Project overview
Samarth Sai Residency is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000035137. Samarth Sai Residency is located at Palghar. This is a New Project being developed by Vijay Pimple.
Samarth Sai Residency has 1 BHK & 2 BHK Apartments with carpet areas ranging from 626 to 1033 Sq.ft. Carpet. The Project has total 38 of which 38 are currently available for sale.
Samarth Sai Residency is being developed on a total land area of 13584 Sq.ft. Samarth Sai Residency has 1 Wings / Towers Samarth Sai Residency
| Project | Developer | Location | Possession |
-
Project:
Samarth Sai Residency
-
Location:
-
Palghar
-
Const. Stage:
New Project
-
Possession:
31 Mar 2026
-
Developer:
Vijay Pimple
-
Phone:
-
Address:
-
38, Ground Floor, Yashwant Plaza, Navapur Naka, Boisar, Boisar, 401501
| MAHA REARA No: |
P99000035137 |
| Project Type |
Residential |
| RERA Project Status |
New Project |
| Funding Bank |
IDBI BANK |
| Proposed Possession |
31 Mar 2026 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
06 May 2022 |
| Last Retrived |
28 Jul 2025 |
Samarth Sai Residency QR Code
Samarth Sai Residency
MahaRERA - P99000035137
| Type | Area |
| 1 BHK | 58.15 Sq.mts. ( 626 Sq.ft. ) |
| 1 BHK | 64.73 Sq.mts. ( 697 Sq.ft. ) |
| 2 BHK | 78.5 Sq.mts. ( 845 Sq.ft. ) |
| 2 BHK | 83.54 Sq.mts. ( 899 Sq.ft. ) |
| 2 BHK | 85.4 Sq.mts. ( 919 Sq.ft. ) |
| 2 BHK | 90.65 Sq.mts. ( 976 Sq.ft. ) |
| 2 BHK | 91.72 Sq.mts. ( 987 Sq.ft. ) |
| 2 BHK | 96 Sq.mts. ( 1033 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Samarth Sai Residencylast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Work Not Start |
|
|
|
Work Not Start |
Fire Protection And Fire Safety
Requirements
|
|
Work Not Start |
Landscaping & Tree Planting
|
|
Work Not Start |
|
|
|
Work Not Start |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
Work Not Start |
Solid Waste Management And Disposal
|
|
Work Not Start |
|
|
|
Work Not Start |
|
|
|
Work Not Start |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Work Not Start |
Water Conservation, Rain water Harvesting
|
|
Work Not Start |
|
|
|
Work Not Start |
Buildings / Wings in Samarth Sai Residency
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Samarth Sai Residency by Vijay Pimplelast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
38
apartments in total
Saleable Area Statistics (Sq. ft.)
33787
Total
Total 38 apartments in project. 0 apartments booked. 0% apartments booked.
Total 33787 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Samarth Sai Residency | Mar 2026 | 6 | 1 | 0 | 1 | 0 | 0 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 58.15 Sq.mts. ( 626 Sq.ft. ) | 4 | |
| 1 BHK | 64.73 Sq.mts. ( 697 Sq.ft. ) | 4 | |
| 2 BHK | 78.5 Sq.mts. ( 845 Sq.ft. ) | 4 | |
| 2 BHK | 83.54 Sq.mts. ( 899 Sq.ft. ) | 4 | |
| 2 BHK | 85.4 Sq.mts. ( 919 Sq.ft. ) | 6 | |
| 2 BHK | 90.65 Sq.mts. ( 976 Sq.ft. ) | 6 | |
| 2 BHK | 91.72 Sq.mts. ( 987 Sq.ft. ) | 4 | |
| 2 BHK | 96 Sq.mts. ( 1033 Sq.ft. ) | 6 | |
38 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Samarth Sai Residency | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Vijay Pimple
for Project
Samarth Sai Residency
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |