Project overview

Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000020234. Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building is located at Part Of Avenue L1-L2 -L4 Being Pt Of Larger Layout Bearing Surve Nos 5 5B 5D 5F 5G Of Village Dongre. This is a New being developed by Keystone Infrastructure Private Limited.

Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building has 1 BHK, 2 BHK TYPE 1 & 2 BHK TYPE 2 Apartments with carpet areas ranging from 331 to 512 Sq.ft. Carpet. The Project has total 239 of which 25 are currently available for sale.

Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building is being developed on a total land area of 16168 Sq.ft. Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building has 3 Wings / Towers Retail Building,Wing E,Wing F

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building
  • Location:
  • Part Of Avenue L1-L2 -L4 Being Pt Of Larger Layout Bearing Surve Nos 5 5B 5D 5F 5G Of Village Dongre
  • Const. Stage:
    New
  • Possession:
    28 Feb 2023
Developer Details

  • Developer:
    Keystone Infrastructure Private Limited
  • Phone:
  • Address:
  • Natraj
Project RERA Details
MAHA REARA No: P99000020234
Project Type Others
RERA Project Status New
Architect M/S. Abhikalpan Architects & Planners
Funding Bank ICICI BANK LIMITED
Proposed Possession 28 Feb 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 21 Nov 2023
Last Retrived 28 Jul 2025
Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building QR Code
Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building
MahaRERA - P99000020234
Apartment Details & Configuration
TypeArea
Comm. Unit Type 1331.49 Sq.mts. ( 3568 Sq.ft. )
Comm. Unit Type 2337.34 Sq.mts. ( 3631 Sq.ft. )
Commr. Unit Type 356.55 Sq.mts. ( 609 Sq.ft. )
1 BHK TYPE 130.74 Sq.mts. ( 331 Sq.ft. )
2 BHK TYPE 143.87 Sq.mts. ( 472 Sq.ft. )
2 BHK TYPE 247.57 Sq.mts. ( 512 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Buildinglast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
box cricket on podium top
Yes As Part Of L1-L2 Project
children play area with rubber mat and play equipment on podium top
Yes As Part Of L1-L2 Project
common area fire sprinklers
As Part Of L1- L2 Avenue Project
common area lighting
As Part Of L1- L2 Avenue Project
Community Buildings
Na
Designer Entrance Lobby
Yes Except For Commercial Building
DG Back up for Elevators and Common area Lighting
Yes Except For Commercial Building
Earthquake resistant structure
Yes As Proposed
Electrical Meter Room, Sub-Station, Receiving Station
Yes As Proposed Except Receiving Station
Elevators
Yes As Part Of L1-L2 Project
Energy management
As Per Appvoed Plans
Fire Protection And Fire Safety Requirements
Yes Part Of L1-L2 Project As Per Cfo Requirement
futsal court on podium top
Yes As Part Of L1-L2 Project
Landscaping & Tree Planting
Na
multipurpose lawn on podium top
Yes As Part Of L1-L2 Project
Open Parking
Yes As Proposed
organic waster converter for recycle of wet garbage
As Part Of L1- L2 Avenue Project
podium parking
Yes As Proposed
podium top landscaping and Trees planting
Yes As Part Of L1-L2 Project
senior citizen area on podium top
Yes As Part Of L1-L2 Project
Sewerage (Chamber, Lines, Septic Tank , STP)
As Part Of L1- L2 Avenue Project
skating area on podium top
Yes As Part Of L1-L2 Project
Solar System
As Part Of L1- L2 Avenue As Per Environmetal Permi
Solid Waste Management And Disposal
Bins Are Propposed
Staircase and lift lobbies
Yes As Part Of L1-L2 Project
Storm Water Drains
As Per Appvoed Plans
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
walking cum jogging track on podium top
Yes As Part Of L1-L2 Project
Water Conservation, Rain water Harvesting
Internal Rwh Chambers &Amp; Piping Are Under Constucti
Water Supply
Provisions To Be Made-Supply As Per Vvcmc Approval
Buildings / Wings in Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building by Keystone Infrastructure Private Limitedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

16168 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

239 apartments in total
Total
239
Booked
214
Available
25

Saleable Area Statistics (Sq. ft.)

111281 Total
Total
111281
Booked
88525
Available
22757
Total 239 apartments in project. 214 apartments booked. 89% apartments booked.
Total 111281 Sq.ft. saleable area. 88525 saleable area booked.
80% area booked.

Retail Building

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Retail BuildingAug 202250000150
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Comm. Unit Type 1331.49 Sq.mts. ( 3568 Sq.ft. )1
None Booked0% Booked
0% Booked
Comm. Unit Type 2337.34 Sq.mts. ( 3631 Sq.ft. )3
None Booked0% Booked
0% Booked
Commr. Unit Type 356.55 Sq.mts. ( 609 Sq.ft. )1
None Booked0% Booked
0% Booked
5 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Retail BuildingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EAug 2022151012840
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK TYPE 130.74 Sq.mts. ( 331 Sq.ft. )59
52 Booked88% Booked
88% Booked
2 BHK TYPE 143.87 Sq.mts. ( 472 Sq.ft. )28
26 Booked92% Booked
92% Booked
2 BHK TYPE 247.57 Sq.mts. ( 512 Sq.ft. )30
29 Booked96% Booked
96% Booked
117 total apartments / 107 apartments booked. 91% apartments booked.
Work Description in Building Wing ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing FAug 2022151012417
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.74 Sq.mts. ( 331 Sq.ft. )59
53 Booked89% Booked
89% Booked
2 BHK TYPE 143.87 Sq.mts. ( 472 Sq.ft. )28
25 Booked89% Booked
89% Booked
2 BHK TYPE 247.57 Sq.mts. ( 512 Sq.ft. )30
29 Booked96% Booked
96% Booked
117 total apartments / 107 apartments booked. 91% apartments booked.
Work Description in Building Wing FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Keystone Infrastructure Private Limited
for Project
Rustomjee Virar Avenue L1-L2 And L4 Wing E And F And Retail Building
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation