Project overview

Sarita Apartment is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700030296. Sarita Apartment is located at 76/1070. This is a New being developed by Shivansh Vaishnavi Constraction.

Sarita Apartment has 1 BHK & 1RK Apartments with carpet areas ranging from 133 to 196 Sq.ft. Carpet. The Project has total 17 of which 11 are currently available for sale.

Sarita Apartment is being developed on a total land area of 2336 Sq.ft. out of which 5629 Sq.ft. i.e 241% is reserved for recreational purposes. Sarita Apartment has 1 Wings / Towers Sarita Apartment

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sarita Apartment
  • Location:
  • 76/1070
  • Const. Stage:
    New
  • Possession:
    31 Oct 2022
Developer Details

  • Developer:
    Shivansh Vaishnavi Constraction
  • Phone:
  • Address:
  • Building No 2/E3 Phash 3 Mohan Tulsi Vihar
Project RERA Details
MAHA REARA No: P51700030296
Project Type Residential / Group Housing
RERA Project Status New
Architect Kamlesh Sutar
Funding Bank TJSB SAHAKARI BANK LTD
Proposed Possession 31 Oct 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 24 Jan 2023
Last Retrived 26 Jul 2025
Sarita Apartment QR Code
Sarita Apartment
MahaRERA - P51700030296
Apartment Details & Configuration
TypeArea
1 BHK18.23 Sq.mts. ( 196 Sq.ft. )
1RK12.32 Sq.mts. ( 133 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sarita Apartmentlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space50% completed
50% Complete
Old Home
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
Electricity Metter
Energy management50% completed
50% Complete
Solar Penal
Fire Protection And Fire Safety Requirements50% completed
50% Complete
Fire Wire Pump
Landscaping & Tree Planting50% completed
50% Complete
Plantation
Open Parking50% completed
50% Complete
Parking
Sewerage (Chamber, Lines, Septic Tank , STP)80% completed
80% Complete
Sewwrage
Solid Waste Management And Disposal50% completed
50% Complete
Disposal
Storm Water Drains
Na
Street Lighting100% completed
95% Complete
Street Light
Treatment And Disposal Of Sewage And Sullage Water50% completed
50% Complete
Pipe Line
Water Conservation, Rain water Harvesting50% completed
50% Complete
Pipe Line
Water Supply100% completed
95% Complete
Pipe Line
Buildings / Wings in Sarita Apartment
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sarita Apartment by Shivansh Vaishnavi Constractionlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

2336 Sq. ft.

Project Area

5629 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

17 apartments in total
Total
17
Booked
6
Available
11

Saleable Area Statistics (Sq. ft.)

3018 Total
Total
3018
Booked
859
Available
2159
Total 17 apartments in project. 6 apartments booked. 35% apartments booked.
Total 3018 Sq.ft. saleable area. 859 saleable area booked.
28% area booked.

Sarita Apartment

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sarita ApartmentOct 20227100050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK18.23 Sq.mts. ( 196 Sq.ft. )12
1RK12.32 Sq.mts. ( 133 Sq.ft. )5
5 Booked100% Booked
100% Booked
17 total apartments / 6 apartments booked. 35% apartments booked.
Work Description in Building Sarita ApartmentCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Shivansh Vaishnavi Constraction
for Project
Sarita Apartment
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation