Project overview

Rudra Heights is a MahaRERA Registered Project bearing MahaRERA Registration Number P51900005874. Rudra Heights is located at Cs No. 197/74, Plot No 209. This is a Ongoing being developed by Gold Plaza Developers Pvt Ltd.

Rudra Heights has 1 BHK, 2 BHK & SHOP Apartments with carpet areas ranging from 177 to 478 Sq.ft. Carpet. The Project has total 21 of which 0 are currently available for sale.

Rudra Heights is being developed on a total land area of 4652 Sq.ft. Rudra Heights has 1 Wings / Towers Rudra Heights

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Rudra Heights
  • Location:
  • Cs No. 197/74, Plot No 209
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Gold Plaza Developers Pvt Ltd
  • Phone:
  • Address:
  • Jetha Compound
Project RERA Details
MAHA REARA No: P51900005874
Project Type Others
RERA Project Status Ongoing
Architect Ansari Ishrat Mohammed Yunus
Funding Bank THE COSMOS CO OPERATIVE BANK LIMITED
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession 30 Dec 2021
Litigations No Litigations
Last Modified 09 Sep 2021
Last Retrived 26 Jul 2025
Rudra Heights QR Code
Rudra Heights
MahaRERA - P51900005874
Apartment Details & Configuration
TypeArea
1 BHK35.26 Sq.mts. ( 380 Sq.ft. )
1 BHK36.58 Sq.mts. ( 394 Sq.ft. )
1 BHK40.73 Sq.mts. ( 438 Sq.ft. )
1 BHK29.41 Sq.mts. ( 317 Sq.ft. )
2 BHK44.42 Sq.mts. ( 478 Sq.ft. )
2 BHK44.43 Sq.mts. ( 478 Sq.ft. )
SHOP31.14 Sq.mts. ( 335 Sq.ft. )
SHOP16.48 Sq.mts. ( 177 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Rudra Heightslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Substation &Amp; Receving Station Not Required
Energy management
Na
Fire Protection And Fire Safety Requirements
Will Be Provided As Per Approval
Landscaping & Tree Planting
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank &Amp; Stp Not Required
Solid Waste Management And Disposal
Will Be Provided As Per Approval
Storm Water Drains
Will Be Provided As Per Approval
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Water Conservation Not Required
Water Supply
Will Be Provided As Per Approval
Buildings / Wings in Rudra Heights
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Rudra Heights by Gold Plaza Developers Pvt Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

4652 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

21 apartments in total
Total
21
Booked
21
Available
0

Saleable Area Statistics (Sq. ft.)

8382 Total
Total
8382
Booked
8382
Available
0
Total 21 apartments in project. 21 apartments booked. 100% apartments booked.
Total 8382 Sq.ft. saleable area. 8382 saleable area booked.
100% area booked.

Rudra Heights

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rudra HeightsDec 201923110000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK35.26 Sq.mts. ( 380 Sq.ft. )6
6 Booked100% Booked
100% Booked
1 BHK36.58 Sq.mts. ( 394 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK40.73 Sq.mts. ( 438 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK29.41 Sq.mts. ( 317 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK44.42 Sq.mts. ( 478 Sq.ft. )5
5 Booked100% Booked
100% Booked
2 BHK44.43 Sq.mts. ( 478 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP31.14 Sq.mts. ( 335 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP16.48 Sq.mts. ( 177 Sq.ft. )1
1 Booked100% Booked
100% Booked
21 total apartments / 21 apartments booked. 100% apartments booked.
Work Description in Building Rudra HeightsCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress75% done
75% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Gold Plaza Developers Pvt Ltd
for Project
Rudra Heights
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation