Project overview

Sai Leela is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800001249. Sai Leela is located at Nd5di1flbwwkk6lmyzq9gejbr2zbilecetr7bxfwtta=. This is a Ongoing being developed by Laxmi Associates.

Sai Leela has 1 BHK & 2 BHK Apartments with carpet areas ranging from 389 to 520 Sq.ft. Carpet. The Project has total 118 of which 36 are currently available for sale.

Sai Leela is being developed on a total land area of 19895 Sq.ft. Sai Leela has 3 Wings / Towers Wing A,Wing B,Wing C

ProjectDeveloperLocationPossession
A And O EminenteAshapura Housing Private Limited400068, Mumbai Suburban31-12-2021 00:00:00
Radha Madhav ChslShri Krishna Chaitanya EnterprisesO0z0ympgvzxvjzjjgelmag==30-09-2018 00:00:00
Shri Vallabh ResidencySwadhinta Builders Llp Jczarsl8c7udhn7qenl3gg==26-01-2022 00:00:00
Earth Residency Wing C And Wing DEarth Estate Developers Pvt LtdXtsoxab6il0puhllpa6imfrqh0ox3mhpi0ypuo5mzuo=28-08-2023 00:00:00
Teenmurty SummitM/S Teenmurty Summit Realty LlpGrfcearg0ccbsjh6uq9tyq==31-07-2022 00:00:00
Elite TowerElite Construction Co.400066, Mumbai Suburban31-07-2023 00:00:00
Park ResidencyPavan Sheth And Associates AopXoj/Gibvapoivyeyq/Ibag==31-01-2021 00:00:00
AudumbarVas Builder & DevelopersPcuw76gswj5x90+Itralbq==31-12-2019 00:00:00
New Mahavir Darshan ChslLmp GroupDqltll1zwvx7hll9jf3iyidldna/Wta2i9nya1pon18=31-03-2018 00:00:00
Dahisar Sunderbaug Co-Op Housing Society Ltd.Rishabraj Estate Developers Pvt LtdG+T3hid0q2omtwcqg5azjg==31-12-2018 00:00:00
Sbies Geetanjali ChslB.Chopda Construction Pvt LtdLckcgcqmbparsf1jzx7mgfamelsmv9w1xcqhvfffvx/Tanq6q7i/Gxys4lldpbco31-07-2019 00:00:00
Modispaces TashkentModispaces Real Estate Pvt LtdYfbt2v2+Zw8ldlb1mtgkb1htavo5xztnycqkrxnxeyowsfgsabv4xktjdqtkapfl31-12-2018 00:00:00
Sanghvi SolitaireSanghvi Premises Private LimitedB9by6wvbspdk78uxd4oadb6jxncwzd6nlpxqmg1vsasne5wure4nxwqybgiseencxaljlznhxydhtncdxlfxmg==31-12-2018 00:00:00
Borivali Dipti Co-Op Hsg LtdShree Riddhi Siddhi Builders5Kcjwvvj0mycheijvcuytw==30-06-2019 00:00:00
Construction Of 86 Tenements Out Of 430 Mig Tenements Of Old Magathane Village BorivaliMaharashtra Housing And Area Development AuthorityOcgdge9ht4td5mxkhccrrffwlzq7dnqyab0aes/Q2ozkmkq/Q9aq9y+Ala+0Kcuznv3txq/Gz/Hnawhmns7wxrs5ugr+Xdanl+Lyzz14omo=13-12-2018 00:00:00
Shree Rasraj TowerK Mehta And CompanyLuvuyk/Jqlhlnztoutdzwpjdjzrgfbpmnzwkilrvxfo=31-12-2019 00:00:00
Patel Associates A/C New BelevuePatel Associates A/C New BelevueJgqwsvdbeckgk0lyaema/Hkavmpa7eahpxtvpefu8bx0xpg5u6coq0z710szxsco30-06-2021 00:00:00
Jaliyan Heights BorivaliJaliyan DeveloperZvrh1qbalumgdtvmnscbw4l3kvskiwgkpkvcjgkgekvqnmhbo8sj+Iijubbguzkcetaubsxy+7Tiocdjzdpjbwl4kqe3swa0b61cpa2j03mih6rvemzow1xgrqgfidfq30-07-2021 00:00:00
Sheth MidoriSheth Infraworld Private LimitedOkam1t/0Aonvmif01v+Nstpjpyiplqzsyvrxvmeyrjuolkhmeci8lpc+6Rm8ob4ojtkrn439occiucvtoqcazq==31-05-2019 00:00:00
Navkar AtlantisNavkar Lifespaces Private LimitedDaulat Nagar30-11-2017 00:00:00
Rang Tarang Co Op Hsg Society LtdRang Tarang Chs LtdAmbjcitnswd+Lm5/Jndwh34qk3gt9rxnv3pa28fysje=31-12-2027 00:00:00
Borivali Sai Smruti Cooperative Housing Society LimitedM/S Sapphire DevelopersPjdbpdmmwy+Af+P0pvgtpg==30-06-2027 00:00:00
KarmyogKrishnir Realtors And Developers400066, Mumbai Suburban31-03-2020 00:00:00
Sai ParadiseSai Universal Realtors &Amp; Developers LlpMumbai Suburban, 40006631-12-2017 00:00:00
SHAMBHAV DARSHANAAVISHKAR ENTERPRISESMumbai Suburban, 40006630-06-2020 00:00:00
Shiv Shreyas ChslK P Developers5Iqaxualf2+Aqinrkuqn0w==31-12-2025 00:00:00
MatruchhayaM/S. Rishabraj Balaji Infra4Nryghkl7ay2lymlylwjmk90afaeolskboeyjeyslto=31-12-2024 00:00:00
SaraswatiKarmvir Saraswati Developers LlpMd9jhtjruxzotosqfkse/Pxwj6mtuudi1wgdheqv7oujgaec0kzopzzr8lls+Mkorlf3k1yotjmryml2bes6vkmdxvxorwsy05y7pqzfrgy=24-12-2024 00:00:00
Borivali Sagar ChslMahavir InfraprojectsRvilfikjc2fuqzvsgpmy4jddv6e1pusxiabc7a0kljo=31-03-2026 00:00:00
Sianna HeightsShubhjivan Builders Pvt LtdNgq5nsxzibi9svo14iy+Plfwtcvbillgj3s5vdely2q=31-08-2025 00:00:00
Harsiddhi Sadan Chs LtdRk ConstructionS78jumgciz8wvvdk/Knb9g==30-06-2025 00:00:00
Redevelopment Of Sanjog Chs LtdHeritage Lifestyles Llp/Ikowek2dbvaql5hqj2lz/Qspk+9P0xbk8qb+Xbywpg=31-12-2018 00:00:00
Dahisar Manisha Chs LtdMitnetra EnterpriseRteuk/Runtdkn2ugnw5fah5o1lyhgzyhh8ghe1u4x6u=31-12-2019 00:00:00
Sai LeelaLaxmi AssociatesNd5di1flbwwkk6lmyzq9gejbr2zbilecetr7bxfwtta=31-12-2019 00:00:00
RudranshSpa Jain Real Estate Private LimitedSc6eervygpcpzn0wrgjgqsmxrjewl+Mvrisslpyn3jfxokraqd4xax75eqefkfe7eobutenrh/Dlnus50d4h0w==31-12-2017 00:00:00
TatvaGitanjali Infratech LimitedKjjrtbbk1zxykfe1mjze2g==31-12-2018 00:00:00
Signature-IChaubey Realties Private LimitedX55qh06rr/7T32aebc1mvzvad/Ifg3vgiwtpho8ezdxtyp6qb20gbrhcnm2i5wfl31-12-2021 00:00:00
Redevelopment Of Pravesh ChslPranav Constructions Limited3Qiuiewmyauz2kchqfwrbw==28-11-2023 00:00:00
Rishabraj DivineM/S. Rishabraj Balaji InfraXkuymijzql9eazxs1z8af3av/Djrdvdd0oqifou2wow=30-10-2023 00:00:00
Sankeshwar DarshanM/S. Rishabraj Balaji InfraHml/Ukassvrc4m8vgxyxwb+1Jcvjgt/C0e1tno1ax3kjnk7ljdstiipkjbnbwcsj30-10-2023 00:00:00
The Konark RiseKonark Rajendra ShahW4eokwe5+Wczcufswo4adq==31-03-2026 00:00:00
101 BoulevardH M DevelopersTtu4s9tpp4kmo9yguwtnwy16pxwxz6ngzacs7q//Rvi=30-06-2026 00:00:00
Maruti ResidencyOm ConstructionOxvxfxyhxgjlystdie3wyq==30-06-2025 00:00:00
Redevelopment Of Kripadham Chs LtdKripa Realtors1M4cfoxrxtkt5jchqrwaiw==31-12-2017 00:00:00
Redevelopment Of Divya Jyoti Co-Operative Housing Society LimitedD V Developers LlpL3spzeb+Zvatb1hur7ngj+P2wq/Yimsevqkxkm5yvcln5xuhcf8hlq5id2jsksxd30-12-2021 00:00:00
Kumbhavati NiwasKrishna Bhooraram PurohitYihyirnweznf9urs+Pu7wg==30-12-2021 00:00:00
Star PlazaSevenstar DevelopersF6xphjuncphfjzxqd+6Hz/Vxm9itdvnxtprlkemoeqcc4btjimirxf8yjwgy9b4b30-12-2022 00:00:00
Ratna Mohan Triveni ChslAtul CorporatesJnhmh5e4ympnz5gavbhboa==31-12-2018 00:00:00
Marina Enclave Wing J,K,L Phase -IGurukrupa Developers D N Nagar ProjectCfk3y9bdoaz6tuvoy8xdow==30-12-2020 00:00:00
Sbi Employees Prashant ChsAditya Developers40006618-05-2020 00:00:00
Shree KrishnaShakuntala BhoirMumbai Suburban, 40006831-12-2018 00:00:00
Torna ApartmentRajmudra Construction Pvt LtdAut5gqneeycjdpptus+Okg==31-01-2018 00:00:00
Megha Edge- Red RoseMegha Lakshmi Enterprise2O4emi/Akbdqselsfgyela==30-09-2025 00:00:00
Chheda BhuvanHaresh Popatlal ChhedaCy1i2wq+Tnazjgkeaqkerfzafl6ml60ot8ogltexdos=31-12-2026 00:00:00
Jeevan Shobha Chsl And Bhansali ChslHirani Realtors LlpLcqgtjx96jfxdn5jo/Gvshixynoclxrsrvveqf2oqeeeb54ktsyl+Gbwdq6av+Lc31-03-2026 00:00:00
Unicorn HeightsTeoama Infrastructure Private LimitedGglw2u/3Pcwcznlspaomnhlcxcqw/Uflnnlwz8z3nle=30-06-2025 00:00:00
Borivali New Roma Sadan ChslSumukh InfraprojectJptqfcg0uvxkt5+Qgqxbzq==30-06-2023 00:00:00
Arkade CrownArkade Developers Private LimitedPrvor++El1fudpo1y6md/Q==31-12-2025 00:00:00
GrandnessM/S Om Saath Realties LlpZupuporpcklmp5rpef0kj6lwvre8d/7V6ueiinkmehm=30-12-2022 00:00:00
Gaurishankar Bungalow RedevelopmentS S RealityCxx7mwdgi/Yyz+Jlzmfnpa==31-12-2019 00:00:00
Nishchay - Wing EShreeraj Developer LlpRqey4x9ui6rbj3kh1o4vmg==30-12-2024 00:00:00
PavapuriKum Kum EnterprisesQo7ap3oumpaoxijoh2l+0Q==31-12-2026 00:00:00
Gurukrupa SharanamGurukrupa Realcon Lifespaces LlpU7z3ilzlt/U2/Qrbhpqt/Bpj3tmjqwzjvy05lgngqnovfr4qmyqfnfbafknhldzsp4x4c42u/Kdgqkbapkxmsertk+Ifdztncot0m6ezlf0=31-12-2026 00:00:00
Navkar HeightsNavkar Groups Private LimitedI4ofuppchnguavuysj8khq==30-12-2021 00:00:00
Maa EnrichDhanish Jitendra ShahA/Xsd5ynqsaqjazt0y+Yjg==31-05-2018 00:00:00
Modirealty AcaciaModirealty Developers Pvt Ltd6Riqfb0z2cysh2hhtq1tpwmtfoaykrageqmaqyqiubk=31-03-2028 00:00:00
Sbi Ragvihar ChsTuvin Consultancy Llp/Pnegt/5Coplf0ogc2d4za==10-12-2020 00:00:00
Swayambhu ResidencyYogiraj Builders And DevelopersPakuzzrfu5fdq+9Iyqd33w==30-09-2021 00:00:00
Aakasha ChslTrivenidevelopersUq5bj6szn8+Fp7aswv0twa==31-12-2017 00:00:00
Sai JharokhaSwastik SpaceHwlqchars7kzj8vhhr3zxw==30-09-2017 00:00:00
Parmarth Niketan - Redevelopment Of Mani BhuvanJ V Constructions & DevelopersJ6dguqag5bty4najjzysdvptuaexypzy5bloetwwd80=31-12-2019 00:00:00
Shashwat ResidencyRushi Realty India Pvt Ltd9Jdfisn4fftodneqiqoszroi6mg35hadrvdxuexpatucimogbdf5285hah+Oqqf1pmbxbzb4zhnc+Lvpscrgynzhbqm9zhs2s6sel4e/Gzk4+7Kikk5vtf30cs3pt0gm30-12-2022 00:00:00
Nishchay Wing DShreeraj Developer LlpNructmdx/Qwjwpgvblmjfg==30-12-2024 00:00:00
Proposed Redevelopment Of Prakashkunj ChslYash Realtors & Developers7Xipfhvqbs+Wwukevke5w70kojvlbyvqgrj1etls4tq=30-12-2023 00:00:00
Golden GatewayD.N DevelopersMpwow3uysasdjgec0eqtnq==31-12-2029 00:00:00
Varella MansionDean Home Llp2Prm01d6zzvl19chrqigp7fbfpjesbesvfgizeau/V8=31-10-2027 00:00:00
Adinath HeightsShri Neelkanth DevelopersGx8jresglohl4kq2t6/O0g==31-03-2026 00:00:00
Shraddha Park CityShraddha Prime Projects LimitedQn3pocelmguc3stmhc0a8mhfaxau6rfege2wmm2ibyht5ucrecwuqumo3bgkfad431-12-2029 00:00:00
21 JewelRatansingh And BrothersHlfrkostfhskjrzox84npccuzjedrcw0wsw62csycpi=31-12-2028 00:00:00
103 WestM/S. Relcon Zp Je Construction LlpFmq6rurkazksxgo+Alsysa==31-03-2029 00:00:00
Shreeji LeelaK Mehta And CompanyJ4hhwt+Trjpx5pg2fcrnxr5ocrnskvdqmyzffqfzcts=30-06-2028 00:00:00
Raghukul ChslRamniyati Realities Llp9Zigemu0fmceglhidkg9fg==31-12-2029 00:00:00
KASHI BHUVANBHARAT V KENNY1011/A31-12-2024 00:00:00
Blue Star Crystal ChslParadigm Blue Star Llp5Ptzy29q9kenhntcso9kuw==12-07-2027 00:00:00
Apurva Vaishali ChslDiravya Developers Llp3Nllyyapenlahdku9pkjya==30-09-2025 00:00:00
State Sector Bank Employees Chs Ltd Kailas BuildingKonark Structural Engineers Private LimitedNlvxg3uxzrzqudvziiqaww==31-03-2025 00:00:00
Bhavik Darshan Chs Ltd And Gajmukh Chs LtdKonark Structural Engineers Private LimitedDddho45evol0zxr4eg1mrjtll1g1r3ckleohhmws/Ighhuti2pkwl1v7azlv8jncvcgfn8jnzczzlzo5avvsm+Xn3jtpscytqpmxfv2tanq=31-12-2027 00:00:00
Nishchay Wing FShreeraj Developer LlpRqey4x9ui6rbj3kh1o4vmg==30-12-2024 00:00:00
The Borivali Neel Akash ChslTriveni Developers400066, Mumbai Suburban31-12-2018 00:00:00
MadonnaMichael Rodrigues8Smururjovg+3V6y1pwekq==15-12-2019 00:00:00
Pratham - By ShraddhaShraddha Prime Projects Limited0Dhooynxpjsglqxlkpi+2Ooiiko+4Hxi5j2vdedjvsi=31-12-2029 00:00:00
66 Aventus AvenueAventus Infrastructure LlpYump8ulrxlsb5qvgcpr67ha6k8iaqqc3yovfje3c78a=31-12-2029 00:00:00
Shiv Guru TowerRajlaxmi DevelopersHccj4hqz12x65owbz6kokw==31-12-2027 00:00:00
Poonam ChslDigam Lifespaces LlpYcmaqebhjo/Zl+Nti/Kcqd0zysokl16vrzn26cxe7b3squdenapxncxml2ursljl31-10-2027 00:00:00
Shri Hari BuildingShri Neelkanth Developers3Zg6ixbnssbbn613yaak0w==31-01-2019 00:00:00
Vklal Hari Phase IVeekaylal Investment Company Private LimitedCzsut03qofq5yoskhwavyw==30-12-2025 00:00:00
Aditya Aryan / EjajDinesh C Agarwal6Md20l9hn8a2b/Ttbnagfrezwcqhdjl2lvsm56eoznqxp2wdtp6n+5Ehndc49qpxctu3g5no6vlwlywppc5zlno/Xvm2g1tnjxznp9z6to/Akyeven6hy6b1rx32ukrd31-03-2018 00:00:00
Dahisar Sagar Co-Operative Housing Society LimitedM/S. Trilogy Realtors Private LimitedCkzlimpqf4eofeb7x6lhpq==31-12-2029 00:00:00
Raj CapitalRaj Insignia Private LimitedDxlwepxrclasnu+Bmekagg==31-08-2026 00:00:00
Manglam RajanigandhaManglam & Karnani Ventures LlpRmfgecjt2huzyguipndxuw==30-06-2027 00:00:00
Bldg No.1 Dahisar Sai Sadan Chs LtdTrumph DevelopersQdriatdybiebmg3e5vruvq==31-12-2019 00:00:00
Suresh SadanJaverben Nenshi ChhadvaMdwjkl/Boww91dldjonbjruk1qwdjmikznmpbzmyjicdnpf2eg44ophso+4Ild6k7webobjwaqj+Q3jpv7wxx9ibkfzrjcvjpxukpzxklkg=31-12-2018 00:00:00
Parimal HeritageDvnm Realty Private Limited2Thueykpl152fza9lpeuopa4ohmjuj+7J0v+9Rtfvla=31-03-2027 00:00:00
Shree Sai Prasad Sra Chs LtdArjun WaghmareBorivali West31-12-2018 00:00:00
Saikrupa ChsHasmukh R Hirani4Wx/Nfgd2gwpslzyy/Tplw==30-06-2019 00:00:00
Rishabraj EmeraldH Rishabraj UniversalWglijtqx0e7mfsq+Nfhx7a==31-12-2026 00:00:00
SanskritiJem And AssociatesG5mcdfv2aoo85ouakjeq5fk1089aamheux8fga7uq1c=31-01-2021 00:00:00
Jalaram SquareShree Jalaram Developers30-09-2027 00:00:00
Avvirahi PlatinumAvvirahi Infra Llp25-12-2030 00:00:00
Shree Hari Om NagarRising Pioneers Infra LlpBao7qcbctijrofixgzavsq==31-12-2027 00:00:00
ShivalayaParadigm Friends Realtors Llp 02-01-2029 00:00:00
Modirealty AshvatthaModirealty Developers Pvt LtdXvhdcccq1u0mcxg8pu9bsr2h2rz4hm+Qookjisxpqk8=31-03-2027 00:00:00
Ami OneAmi Wiseowlzz Realty31-12-2027 00:00:00
Redevelopment Of Sbi Emp Navjeevan ChslPranav Constructions Limited21-07-2028 00:00:00
Tasmai AnandaTasmai Shree30-06-2027 00:00:00
Rajhans VandanaRajhans Constructions31-12-2027 00:00:00
Jay Shrinath ChslK Mehta And CompanyHguulqifjlu2iaqcb758nq==30-06-2025 00:00:00
Chaitanya Om Shivam - Om Shivam Premises CslChaitanya Enterprises84Mnczrpwpqx3l35tlkciq==31-05-2024 00:00:00
Avyukta MeghaKhushi Spaces Llp30-12-2028 00:00:00
Sambhav Darshan Purshottam Park Co-Operative Housing Society LtdSamarpan Homes & Developers31-12-2027 00:00:00
Rishabraj Forest FrontRishabraj Estate Developers Pvt Ltd31-12-2028 00:00:00
Parekh EminenceParekh Spaces Llp31-12-2028 00:00:00
Rishabraj ChambersRishabraj Estate Developers Pvt LtdQv6rbotjo5ykz5nuidmmmo/5H58um5xtv1liqckuuiu=31-12-2025 00:00:00
Shiv ParbatV3 PartnersFo2virvki0wqjlt0kvglqa==15-03-2027 00:00:00
Rijin PrideSurbhi Construction30-09-2028 00:00:00
25 RbcRander Bandhu Corporation Llp31-03-2029 00:00:00
Empire EternityEmpire Land Developers Llp31-07-2028 00:00:00
Gorai Samadhan Cooperative Housing Society LimitedGorai Samadhan Cooperative Housing Society Limited30-06-2027 00:00:00
Project Details
  • Project:
    Sai Leela
  • Location:
  • Nd5di1flbwwkk6lmyzq9gejbr2zbilecetr7bxfwtta=
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Laxmi Associates
  • Phone:
  • Address:
  • Akhil Tower
Project RERA Details
MAHA REARA No: P51800001249
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect A R Mehta & Associates
Funding Bank IDBI BANK
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession 30 Dec 2022
Litigations No Litigations
Last Modified 09 Sep 2021
Last Retrived 13 Feb 2026
Sai Leela QR Code
Sai Leela
MahaRERA - P51800001249
Apartment Details & Configuration
TypeArea
1 BHK33.3 Sq.mts. ( 358 Sq.ft. )
1 RK19.83 Sq.mts. ( 213 Sq.ft. )
1 RK23 Sq.mts. ( 248 Sq.ft. )
1 RK26.89 Sq.mts. ( 289 Sq.ft. )
1 RK28.9 Sq.mts. ( 311 Sq.ft. )
1 RK31.41 Sq.mts. ( 338 Sq.ft. )
2 BHK48.73 Sq.mts. ( 525 Sq.ft. )
2 BHK54.81 Sq.mts. ( 590 Sq.ft. )
2 BHK60.05 Sq.mts. ( 646 Sq.ft. )
2 BHK60.75 Sq.mts. ( 654 Sq.ft. )
1 BHK31.26 Sq.mts. ( 336 Sq.ft. )
1 BHK36.15 Sq.mts. ( 389 Sq.ft. )
2 BHK41.12 Sq.mts. ( 443 Sq.ft. )
2 BHK45.48 Sq.mts. ( 490 Sq.ft. )
2 BHK48.29 Sq.mts. ( 520 Sq.ft. )
1 BHK36.36 Sq.mts. ( 391 Sq.ft. )
2 BHK48.3 Sq.mts. ( 520 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sai Leelalast updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station90% completed
90% Complete
Na
Energy management
Na
Fire Protection And Fire Safety Requirements85% completed
85% Complete
Na
Landscaping & Tree Planting50% completed
50% Complete
Na
Open Parking80% completed
80% Complete
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Na
Solid Waste Management And Disposal
Na
Storm Water Drains90% completed
90% Complete
Na
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting85% completed
85% Complete
Na
Water Supply
Na
Buildings / Wings in Sai Leela
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sai Leela by Laxmi Associateslast updated on 13 Feb 2026 as per information obtained from MARA RERA.

19895 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

118 apartments in total
Total
118
Booked
82
Available
36

Saleable Area Statistics (Sq. ft.)

47635 Total
Total
47635
Booked
33465
Available
14171
Total 118 apartments in project. 82 apartments booked. 69% apartments booked.
Total 47635 Sq.ft. saleable area. 33465 saleable area booked.
70% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJan 1900101010416
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.3 Sq.mts. ( 358 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 RK19.83 Sq.mts. ( 213 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 RK23 Sq.mts. ( 248 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 RK26.89 Sq.mts. ( 289 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 RK28.9 Sq.mts. ( 311 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 RK31.41 Sq.mts. ( 338 Sq.ft. )9
9 Booked100% Booked
100% Booked
2 BHK48.73 Sq.mts. ( 525 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK54.81 Sq.mts. ( 590 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK60.05 Sq.mts. ( 646 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK60.75 Sq.mts. ( 654 Sq.ft. )1
1 Booked100% Booked
100% Booked
32 total apartments / 29 apartments booked. 90% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BDec 2019121010416
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.26 Sq.mts. ( 336 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK36.15 Sq.mts. ( 389 Sq.ft. )20
20 Booked100% Booked
100% Booked
2 BHK41.12 Sq.mts. ( 443 Sq.ft. )11
10 Booked90% Booked
90% Booked
2 BHK45.48 Sq.mts. ( 490 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK48.29 Sq.mts. ( 520 Sq.ft. )10
10 Booked100% Booked
100% Booked
43 total apartments / 42 apartments booked. 97% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CDec 2019121010517
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.15 Sq.mts. ( 389 Sq.ft. )21
1 BHK36.36 Sq.mts. ( 391 Sq.ft. )11
2 BHK48.3 Sq.mts. ( 520 Sq.ft. )11
8 Booked72% Booked
72% Booked
43 total apartments / 11 apartments booked. 25% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Laxmi Associates
for Project
Sai Leela
last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation