Project overview

Sahakar Avenue is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800003995. Sahakar Avenue is located at 551/1 To 5. This is a Ongoing being developed by Sahakar Corporation.

Sahakar Avenue has 1 BHK, 2 BHK, Additional Area B803, Addl Area, Addl Area B203, AddlareaB801 & AddlB302 Apartments with carpet areas ranging from 140 to 105 Sq.ft. Carpet. The Project has total 80 of which 49 are currently available for sale.

Sahakar Avenue is being developed on a total land area of 20426 Sq.ft. out of which 2626 Sq.ft. i.e 13% is reserved for recreational purposes. Sahakar Avenue has 2 Wings / Towers A Wing,B Wing Rehab Component

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sahakar Avenue
  • Location:
  • 551/1 To 5
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2020
Developer Details

  • Developer:
    Sahakar Corporation
  • Phone:
  • Address:
  • Sham Nirmal Apt
Project RERA Details
MAHA REARA No: P51800003995
Project Type Others
RERA Project Status Ongoing
Architect Rasik P Hingoo
Funding Bank INDIAN BANK
Proposed Possession 31 Dec 2020
Revised Possession 31 Dec 2020
Extended Possession 31 Mar 2025
Litigations No Litigations
Last Modified 10 Mar 2025
Last Retrived 26 Jul 2025
Sahakar Avenue QR Code
Sahakar Avenue
MahaRERA - P51800003995
Apartment Details & Configuration
TypeArea
1.5 BHK55.54 Sq.mts. ( 598 Sq.ft. )
2 BHK61.39 Sq.mts. ( 661 Sq.ft. )
2 BHK69.85 Sq.mts. ( 752 Sq.ft. )
2 BHK70.99 Sq.mts. ( 764 Sq.ft. )
2 BHK79.8 Sq.mts. ( 859 Sq.ft. )
2 BHK82.25 Sq.mts. ( 885 Sq.ft. )
OFFICE139.22 Sq.mts. ( 1499 Sq.ft. )
Shop13.43 Sq.mts. ( 145 Sq.ft. )
Shop23.6 Sq.mts. ( 254 Sq.ft. )
SHOP35.9 Sq.mts. ( 386 Sq.ft. )
1 BHK37.35 Sq.mts. ( 402 Sq.ft. )
1 BHK44.3 Sq.mts. ( 477 Sq.ft. )
2 BHK54.48 Sq.mts. ( 586 Sq.ft. )
2 BHK58.35 Sq.mts. ( 628 Sq.ft. )
2 BHK68.54 Sq.mts. ( 738 Sq.ft. )
Additional Area B8039.75 Sq.mts. ( 105 Sq.ft. )
Addl Area13.01 Sq.mts. ( 140 Sq.ft. )
Addl Area8.83 Sq.mts. ( 95 Sq.ft. )
Addl Area B2039.29 Sq.mts. ( 100 Sq.ft. )
AddlareaB80121 Sq.mts. ( 226 Sq.ft. )
AddlB3025.11 Sq.mts. ( 55 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sahakar Avenuelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Yet To Start
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station80% completed
80% Complete
Work In Progress
Energy management
Na
Fire Protection And Fire Safety Requirements50% completed
50% Complete
Work In Progress
Landscaping & Tree Planting50% completed
50% Complete
Yet To Start
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Work In Progress
Solid Waste Management And Disposal
Na
Storm Water Drains90% completed
90% Complete
Yet To Start
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Yet To Start
Water Supply50% completed
50% Complete
Work In Progress
Buildings / Wings in Sahakar Avenue
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sahakar Avenue by Sahakar Corporationlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

20426 Sq. ft.

Project Area

2626 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

80 apartments in total
Total
80
Booked
31
Available
49

Saleable Area Statistics (Sq. ft.)

47593 Total
Total
47593
Booked
15938
Available
31655
Total 80 apartments in project. 31 apartments booked. 38% apartments booked.
Total 47593 Sq.ft. saleable area. 15938 saleable area booked.
33% area booked.

A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A WingDec 202019101200
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK55.54 Sq.mts. ( 598 Sq.ft. )15
6 Booked40% Booked
40% Booked
2 BHK61.39 Sq.mts. ( 661 Sq.ft. )17
2 BHK69.85 Sq.mts. ( 752 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK70.99 Sq.mts. ( 764 Sq.ft. )14
5 Booked35% Booked
35% Booked
2 BHK79.8 Sq.mts. ( 859 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK82.25 Sq.mts. ( 885 Sq.ft. )1
1 Booked100% Booked
100% Booked
OFFICE139.22 Sq.mts. ( 1499 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop13.43 Sq.mts. ( 145 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop23.6 Sq.mts. ( 254 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP35.9 Sq.mts. ( 386 Sq.ft. )1
1 Booked100% Booked
100% Booked
53 total apartments / 19 apartments booked. 35% apartments booked.
Work Description in Building A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress50% done
50% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress70% done
70% Booked
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress96% done
96% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress96% done
96% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress90% done
90% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

B Wing Rehab Component

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B Wing Rehab ComponentDec 202018101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.35 Sq.mts. ( 402 Sq.ft. )5
2 Booked40% Booked
40% Booked
1 BHK44.3 Sq.mts. ( 477 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK54.48 Sq.mts. ( 586 Sq.ft. )7
3 Booked42% Booked
42% Booked
2 BHK58.35 Sq.mts. ( 628 Sq.ft. )6
None Booked0% Booked
0% Booked
2 BHK68.54 Sq.mts. ( 738 Sq.ft. )1
None Booked0% Booked
0% Booked
Additional Area B8039.75 Sq.mts. ( 105 Sq.ft. )1
1 Booked100% Booked
100% Booked
Addl Area13.01 Sq.mts. ( 140 Sq.ft. )1
1 Booked100% Booked
100% Booked
Addl Area8.83 Sq.mts. ( 95 Sq.ft. )2
2 Booked100% Booked
100% Booked
Addl Area B2039.29 Sq.mts. ( 100 Sq.ft. )1
1 Booked100% Booked
100% Booked
AddlareaB80121 Sq.mts. ( 226 Sq.ft. )1
1 Booked100% Booked
100% Booked
AddlB3025.11 Sq.mts. ( 55 Sq.ft. )1
1 Booked100% Booked
100% Booked
27 total apartments / 12 apartments booked. 44% apartments booked.
Work Description in Building B Wing Rehab ComponentCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress50% done
50% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress70% done
70% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress96% done
96% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress96% done
96% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress90% done
90% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Sahakar Corporation
for Project
Sahakar Avenue
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation