Project overview

Sahakar Dwarka 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000005452. Sahakar Dwarka 2 is located at 111/2. This is a Ongoing being developed by Megha Enterprises.

Sahakar Dwarka 2 has 1 BHK Apartments with carpet areas ranging from 307 to 407 Sq.ft. Carpet. The Project has total 397 of which 43 are currently available for sale.

Sahakar Dwarka 2 is being developed on a total land area of 175884 Sq.ft. out of which 57709 Sq.ft. i.e 33% is reserved for recreational purposes. Sahakar Dwarka 2 has 16 Wings / Towers Bldg 1 - A B Wing,Bldg 10,Bldg 11,Bldg 12 - A B Wing,Bldg 13,Bldg 14 - A B Wing,Bldg 15,Bldg 16,Bldg 2 - A B Wing,Bldg 3 -A B Wing,Bldg 4 - A B Wing,Bldg 5 - A B Wing,Bldg 6 - A B Wing,Bldg 7,Bldg 8 - A B Wing,Bldg 9 - A B Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sahakar Dwarka 2
  • Location:
  • 111/2
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2021
Developer Details

  • Developer:
    Megha Enterprises
  • Phone:
  • Address:
  • Neelkanth Darshan
Project RERA Details
MAHA REARA No: P52000005452
Project Type Others
RERA Project Status Ongoing
Funding Bank STATE BANK OF INDIA
Proposed Possession 30 Jun 2021
Revised Possession 30 Jun 2021
Extended Possession 31 Dec 2024
Litigations No Litigations
Last Modified 26 Mar 2025
Last Retrived 28 Jul 2025
Sahakar Dwarka 2 QR Code
Sahakar Dwarka 2
MahaRERA - P52000005452
Apartment Details & Configuration
TypeArea
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )
2 BHK47 Sq.mts. ( 506 Sq.ft. )
2 BHK54.93 Sq.mts. ( 591 Sq.ft. )
00 Sq.mts. ( 0 Sq.ft. )
2 BHK47.81 Sq.mts. ( 515 Sq.ft. )
2 BHK48.08 Sq.mts. ( 518 Sq.ft. )
2 BHK56.17 Sq.mts. ( 605 Sq.ft. )
2 BHK57.65 Sq.mts. ( 621 Sq.ft. )
Shop5.71 Sq.mts. ( 61 Sq.ft. )
Shop6.72 Sq.mts. ( 72 Sq.ft. )
Shop7.36 Sq.mts. ( 79 Sq.ft. )
Shop7.42 Sq.mts. ( 80 Sq.ft. )
Shop9.94 Sq.mts. ( 107 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sahakar Dwarka 2last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Open To Sky
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station70% completed
70% Complete
Mseb
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting80% completed
80% Complete
As Per Approved Plan
LIFT IN EACH BUILDING55% completed
55% Complete
As Per Approved Plan
Open Parking80% completed
80% Complete
As Per Approved Plan
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
70% Complete
As Per Approved Plan
Solid Waste Management And Disposal50% completed
50% Complete
As Per Approved Plan
Storm Water Drains70% completed
70% Complete
As Per Approved Plan
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Stp
Water Conservation, Rain water Harvesting50% completed
50% Complete
As Per Approved Plan
Water Supply100% completed
95% Complete
As Per Approved Plan
Buildings / Wings in Sahakar Dwarka 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sahakar Dwarka 2 by Megha Enterpriseslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

175884 Sq. ft.

Project Area

57709 Sq. ft.

Recreational Open Space

Total 16

Wings / Towers in Project

Apartments Statistics

397 apartments in total
Total
397
Booked
354
Available
43

Saleable Area Statistics (Sq. ft.)

143869 Total
Total
143869
Booked
129183
Available
14686
Total 397 apartments in project. 354 apartments booked. 89% apartments booked.
Total 143869 Sq.ft. saleable area. 129183 saleable area booked.
90% area booked.

Bldg 1 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 1 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
11 Booked91% Booked
91% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
2 Booked100% Booked
100% Booked
39 total apartments / 37 apartments booked. 94% apartments booked.
Work Description in Building Bldg 1 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 10

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 10Dec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47 Sq.mts. ( 506 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK54.93 Sq.mts. ( 591 Sq.ft. )2
2 Booked100% Booked
100% Booked
16 total apartments / 16 apartments booked. 100% apartments booked.
Work Description in Building Bldg 10Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 11

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 11Dec 20200000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Bldg 11Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bldg 12 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 12 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
10 Booked83% Booked
83% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
9 Booked75% Booked
75% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
2 Booked100% Booked
100% Booked
39 total apartments / 33 apartments booked. 84% apartments booked.
Work Description in Building Bldg 12 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 13

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 13Dec 20200000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Bldg 13Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bldg 14 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 14 - A B WingDec 20200000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Bldg 14 - A B WingCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bldg 15

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 15Dec 20200000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Bldg 15Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bldg 16

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 16Dec 20200000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Bldg 16Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bldg 2 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 2 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
7 Booked58% Booked
58% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
7 Booked58% Booked
58% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
1 Booked50% Booked
50% Booked
39 total apartments / 27 apartments booked. 69% apartments booked.
Work Description in Building Bldg 2 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 3 -A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 3 -A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
7 Booked58% Booked
58% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
8 Booked66% Booked
66% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
2 Booked100% Booked
100% Booked
39 total apartments / 27 apartments booked. 69% apartments booked.
Work Description in Building Bldg 3 -A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 4 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 4 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47 Sq.mts. ( 506 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK47.81 Sq.mts. ( 515 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK48.08 Sq.mts. ( 518 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK54.93 Sq.mts. ( 591 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK56.17 Sq.mts. ( 605 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK57.65 Sq.mts. ( 621 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop5.71 Sq.mts. ( 61 Sq.ft. )4
3 Booked75% Booked
75% Booked
Shop6.72 Sq.mts. ( 72 Sq.ft. )4
3 Booked75% Booked
75% Booked
Shop7.36 Sq.mts. ( 79 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop7.42 Sq.mts. ( 80 Sq.ft. )4
4 Booked100% Booked
100% Booked
Shop9.94 Sq.mts. ( 107 Sq.ft. )4
4 Booked100% Booked
100% Booked
50 total apartments / 48 apartments booked. 96% apartments booked.
Work Description in Building Bldg 4 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 5 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 5 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
11 Booked91% Booked
91% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
2 Booked100% Booked
100% Booked
39 total apartments / 36 apartments booked. 92% apartments booked.
Work Description in Building Bldg 5 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 6 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 6 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
11 Booked91% Booked
91% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
2 Booked100% Booked
100% Booked
39 total apartments / 38 apartments booked. 97% apartments booked.
Work Description in Building Bldg 6 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 7

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 7Dec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
19 total apartments / 19 apartments booked. 100% apartments booked.
Work Description in Building Bldg 7Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 8 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 8 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
11 Booked91% Booked
91% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
2 Booked100% Booked
100% Booked
39 total apartments / 38 apartments booked. 97% apartments booked.
Work Description in Building Bldg 8 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Bldg 9 - A B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg 9 - A B WingDec 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.52 Sq.mts. ( 307 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 BHK32.86 Sq.mts. ( 354 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK33.26 Sq.mts. ( 358 Sq.ft. )12
10 Booked83% Booked
83% Booked
1 BHK35.31 Sq.mts. ( 380 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK35.71 Sq.mts. ( 384 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.36 Sq.mts. ( 402 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )2
2 Booked100% Booked
100% Booked
39 total apartments / 35 apartments booked. 89% apartments booked.
Work Description in Building Bldg 9 - A B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Megha Enterprises
for Project
Sahakar Dwarka 2
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation