Project overview

Sai Nirvana is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700003913. Sai Nirvana is located at 1537 To 1547 . This is a Ongoing being developed by Shanklesha Constructions.

Sai Nirvana has 1 BHK, 2 BHK, 2 BHKPREMIUM & COMMERCIAL Apartments with carpet areas ranging from 14797 to 9093 Sq.ft. Carpet. The Project has total 780 of which 12 are currently available for sale.

Sai Nirvana is being developed on a total land area of 104648 Sq.ft. out of which 10002 Sq.ft. i.e 10% is reserved for recreational purposes. Sai Nirvana has 3 Wings / Towers Building 1 Mmrda Rental,Building 2,Building 3

ProjectDeveloperLocationPossession
Anand HomesShrinath DevelopersS. No. 40 H.No. 1 /H Plot No. 10, S.No. 40 H.No. 1/G Plot No. 930-12-2020 00:00:00
Sarvoday Patwardhan BaugSarvoday DeveloperS No 35 Hissa No 2/1 2/2A 2/2C 2/3 2/4 2/531-01-2021 00:00:00
Diwadkar LotusHonest Infra2878 A31-12-2019 00:00:00
Tycoons Valley Tower AM/S. Milestone SpaceS.No. 1, H.No. 2 30-06-2020 00:00:00
Tulsi SamarthShree Krupa EnterprisesSurvey No. 47 Hissa No. 330-12-2021 00:00:00
V Ten ResidencyV Ten Realty Private LimitedSurvey No 105 Hissa No 1 Village Chikanghar Kalyan 30-12-2020 00:00:00
Al-Nashra HeightsUnique Builders And DevelopersS.No.295/131-01-2021 00:00:00
Mangeshi FloraOm Realty123 7 2 123 231-03-2019 00:00:00
Shrushti AvenueKishore DesaiThane, 42130131-12-2017 00:00:00
Mahaveer Heavens Phase IiMahaveer Infrastructure Pvt Ltd29/11, 29/12P30-12-2023 00:00:00
MannatJayshree BuildersCts No 323, 33630-12-2021 00:00:00
Atlantic OrraAtlantic Winds Infrastructure Pvt.Ltd.41 Pt27-02-2019 00:00:00
Vardhaman ParkVardhaman DevelopersSn Cts 84230-12-2021 00:00:00
Kashi DarshanVaraj Raj ConstructionThane, 42130119-05-2019 00:00:00
Tulsi TowerShri Kalki EnterprisesS. No 20, H.No 1230-09-2020 00:00:00
Atrinandan HeightsHeramb ConstructionS.No- 40, Plot No-1230-12-2022 00:00:00
Kohinoor MajesticSonu Anilkumar Hotchandani55/1/A/1, 55/3/A/1/A30-12-2023 00:00:00
Sky Villas Wing A1 And Wing A2Vertex Newton Projects Private LimitedPlot B Of Sanctioned Layout On Survey Nos 43/3 P, 66/1,66/6, 67/1,68, 69,73/1, 73/2,74 P30-05-2023 00:00:00
Commercial-1S M Associates421301, Thane30-06-2018 00:00:00
Sai Sharnam- Tybe BAnjana Sahebrao ChavanSurvey No. 10, Hissa No. 130-06-2021 00:00:00
New Shivneri Darshan Co. Operative Housing Society LimitedGlobal Housing Venture962P17-07-2021 00:00:00
Sky HeightsSpace BuildconCts No 3380, Village Kalyan30-12-2025 00:00:00
Commercial-2S M Associates421301, Thane30-06-2018 00:00:00
Sawlaram SrushtiShree Sai Builders And DevelopersSurvey 34/1 Hissa No 1/1131-12-2017 00:00:00
Godown-AS M AssociatesThane, 42130130-06-2018 00:00:00
Shree Swami Pushpa Phase-1 Shelar ParkShelar Developers42/1,42/731-12-2019 00:00:00
Neelkanth ShrushtiAshapura CombinesSurvey No 86,88,9030-12-2021 00:00:00
Shree Sai DarshanShree Siddhivinayak Builders & DevelopersS No 342 Old 79 New31-03-2018 00:00:00
Royce Paradise Phase IiRoyce Developers11/2A, 12/3A, 13/231-12-2019 00:00:00
Girnar TirthParshwa AssociatesSurvey No77 And 23630-06-2019 00:00:00
DhundirajHeramb Construction832 To 842 And 85131-12-2018 00:00:00
Kohinoor LifestyleSonu Anil Hotchandani5/130-12-2020 00:00:00
Mohan SkyvilleMohan Lifespaces Llp9/4/2,9/5/1,9/5/2,15/16/1,15/6/2,17/2/6,17/3,18/2/1,23/2/1,62/130-06-2019 00:00:00
White Square Nx Wing A,C,DShri Ram Sthapatya2831,2832/A,2832/B/1,2834/A/1,283531-12-2028 00:00:00
Sarvoday DattSarvoday Combine86/3 & 87/231-12-2027 00:00:00
Vishwanath DarshanAshapura CombinesSurvey No 91 Hissa No 831-12-2029 00:00:00
Tulsi ArianaTulsi RealtySurvey No. 26, Hissa No.1/2A30-12-2027 00:00:00
Sai Sharada Chs LtdM Square DevelopersSr No. 87 H.No 9 Plot No- 2731-05-2026 00:00:00
White SquareShri Raghuveer SthapatyaCiti Survey No. 2837,2838,283931-12-2027 00:00:00
BileshwarAshapura CombinesSurvey No 89 Hissa No 1,2,3 & 5 Survey No 90 Hissa No 531-12-2028 00:00:00
Manovi UptownManovi UptownCts No.2338/B/2, (Old Cts No. 2338/B Pt)23-04-2027 00:00:00
Art ShreeArt EnterprisesC.T.S. No- 688B31-03-2026 00:00:00
Mangeshi TulipMangesh GaikarThane30-07-2026 00:00:00
Anand 21 UptownVpa DevelopersS. No 70 H. No. 1/1, S. No. 70 H. No. 1/B/1 (Old S. No. 70 H. No. 1/2 (P)31-08-2026 00:00:00
Project Details
  • Project:
    Sai Nirvana
  • Location:
  • 1537 To 1547
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Shanklesha Constructions
  • Phone:
  • Address:
  • Sainirvana
Project RERA Details
MAHA REARA No: P51700003913
Project Type Others
RERA Project Status Ongoing
Architect Bhupendra Patrawala
Funding Bank ICICI BANK LIMITED
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession 31 Mar 2024
Litigations No Litigations
Last Modified 21 Nov 2023
Last Retrived 26 Jul 2025
Sai Nirvana QR Code
Sai Nirvana
MahaRERA - P51700003913
Apartment Details & Configuration
TypeArea
1 RHK4929.6 Sq.mts. ( 53062 Sq.ft. )
1 BHK3836.4 Sq.mts. ( 41295 Sq.ft. )
2 BHK6873.55 Sq.mts. ( 73987 Sq.ft. )
3 BHK3828.3 Sq.mts. ( 41208 Sq.ft. )
COMMERCIAL1551.84 Sq.mts. ( 16704 Sq.ft. )
1 BHK767.28 Sq.mts. ( 8259 Sq.ft. )
2 BHK1374.71 Sq.mts. ( 14797 Sq.ft. )
2 BHKPREMIUM2547.72 Sq.mts. ( 27424 Sq.ft. )
COMMERCIAL844.8 Sq.mts. ( 9093 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sai Nirvanalast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
In Process
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
In Process
Energy management
In Process
Fire Protection And Fire Safety Requirements
In Process
Landscaping & Tree Planting
In Process
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
In Process
Solid Waste Management And Disposal
In Process
Storm Water Drains
In Process
Street Lighting
In Process
Treatment And Disposal Of Sewage And Sullage Water
In Process
Water Conservation, Rain water Harvesting
In Process
Water Supply
In Process
Buildings / Wings in Sai Nirvana
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sai Nirvana by Shanklesha Constructionslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

104648 Sq. ft.

Project Area

10002 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

780 apartments in total
Total
780
Booked
768
Available
12

Saleable Area Statistics (Sq. ft.)

34817417 Total
Total
34817417
Booked
34655021
Available
162395
Total 780 apartments in project. 768 apartments booked. 98% apartments booked.
Total 34817417 Sq.ft. saleable area. 34655021 saleable area booked.
100% area booked.

Building 1 Mmrda Rental

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 1 Mmrda RentalJun 202123101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 RHK4929.6 Sq.mts. ( 53062 Sq.ft. )316
316 Booked100% Booked
100% Booked
316 total apartments / 316 apartments booked. 100% apartments booked.
Work Description in Building Building 1 Mmrda RentalCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 2Jun 20213110060307
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK3836.4 Sq.mts. ( 41295 Sq.ft. )115
115 Booked100% Booked
100% Booked
2 BHK6873.55 Sq.mts. ( 73987 Sq.ft. )115
115 Booked100% Booked
100% Booked
3 BHK3828.3 Sq.mts. ( 41208 Sq.ft. )42
42 Booked100% Booked
100% Booked
COMMERCIAL1551.84 Sq.mts. ( 16704 Sq.ft. )57
50 Booked87% Booked
87% Booked
329 total apartments / 322 apartments booked. 97% apartments booked.
Work Description in Building Building 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 3Jun 2021311006072
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK767.28 Sq.mts. ( 8259 Sq.ft. )23
23 Booked100% Booked
100% Booked
2 BHK1374.71 Sq.mts. ( 14797 Sq.ft. )23
23 Booked100% Booked
100% Booked
2 BHKPREMIUM2547.72 Sq.mts. ( 27424 Sq.ft. )42
42 Booked100% Booked
100% Booked
COMMERCIAL844.8 Sq.mts. ( 9093 Sq.ft. )47
42 Booked89% Booked
89% Booked
135 total apartments / 130 apartments booked. 96% apartments booked.
Work Description in Building Building 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shanklesha Constructions
for Project
Sai Nirvana
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation