Project overview

Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000018622. Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building is located at Part Of Avenue L1-L2 L4 Being Pt Of Larger Layout Bearing Surve Nos 5 5B 5D 5F 5G Of Village Dongre. This is a New being developed by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED.

Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building has 1 BHK TYPE 1, 2 BHK TYPE 1 & 2 BHK TYPE 2 Apartments with carpet areas ranging from 331 to 512 Sq.ft. Carpet. The Project has total 239 of which 43 are currently available for sale.

Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building is being developed on a total land area of 16455 Sq.ft. Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building has 3 Wings / Towers Retail Building,Wing A,Wing B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building
  • Location:
  • Part Of Avenue L1-L2 L4 Being Pt Of Larger Layout Bearing Surve Nos 5 5B 5D 5F 5G Of Village Dongre
  • Const. Stage:
    New
  • Possession:
    31 Jul 2022
Developer Details

  • Developer:
    KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
  • Phone:
  • Address:
  • Natraj
Project RERA Details
MAHA REARA No: P99000018622
Project Type Others
RERA Project Status New
Architect M/S. Abhikalpan Architects & Planners
Funding Bank ICICI BANK LIMITED
Proposed Possession 31 Jul 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 12 Jan 2023
Last Retrived 14 Feb 2026
Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building QR Code
Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building
MahaRERA - P99000018622
Apartment Details & Configuration
TypeArea
Comm Unit type 2363.95 Sq.mts. ( 3918 Sq.ft. )
Comm Unit type 373.62 Sq.mts. ( 792 Sq.ft. )
Comm Unit typef 1357.66 Sq.mts. ( 3850 Sq.ft. )
1 BHK TYPE 130.74 Sq.mts. ( 331 Sq.ft. )
2 BHK TYPE 143.87 Sq.mts. ( 472 Sq.ft. )
2 BHK TYPE 247.54 Sq.mts. ( 512 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Buildinglast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
box cricket on podium top
As Part Of L1- L2 Avenue Project
common area fire sprinklers
Part Of L1- L2 Avenue As Per Cfo Requirement
common area lighting
As Part Of L1- L2 Avenue Project
Community Buildings
Na
Designer Entrance Lobby
Yes Except For Commercial Building
DG Back up for Elevators and Common area Lighting
As Part Of L1- L2 Avenue Project
Earthquake resistant structure
As Part Of L1- L2 Avenue Project
Electrical Meter Room, Sub-Station, Receiving Station
Part Of Whole Avenue
Elevators
As Per Appvoed Plans
Energy management
Except Receving Station
Fire Protection And Fire Safety Requirements
Common Area Lisgting Are Led
futsal court on podium top
As Part Of L1- L2 Avenue Project
Landscaping & Tree Planting
Bins Are Propposed
multipurpose lawn on podium top
As Part Of L1- L2 Avenue Project
Open Parking
Yes As Proposed
organic waster converter for recycle of wet garbage
Yes As Proposed
podium parking
Yes As Proposed
podium top landscaping and Trees planting
As Part Of L1- L2 Avenue Project
Sewerage (Chamber, Lines, Septic Tank , STP)
Supply Will As Per Vvcmc
Solar System
As Part Of L1- L2 Avenue Project As Per Approval
Solid Waste Management And Disposal
Na
Staircase and lift lobbies
Part Of Whole Project
Storm Water Drains
Yes As Proposed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
walking cum jogging track on podium top
As Part Of L1- L2 Avenue Project
Water Conservation, Rain water Harvesting
Internal Rwh Chambers &Amp; Piping Are Under Constucti
Water Supply
Provisiona Will Be Made
Buildings / Wings in Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building by KEYSTONE INFRASTRUCTURE PRIVATE LIMITEDlast updated on 14 Feb 2026 as per information obtained from MARA RERA.

16455 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

239 apartments in total
Total
239
Booked
196
Available
43

Saleable Area Statistics (Sq. ft.)

112587 Total
Total
112587
Booked
79571
Available
33015
Total 239 apartments in project. 196 apartments booked. 82% apartments booked.
Total 112587 Sq.ft. saleable area. 79571 saleable area booked.
71% area booked.

Retail Building

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Retail BuildingJan 20225000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Comm Unit type 2363.95 Sq.mts. ( 3918 Sq.ft. )3
None Booked0% Booked
0% Booked
Comm Unit type 373.62 Sq.mts. ( 792 Sq.ft. )1
None Booked0% Booked
0% Booked
Comm Unit typef 1357.66 Sq.mts. ( 3850 Sq.ft. )1
None Booked0% Booked
0% Booked
5 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Retail BuildingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress89% done
89% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress47% done
47% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress47% done
47% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress89% done
89% Booked

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJan 2022151012440
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK TYPE 130.74 Sq.mts. ( 331 Sq.ft. )59
54 Booked91% Booked
91% Booked
2 BHK TYPE 143.87 Sq.mts. ( 472 Sq.ft. )28
24 Booked85% Booked
85% Booked
2 BHK TYPE 247.54 Sq.mts. ( 512 Sq.ft. )30
23 Booked76% Booked
76% Booked
117 total apartments / 101 apartments booked. 86% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress78% done
78% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress78% done
78% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress40% done
40% Booked
Sanitary Fittings within the flats / premises
work-in-progress40% done
40% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJan 2022151012341
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK TYPE 130.74 Sq.mts. ( 331 Sq.ft. )59
51 Booked86% Booked
86% Booked
2 BHK TYPE 143.87 Sq.mts. ( 472 Sq.ft. )28
20 Booked71% Booked
71% Booked
2 BHK TYPE 247.54 Sq.mts. ( 512 Sq.ft. )30
24 Booked80% Booked
80% Booked
117 total apartments / 95 apartments booked. 81% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress78% done
78% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress78% done
78% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress40% done
40% Booked
Sanitary Fittings within the flats / premises
work-in-progress40% done
40% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
for Project
Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building
last updated on 14 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation