Project overview

Royal Pearl / Royal Sankalp is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800001607. Royal Pearl / Royal Sankalp is located at 154, 154/1 To 154/39. This is a Ongoing being developed by Royal Realtors.

Royal Pearl / Royal Sankalp has ROYAL PEARL 2 BHK, ROYAL PEARL 2BHK, ROYAL PEARL 3 BHK, ROYAL PEARL MP ROOM, ROYAL SANKALP 1BHK 1, ROYAL SANKALP 1BHK 2, ROYAL SANKALP 1BHK 3, ROYAL SANKALP 1BHK 4, ROYAL SANKALP 1BHK 5, ROYAL SANKALP COMM 1, ROYAL SANKALP COMM 2 & ROYAL SANKALP MPROOM Apartments with carpet areas ranging from 1241 to 764 Sq.ft. Carpet. The Project has total 56 of which 10 are currently available for sale.

Royal Pearl / Royal Sankalp is being developed on a total land area of 21058 Sq.ft. out of which 1098 Sq.ft. i.e 5% is reserved for recreational purposes. Royal Pearl / Royal Sankalp has 1 Wings / Towers Royal Pearl / Royal Sankalp

ProjectDeveloperLocationPossession
Sankalp HeritageShyam Biharilal Gehani986/1 T O4, 98631-12-2019 00:00:00
Sky Residency Loksadan Chs Phase 1 Up To G Plus 7Pt.Sky Property Developers Private Limited766, 766/1 To 531-12-2017 00:00:00
Aqsa Palace Chs LtdK T Group400064, Mumbai Suburban30-09-2017 00:00:00
Sky CrestSky Property Developers Private LimitedCts Number 37 37/A And 38 38/1 To 38/731-01-2021 00:00:00
Raj NirmanFerro Build682/682/1 To 228-06-2018 00:00:00
Unity ComplexR B Shah And CoCts No 278Pt 280Pt 282 283 284 284/1 To 22 285 285/1 To 37 286 287 289 290 291 29230-12-2021 00:00:00
Om HeightsKosmos &Amp; Apple RealtyMalad31-12-2020 00:00:00
Conwood Housing-Palace RoyaleConwood Housing Private Limited202, 202-B, 202-A30-09-2020 00:00:00
Sahakar AvenueSahakar Corporation551/1 To 531-12-2020 00:00:00
21 HillsAmar Developers679/1 To 7 Of Village Malad, Cts Nos 67930-06-2018 00:00:00
Laxman NiwasYash RealtorsCts 83 930-06-2018 00:00:00
Jalan NiwasKarmvir Intelligent Housing Private Limited400064, Mumbai Suburban31-12-2022 00:00:00
Redevelopment Of Khatri Apartments Cooperative Housing Society LimitedSrp Realtors Privaye LimitedSurvey No 36, Cts No 747A31-12-2019 00:00:00
Sea JewelSea Jewel Property Developers Llp320 / 1 To 16, 32030-12-2021 00:00:00
AdhritMundara DevelopersCts 838B 838B 1To 90 840 841 Pt 841 1To 53 And 58 To 6330-10-2023 00:00:00
Liberty Garden Chs LtdK T Group400064, Mumbai Suburban18-05-2017 00:00:00
Mandlik Nagar Chs Ltd Phase Ii Rehab Wing E Pt And FTriumph Builders Llp29 Pt31-12-2018 00:00:00
Horizon JewelHorizon Dream Homes Private Limited10B, Cts No 10A31-12-2019 00:00:00
Crystal PrideCrystal Construction Company401, 401/1 To 401/25, 402 Part31-12-2019 00:00:00
Udyam Kunj Chs Redevelopment Phase IMahendra Mhatre40009731-12-2017 00:00:00
Darpan HeightsDudhal Infra461, 4611 To 4.30-06-2018 00:00:00
Shreeji Plaza Wing ASiddharth EnterprisesCts No 1 Pt And 2 Pt Of Village Valnai Taluka Borivali Orlem Malad - West Mumbai30-06-2023 00:00:00
Subhshri ArcadeSubhshridevelopers163/1/24, 16328-02-2021 00:00:00
Das Bhavan ChslRishabraj Estate Developers Pvt Ltd777 1 To 4, 77731-12-2017 00:00:00
Gaurav SocietyPadmavati Maitri Corporation LlpMalad (East)31-12-2020 00:00:00
Divyam ResidencyBhavesh Mahendra Mehta437 1 To 11, 43731-12-2017 00:00:00
Romell Diva Phase Ii - 17Th To 20Th FoorRomell Real Estate Private Limited954B And 954D30-12-2025 00:00:00
Maharshi HeightsAiyannar Enterprises4030-12-2025 00:00:00
Sainik EnterprisesCaptain Dilip Kopikar610/B/1 Rani Sati Marg Malad East31-12-2018 00:00:00
Chandraraj ComplexShree Sai Shraddha Associates15/C20-03-2018 00:00:00
Jay Kirti Chs LtdRajendra ShahMumbai Suburban, 40006431-12-2017 00:00:00
Sainath Malad Sra ChsShree Mahalaxmi Associates578 1 To 2831-12-2017 00:00:00
Bhoomi Celestia B-WingSashwat Construwell Private Limited554 554/1To10 555 555/1To3 556A 557 557/1To3 558To560 562 563 580Pt To 582 589A 590 593A30-12-2021 00:00:00
Navjeevan HeightsKonark Shakti Group Of CompaniesCts No 21B30-09-2018 00:00:00
New Simit ApartmentReliable Buildhights Llp786-1, 786-2, S.No.78610-10-2019 00:00:00
Malad ShantiSachit Thakkar939/A/1431-12-2018 00:00:00
Lovedale ResidencesYashodhan Unique Construction Company4A31-03-2018 00:00:00
Laxmi HeightsDudhal InfraNew Cts Number 397A30-06-2018 00:00:00
Pushpak HeightsPushpak Realties Private LimitedMalad31-12-2019 00:00:00
Raj Rani PrideGeetaraj Realtors463 463/1 To 463/731-12-2020 00:00:00
Bhoomi Celestia -A1 WingSashwat Construwell Private Limited554 554/1To10 555 555/1To3 556A 557 557/1To3 558To560 562 563 580Pt To582 589A 590 593A30-12-2022 00:00:00
Shree Santosh AppartmentBharat Navinchandra GalaC.S.T. No-96831-12-2018 00:00:00
Tilak Revelopment Project Of Tilak Apartment ChslKabra And AssociatesPlot No 4 Cts No 132 132 1 To 431-12-2017 00:00:00
Parsh GalaxyParsh Housing Pvt Ltd133/133/1-431-12-2017 00:00:00
Vasundhara ParadiseVasundhara Develocus Llp244A 244B 244C31-12-2026 00:00:00
Center Plaza Phase 1B V Enterprises40009731-12-2023 00:00:00
Rite AmorRite Pragati DevelopersCts No 495A And 495C Of Malad North Taluka Borivali31-08-2023 00:00:00
Leela AashishLeela Creators400097, Mumbai Suburban31-12-2020 00:00:00
Hira Kutir Chs LtdH Rishabraj Projects370 A And D30-12-2023 00:00:00
Milan ResidencyM/S Milan Builders788/B/1/B31-12-2018 00:00:00
Chetna Kunj ChsK Merchant Construction Ltd972B31-12-2019 00:00:00
Sham Nirmal HeightsAltaa Builders57, 58/539A, B/38Part Hissa No.130-12-2022 00:00:00
Aristo ClassicAop Of Bindesh And Milind Somaiya400064, Mumbai Suburban09-02-2019 00:00:00
SolitaireSolitaire ConstructionsCts No 855 C31-03-2019 00:00:00
Unity HeightsUnited Developers6741-7675 6761 9871-1031-07-2018 00:00:00
Victory DivineYashodanand Realtors960/830-09-2020 00:00:00
Romell Diva Phase Iii - 21St To 23Rd FloorRomell Real Estate Private Limited954B And 954D30-12-2025 00:00:00
Irene Wing A Phase 1Sheth Creators And Sunvision Private Limited231, 230, 23230-12-2025 00:00:00
Divine TowersKabra Estate And Investment ConsultantsCts No.5597Survey No.13130-12-2021 00:00:00
A.N. HeightsH Square Builders411A/1 To 10, 223/5, 411A, 223/3, 223/6, 220/1130-06-2021 00:00:00
Shanker Smruti Chs LtdShree Shakti Construction CompanyCts No. 736, 736/1 To 531-03-2019 00:00:00
LinkparkAdarsh Industrial Estate Private LimitedResidentail Building No 2 Under Sra Scheme On Plot Bearing Cts No 335/1 Malad Mumbai19-10-2026 00:00:00
Redevelopment Of Malad Swing ChslBharat Realty Venture Private LimitedCts No 629, 629/ 1 To 830-12-2022 00:00:00
Sheetal Om Jay AradhanaD.G.Land Developers Private Limited83431-12-2018 00:00:00
Redevelopment Of Silverene ChslPranav Constructions LimitedCts No 4131-03-2024 00:00:00
SummersetNeo Housing And Infrastructure Development Limited41531-12-2017 00:00:00
Aditya ApartmentTejas Dinesh ShahCts No 145, 145A/1 To 331-01-2019 00:00:00
Sai Vishal Chs LtdK T GroupMumbai Suburban, 40006430-04-2018 00:00:00
Project Details
  • Project:
    Royal Pearl / Royal Sankalp
  • Location:
  • 154, 154/1 To 154/39
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Royal Realtors
  • Phone:
  • Address:
  • Shah Trade Centre
Project RERA Details
MAHA REARA No: P51800001607
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Aakar Architects And Consultant
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession
Litigations No Litigations
Last Modified 29 Jul 2017
Last Retrived 26 Jul 2025
Royal Pearl / Royal Sankalp QR Code
Royal Pearl / Royal Sankalp
MahaRERA - P51800001607
Apartment Details & Configuration
TypeArea
ROYAL PEARL 2 BHK70.96 Sq.mts. ( 764 Sq.ft. )
ROYAL PEARL 2BHK59.8 Sq.mts. ( 644 Sq.ft. )
ROYAL PEARL 3 BHK115.32 Sq.mts. ( 1241 Sq.ft. )
ROYAL PEARL MP ROOM32 Sq.mts. ( 344 Sq.ft. )
ROYAL SANKALP 1BHK 126.79 Sq.mts. ( 288 Sq.ft. )
ROYAL SANKALP 1BHK 231.58 Sq.mts. ( 340 Sq.ft. )
ROYAL SANKALP 1BHK 331.7 Sq.mts. ( 341 Sq.ft. )
ROYAL SANKALP 1BHK 439.43 Sq.mts. ( 424 Sq.ft. )
ROYAL SANKALP 1BHK 543.13 Sq.mts. ( 464 Sq.ft. )
ROYAL SANKALP COMM 144.2 Sq.mts. ( 476 Sq.ft. )
ROYAL SANKALP COMM 252.03 Sq.mts. ( 560 Sq.ft. )
ROYAL SANKALP MPROOM21.54 Sq.mts. ( 232 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Royal Pearl / Royal Sankalplast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completed At Site
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed At Site
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed At Site
Landscaping & Tree Planting100% completed
95% Complete
Completed At Site
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed At Site
Solid Waste Management And Disposal100% completed
95% Complete
Completed At Site
Storm Water Drains100% completed
95% Complete
Completed At Site
Street Lighting100% completed
95% Complete
Completed At Site
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Completed At Site
Water Conservation, Rain water Harvesting100% completed
95% Complete
Complied At Site
Water Supply100% completed
95% Complete
Supplied By Mcgm
Buildings / Wings in Royal Pearl / Royal Sankalp
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Royal Pearl / Royal Sankalp by Royal Realtorslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

21058 Sq. ft.

Project Area

1098 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

56 apartments in total
Total
56
Booked
46
Available
10

Saleable Area Statistics (Sq. ft.)

46124 Total
Total
46124
Booked
37317
Available
8807
Total 56 apartments in project. 46 apartments booked. 82% apartments booked.
Total 46124 Sq.ft. saleable area. 37317 saleable area booked.
81% area booked.

Royal Pearl / Royal Sankalp

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Royal Pearl / Royal SankalpDec 2019231110074
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
ROYAL PEARL 2 BHK70.96 Sq.mts. ( 764 Sq.ft. )18
17 Booked94% Booked
94% Booked
ROYAL PEARL 2BHK59.8 Sq.mts. ( 644 Sq.ft. )1
None Booked0% Booked
0% Booked
ROYAL PEARL 3 BHK115.32 Sq.mts. ( 1241 Sq.ft. )20
15 Booked75% Booked
75% Booked
ROYAL PEARL MP ROOM32 Sq.mts. ( 344 Sq.ft. )2
1 Booked50% Booked
50% Booked
ROYAL SANKALP 1BHK 126.79 Sq.mts. ( 288 Sq.ft. )1
None Booked0% Booked
0% Booked
ROYAL SANKALP 1BHK 231.58 Sq.mts. ( 340 Sq.ft. )1
1 Booked100% Booked
100% Booked
ROYAL SANKALP 1BHK 331.7 Sq.mts. ( 341 Sq.ft. )1
1 Booked100% Booked
100% Booked
ROYAL SANKALP 1BHK 439.43 Sq.mts. ( 424 Sq.ft. )5
5 Booked100% Booked
100% Booked
ROYAL SANKALP 1BHK 543.13 Sq.mts. ( 464 Sq.ft. )4
4 Booked100% Booked
100% Booked
ROYAL SANKALP COMM 144.2 Sq.mts. ( 476 Sq.ft. )1
1 Booked100% Booked
100% Booked
ROYAL SANKALP COMM 252.03 Sq.mts. ( 560 Sq.ft. )1
None Booked0% Booked
0% Booked
ROYAL SANKALP MPROOM21.54 Sq.mts. ( 232 Sq.ft. )1
1 Booked100% Booked
100% Booked
56 total apartments / 46 apartments booked. 82% apartments booked.
Work Description in Building Royal Pearl / Royal SankalpCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Royal Realtors
for Project
Royal Pearl / Royal Sankalp
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation