Project overview

Royal Fantasy Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800009606. Royal Fantasy Phase I is located at Cts No. 424, 424/1 To 33. This is a Ongoing being developed by Royal Fantasy Constructions Private Limited.

Royal Fantasy Phase I has 2 BHK, 3 BHK & Shop Apartments with carpet areas ranging from 1079 to 1030 Sq.ft. Carpet. The Project has total 64 of which 0 are currently available for sale.

Royal Fantasy Phase I is being developed on a total land area of 65848 Sq.ft. Royal Fantasy Phase I has 3 Wings / Towers Dreamax Height Wing C Ptc Up To 12Th Floor - No S,Dreamax Vega Wing A Full,Dreamax Vega Wing B Full

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Royal Fantasy Phase I
  • Location:
  • Cts No. 424, 424/1 To 33
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2018
Developer Details

  • Developer:
    Royal Fantasy Constructions Private Limited
  • Phone:
  • Address:
  • Upadhaya Compound, Pump House
Project RERA Details
MAHA REARA No: P51800009606
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Arun Kumar Dube
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 31 Dec 2018
Revised Possession 31 Dec 2018
Extended Possession 30 Jun 2022
Litigations No Litigations
Last Modified 14 Mar 2022
Last Retrived 26 Jul 2025
Royal Fantasy Phase I QR Code
Royal Fantasy Phase I
MahaRERA - P51800009606
Apartment Details & Configuration
TypeArea
00 Sq.mts. ( 0 Sq.ft. )
2 BHK66.37 Sq.mts. ( 714 Sq.ft. )
3 BHK89.48 Sq.mts. ( 963 Sq.ft. )
3 BHK95.73 Sq.mts. ( 1030 Sq.ft. )
3 BHK100.2 Sq.mts. ( 1079 Sq.ft. )
2 BHK64.7 Sq.mts. ( 696 Sq.ft. )
Shop24.15 Sq.mts. ( 260 Sq.ft. )
Shop28.24 Sq.mts. ( 304 Sq.ft. )
Shop34.24 Sq.mts. ( 369 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Royal Fantasy Phase Ilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station60% completed
60% Complete
Work In Progress
Energy management
0
Fire Protection And Fire Safety Requirements50% completed
50% Complete
0
Landscaping & Tree Planting
0
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
70% Complete
0
Solid Waste Management And Disposal
Na
Storm Water Drains
0
Street Lighting
0
Treatment And Disposal Of Sewage And Sullage Water65% completed
65% Complete
Work In Progress
Water Conservation, Rain water Harvesting
0
Water Supply
0
Buildings / Wings in Royal Fantasy Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Royal Fantasy Phase I by Royal Fantasy Constructions Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

65848 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

64 apartments in total
Total
64
Booked
64
Available
0

Saleable Area Statistics (Sq. ft.)

49190 Total
Total
49190
Booked
49190
Available
0
Total 64 apartments in project. 64 apartments booked. 100% apartments booked.
Total 49190 Sq.ft. saleable area. 49190 saleable area booked.
100% area booked.

Dreamax Height Wing C Ptc Up To 12Th Floor - No S

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dreamax Height Wing C Ptc Up To 12Th Floor - No SDec 201813101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Dreamax Height Wing C Ptc Up To 12Th Floor - No SCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress48% done
48% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress60% done
60% Booked

Dreamax Vega Wing A Full

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dreamax Vega Wing A FullDec 2018121112016
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK66.37 Sq.mts. ( 714 Sq.ft. )9
9 Booked100% Booked
100% Booked
3 BHK89.48 Sq.mts. ( 963 Sq.ft. )8
8 Booked100% Booked
100% Booked
3 BHK95.73 Sq.mts. ( 1030 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK100.2 Sq.mts. ( 1079 Sq.ft. )1
1 Booked100% Booked
100% Booked
19 total apartments / 19 apartments booked. 100% apartments booked.
Work Description in Building Dreamax Vega Wing A FullCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Dreamax Vega Wing B Full

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dreamax Vega Wing B FullDec 2018121112035
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK64.7 Sq.mts. ( 696 Sq.ft. )23
23 Booked100% Booked
100% Booked
2 BHK66.37 Sq.mts. ( 714 Sq.ft. )10
10 Booked100% Booked
100% Booked
3 BHK89.48 Sq.mts. ( 963 Sq.ft. )7
7 Booked100% Booked
100% Booked
3 BHK95.73 Sq.mts. ( 1030 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK100.2 Sq.mts. ( 1079 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop24.15 Sq.mts. ( 260 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop28.24 Sq.mts. ( 304 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop34.24 Sq.mts. ( 369 Sq.ft. )1
1 Booked100% Booked
100% Booked
45 total apartments / 45 apartments booked. 100% apartments booked.
Work Description in Building Dreamax Vega Wing B FullCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Royal Fantasy Constructions Private Limited
for Project
Royal Fantasy Phase I
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation