Project overview

Sai Nagar is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000006133. Sai Nagar is located at 1271B. This is a Ongoing being developed by Shubhvastu Realcon.

Sai Nagar has 1 BHK Apartments with carpet areas ranging from 228 to 300 Sq.ft. Carpet. The Project has total 150 of which 109 are currently available for sale.

Sai Nagar is being developed on a total land area of 13581 Sq.ft. out of which 12206 Sq.ft. i.e 90% is reserved for recreational purposes. Sai Nagar has 6 Wings / Towers Sai Nagar Bldg 2 Wing C Proposed,Sai Nagar Bldg No 2 Wing A Proposed,Sai Nagar Bldg No 2 Wing C,Sai Nagar Bldg No1 Wing A,Sai Nagar Bldg No1 Wing A Proposed,Sai Nagar Bldg No2 Wing A

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sai Nagar
  • Location:
  • 1271B
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2022
Developer Details

  • Developer:
    Shubhvastu Realcon
  • Phone:
  • Address:
  • Sai Nagar
Project RERA Details
MAHA REARA No: P99000006133
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Shape Consultants
Funding Bank HDFC BANK
Proposed Possession 30 Jun 2022
Revised Possession 30 Jun 2022
Extended Possession 31 Mar 2026
Litigations No Litigations
Last Modified 08 Jun 2023
Last Retrived 28 Jul 2025
Sai Nagar QR Code
Sai Nagar
MahaRERA - P99000006133
Apartment Details & Configuration
TypeArea
1 BHK23.53 Sq.mts. ( 253 Sq.ft. )
1 BHK25.57 Sq.mts. ( 275 Sq.ft. )
1 BHK23.47 Sq.mts. ( 253 Sq.ft. )
1 RK20.54 Sq.mts. ( 221 Sq.ft. )
1 BHK25.58 Sq.mts. ( 275 Sq.ft. )
1 BHK25.74 Sq.mts. ( 277 Sq.ft. )
1 BHK27.57 Sq.mts. ( 297 Sq.ft. )
1 BHK27.58 Sq.mts. ( 297 Sq.ft. )
1 BHK27.84 Sq.mts. ( 300 Sq.ft. )
1 BHK21.19 Sq.mts. ( 228 Sq.ft. )
1 BHK26.48 Sq.mts. ( 285 Sq.ft. )
1 BHK27.07 Sq.mts. ( 291 Sq.ft. )
1 BHK27.7 Sq.mts. ( 298 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sai Nagarlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Not Started
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
As Per Msedcl
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Tree Planting
Open Parking12% completed
12% Complete
In Open Space
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Not Started
Street Lighting
In Open Area
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting50% completed
50% Complete
Rain Water Harvesting
Water Supply
Bore Well/ Municipal Water
Buildings / Wings in Sai Nagar
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sai Nagar by Shubhvastu Realconlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

13581 Sq. ft.

Project Area

12206 Sq. ft.

Recreational Open Space

Total 6

Wings / Towers in Project

Apartments Statistics

150 apartments in total
Total
150
Booked
41
Available
109

Saleable Area Statistics (Sq. ft.)

41799 Total
Total
41799
Booked
12077
Available
29722
Total 150 apartments in project. 41 apartments booked. 27% apartments booked.
Total 41799 Sq.ft. saleable area. 12077 saleable area booked.
29% area booked.

Sai Nagar Bldg 2 Wing C Proposed

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sai Nagar Bldg 2 Wing C ProposedJan 19003000010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.53 Sq.mts. ( 253 Sq.ft. )8
None Booked0% Booked
0% Booked
1 BHK25.57 Sq.mts. ( 275 Sq.ft. )15
None Booked0% Booked
0% Booked
23 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Sai Nagar Bldg 2 Wing C ProposedCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress35% done
35% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress30% done
30% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress20% done
20% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress20% done
20% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress30% done
30% Booked

Sai Nagar Bldg No 2 Wing A Proposed

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sai Nagar Bldg No 2 Wing A ProposedJan 19002000020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.47 Sq.mts. ( 253 Sq.ft. )15
None Booked0% Booked
0% Booked
1 BHK23.53 Sq.mts. ( 253 Sq.ft. )7
None Booked0% Booked
0% Booked
1 RK20.54 Sq.mts. ( 221 Sq.ft. )1
None Booked0% Booked
0% Booked
23 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Sai Nagar Bldg No 2 Wing A ProposedCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress20% done
20% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress41% done
41% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress50% done
50% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress50% done
50% Booked

Sai Nagar Bldg No 2 Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sai Nagar Bldg No 2 Wing CJun 20224101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK25.57 Sq.mts. ( 275 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK25.58 Sq.mts. ( 275 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK25.74 Sq.mts. ( 277 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK27.57 Sq.mts. ( 297 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK27.58 Sq.mts. ( 297 Sq.ft. )13
6 Booked46% Booked
46% Booked
1 BHK27.84 Sq.mts. ( 300 Sq.ft. )9
5 Booked55% Booked
55% Booked
27 total apartments / 12 apartments booked. 44% apartments booked.
Work Description in Building Sai Nagar Bldg No 2 Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress38% done
38% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress40% done
40% Booked

Sai Nagar Bldg No1 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sai Nagar Bldg No1 Wing AJun 20224101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK25.57 Sq.mts. ( 275 Sq.ft. )6
4 Booked66% Booked
66% Booked
1 BHK25.74 Sq.mts. ( 277 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK27.58 Sq.mts. ( 297 Sq.ft. )11
5 Booked45% Booked
45% Booked
1 BHK27.84 Sq.mts. ( 300 Sq.ft. )8
5 Booked62% Booked
62% Booked
27 total apartments / 15 apartments booked. 55% apartments booked.
Work Description in Building Sai Nagar Bldg No1 Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress30% done
30% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress80% done
80% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress61% done
61% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Sai Nagar Bldg No1 Wing A Proposed

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sai Nagar Bldg No1 Wing A ProposedJan 19003000020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.53 Sq.mts. ( 253 Sq.ft. )8
None Booked0% Booked
0% Booked
1 BHK25.57 Sq.mts. ( 275 Sq.ft. )15
None Booked0% Booked
0% Booked
23 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Sai Nagar Bldg No1 Wing A ProposedCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress35% done
35% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress30% done
30% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress20% done
20% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress20% done
20% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress30% done
30% Booked

Sai Nagar Bldg No2 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sai Nagar Bldg No2 Wing AJun 20224101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK21.19 Sq.mts. ( 228 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK26.48 Sq.mts. ( 285 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK27.07 Sq.mts. ( 291 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK27.57 Sq.mts. ( 297 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK27.58 Sq.mts. ( 297 Sq.ft. )13
6 Booked46% Booked
46% Booked
1 BHK27.7 Sq.mts. ( 298 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK27.84 Sq.mts. ( 300 Sq.ft. )6
5 Booked83% Booked
83% Booked
27 total apartments / 14 apartments booked. 51% apartments booked.
Work Description in Building Sai Nagar Bldg No2 Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress30% done
30% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress60% done
60% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress60% done
60% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress59% done
59% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shubhvastu Realcon
for Project
Sai Nagar
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation