Project overview

Sadguru Krupa Ii Phase is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700023944. Sadguru Krupa Ii Phase is located at 42/3, 42/4/2. This is a New being developed by Chirag Enterprises.

Sadguru Krupa Ii Phase has 1 BHK & 1RK Apartments with carpet areas ranging from 260 to 395 Sq.ft. Carpet. The Project has total 74 of which 35 are currently available for sale.

Sadguru Krupa Ii Phase is being developed on a total land area of 22281 Sq.ft. out of which 323 Sq.ft. i.e 1% is reserved for recreational purposes. Sadguru Krupa Ii Phase has 2 Wings / Towers Building No 1,Building No 2

ProjectDeveloperLocationPossession
Tharwani Solitaire Phase IiiAnil Hardasmal Tharwani8/1, 8/2, 12/1-12/730-03-2021 00:00:00
Tharwani Solitaire Phase IAnil Hardasmal Tharwani8/1, 8/2, 12/1-12/730-04-2018 00:00:00
Vasudev Laxmi ParkMahesh Manohar SalphaleSurvey No- 29, Hissa No 4,Z01-01-2027 00:00:00
Galaxy HeritageGrand Galaxy Superstructures Private LimitedBrk No-422, Room No.425 To 432, Cts No.7976 To7980, 7981B, 7982B31-12-2023 00:00:00
Project Details
  • Project:
    Sadguru Krupa Ii Phase
  • Location:
  • 42/3, 42/4/2
  • Const. Stage:
    New
  • Possession:
    30 May 2024
Developer Details

  • Developer:
    Chirag Enterprises
  • Phone:
  • Address:
  • Sadguru Krupa
Project RERA Details
MAHA REARA No: P51700023944
Project Type Residential / Group Housing
RERA Project Status New
Architect Raisingh M Ahuja
Funding Bank BANK OF BARODA
Proposed Possession 30 May 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 21 Jun 2024
Last Retrived 26 Jul 2025
Sadguru Krupa Ii Phase QR Code
Sadguru Krupa Ii Phase
MahaRERA - P51700023944
Apartment Details & Configuration
TypeArea
1 BHK29.88 Sq.mts. ( 322 Sq.ft. )
1 BHK32.01 Sq.mts. ( 345 Sq.ft. )
1 BHK35.02 Sq.mts. ( 377 Sq.ft. )
1 BHK35.38 Sq.mts. ( 381 Sq.ft. )
1 BHK35.57 Sq.mts. ( 383 Sq.ft. )
1RK24.1 Sq.mts. ( 259 Sq.ft. )
Shop10.57 Sq.mts. ( 114 Sq.ft. )
Shop15.95 Sq.mts. ( 172 Sq.ft. )
1 BHK28.6 Sq.mts. ( 308 Sq.ft. )
1 BHK29 Sq.mts. ( 312 Sq.ft. )
1 BHK29.66 Sq.mts. ( 319 Sq.ft. )
1 BHK29.84 Sq.mts. ( 321 Sq.ft. )
1 BHK29.96 Sq.mts. ( 322 Sq.ft. )
1 BHK31.2 Sq.mts. ( 336 Sq.ft. )
1 BHK32.14 Sq.mts. ( 346 Sq.ft. )
1 BHK32.28 Sq.mts. ( 347 Sq.ft. )
1 BHK32.59 Sq.mts. ( 351 Sq.ft. )
1 BHK33.36 Sq.mts. ( 359 Sq.ft. )
1 BHK33.92 Sq.mts. ( 365 Sq.ft. )
1 BHK34.56 Sq.mts. ( 372 Sq.ft. )
1 BHK36.71 Sq.mts. ( 395 Sq.ft. )
1RK24.17 Sq.mts. ( 260 Sq.ft. )
1RK24.5 Sq.mts. ( 264 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sadguru Krupa Ii Phaselast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station75% completed
75% Complete
Work Pending
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Work Complete
Solid Waste Management And Disposal50% completed
50% Complete
Work Pending
Storm Water Drains100% completed
95% Complete
Work Complete
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting50% completed
50% Complete
Work Pending
Water Supply50% completed
50% Complete
Work Pending
Buildings / Wings in Sadguru Krupa Ii Phase
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sadguru Krupa Ii Phase by Chirag Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

22281 Sq. ft.

Project Area

323 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

74 apartments in total
Total
74
Booked
39
Available
35

Saleable Area Statistics (Sq. ft.)

24421 Total
Total
24421
Booked
12982
Available
11439
Total 74 apartments in project. 39 apartments booked. 52% apartments booked.
Total 24421 Sq.ft. saleable area. 12982 saleable area booked.
53% area booked.

Building No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1May 202371070295
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.88 Sq.mts. ( 322 Sq.ft. )13
None Booked0% Booked
0% Booked
1 BHK32.01 Sq.mts. ( 345 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK35.02 Sq.mts. ( 377 Sq.ft. )8
2 Booked25% Booked
25% Booked
1 BHK35.38 Sq.mts. ( 381 Sq.ft. )3
None Booked0% Booked
0% Booked
1 BHK35.57 Sq.mts. ( 383 Sq.ft. )5
3 Booked60% Booked
60% Booked
1RK24.1 Sq.mts. ( 259 Sq.ft. )6
2 Booked33% Booked
33% Booked
Shop10.57 Sq.mts. ( 114 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop15.95 Sq.mts. ( 172 Sq.ft. )1
None Booked0% Booked
0% Booked
38 total apartments / 7 apartments booked. 18% apartments booked.
Work Description in Building Building No 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress80% done
80% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress61% done
61% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress35% done
35% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress35% done
35% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2May 202351050295
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.6 Sq.mts. ( 308 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK29 Sq.mts. ( 312 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK29.66 Sq.mts. ( 319 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK29.84 Sq.mts. ( 321 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK29.96 Sq.mts. ( 322 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK31.2 Sq.mts. ( 336 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK32.14 Sq.mts. ( 346 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK32.28 Sq.mts. ( 347 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK32.59 Sq.mts. ( 351 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK33.36 Sq.mts. ( 359 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK33.92 Sq.mts. ( 365 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK34.56 Sq.mts. ( 372 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK35.57 Sq.mts. ( 383 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK36.71 Sq.mts. ( 395 Sq.ft. )1
None Booked0% Booked
0% Booked
1RK24.17 Sq.mts. ( 260 Sq.ft. )1
1 Booked100% Booked
100% Booked
1RK24.5 Sq.mts. ( 264 Sq.ft. )1
1 Booked100% Booked
100% Booked
36 total apartments / 32 apartments booked. 88% apartments booked.
Work Description in Building Building No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Chirag Enterprises
for Project
Sadguru Krupa Ii Phase
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation