked.
100% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJan 19001712120157
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )28
28 Booked100% Booked
100% Booked
2 BHK78.32 Sq.mts. ( 843 Sq.ft. )21
21 Booked100% Booked
100% Booked
3 BHK107.02 Sq.mts. ( 1152 Sq.ft. )28
28 Booked100% Booked
100% Booked
3 BHK119.19 Sq.mts. ( 1283 Sq.ft. )2
2 Booked100% Booked
100% Booked
4 BHK146.79 Sq.mts. ( 1580 Sq.ft. )2
2 Booked100% Booked
100% Booked
4 BHK147.25 Sq.mts. ( 1585 Sq.ft. )1
1 Booked100% Booked
100% Booked
4 BHK158.77 Sq.mts. ( 1709 Sq.ft. )1
1 Booked100% Booked
100% Booked
5 bhk208.01 Sq.mts. ( 2239 Sq.ft. )2
2 Booked100% Booked
100% Booked
85 total apartments / 85 apartments booked. 100% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress94% done
94% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress94% done
94% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJan 19001612120145
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )26
26 Booked100% Booked
100% Booked
2 BHK78.32 Sq.mts. ( 843 Sq.ft. )44
44 Booked100% Booked
100% Booked
3 BHK119.19 Sq.mts. ( 1283 Sq.ft. )4
4 Booked100% Booked
100% Booked
4 BHK146.79 Sq.mts. ( 1580 Sq.ft. )2
2 Booked100% Booked
100% Booked
4 BHK147.25 Sq.mts. ( 1585 Sq.ft. )2
2 Booked100% Booked
100% Booked
78 total apartments / 78 apartments booked. 100% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress94% done
94% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress94% done
94% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CJan 19001712120157
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )28
28 Booked100% Booked
100% Booked
2 BHK78.32 Sq.mts. ( 843 Sq.ft. )21
21 Booked100% Booked
100% Booked
3 BHK107.02 Sq.mts. ( 1152 Sq.ft. )28
28 Booked100% Booked
100% Booked
3 BHK119.19 Sq.mts. ( 1283 Sq.ft. )2
2 Booked100% Booked
100% Booked
4 BHK146.79 Sq.mts. ( 1580 Sq.ft. )2
2 Booked100% Booked
100% Booked
4 BHK158.77 Sq.mts. ( 1709 Sq.ft. )2
2 Booked100% Booked
100% Booked
5 BHK208.01 Sq.mts. ( 2239 Sq.ft. )2
2 Booked100% Booked
100% Booked
85 total apartments / 85 apartments booked. 100% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress91% done
91% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress91% done
91% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shreenivas Developers
for Project
Satra Park
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation