Project overview

Radhakrishna Chs Ltd is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800018207. Radhakrishna Chs Ltd is located at 1026 1026/1 To 6. This is a New being developed by Westin Sankalp Developers.

Radhakrishna Chs Ltd has 1 BHK & 2 BHK Apartments with carpet areas ranging from 332 to 650 Sq.ft. Carpet. The Project has total 35 of which 4 are currently available for sale.

Radhakrishna Chs Ltd is being developed on a total land area of 7358 Sq.ft. out of which 6835 Sq.ft. i.e 93% is reserved for recreational purposes. Radhakrishna Chs Ltd has 1 Wings / Towers Radhakrishna Chs Ltd

ProjectDeveloperLocationPossession
Arpan Chs LtdParshvanath Superstructures Private Limited35531-12-2019 00:00:00
Kavya Shree LaxmiKavya Kcd DevelopersC.T.S. No. 1C/1/283, Plot No. 22330-06-2021 00:00:00
Medha ChslC H Patil And Sons LlpCts No 86531-03-2019 00:00:00
Shree Prafull ChslShree Shyam DevelopersCts No 894 And 89501-03-2021 00:00:00
Building On Portion Of Sub Plot D Cts No 625 A 4 625 B Pt 627 A Of Kandivali West Mumbai 67 East And West BuildersBuilding On Portion Of Sub Plot D Cts No 625 A 4 625 B Pt 627 A Of Kandivali West Mumbai 6730-12-2023 00:00:00
Bhavya HeightsBhavya Infrastructures India Private Limited1305 A 216431-12-2019 00:00:00
Kamala Chs LtdPravesh Kirti KantherCts No 236 And 236 1 To 18 And 237 And 237 1 To 1631-12-2024 00:00:00
Shreeji AspireShreeji ConstructionCts No 1 Pt And 2 Pt Of Village Valnai Taluka Borivali Orlem Malad - West Mumbai Maharashtra30-11-2020 00:00:00
Ruparel Palacio Ph IShree Siddhivinayak Infrastructure & Realty725 Pt30-12-2023 00:00:00
Redevelopment Of Existing Building No. 5 Known As Mahavir Nagar Tri-Star ChslBharat Realty Venture Private LimitedPlot No 32, Cts No 128/A/24/A/1 Pt.30-12-2023 00:00:00
Rashmi SheelaModis Navnirman Llp934, 93511-02-2021 00:00:00
Gyan KutirSungreens Corp328A/I31-03-2018 00:00:00
Kandivali Geeta Sadan Chs LtdMs Prathmesh Landmark ConsultancyCts No258 258 1 To 4 Village Malad North30-06-2019 00:00:00
AmanKandur Corporation299/1 To 21, 29930-06-2018 00:00:00
Ruparel ElaraShree Siddhivinayak Infrastructure & Realty79531-12-2019 00:00:00
Shriji HeritageShriji Apartments Co-Operative Housing Society Limited2 And 3, 166, 166/130-11-2020 00:00:00
Swami DarshanGirish Rupshi Gada119530-12-2022 00:00:00
Royal Samarpan Phase 1Shreeji Construction1110 Pt 1111 Pt30-06-2021 00:00:00
Rite DivineRite Developers Pvt. Ltd.Cts No 1164 1164-1 To 731-12-2017 00:00:00
LoginBombay Slum Redevelopment Corporation Pvt. Ltd.886 Pt30-09-2022 00:00:00
Solitaire IiTulsi Enterprise Joint Venture269/A-3, 267/A, 268/A31-12-2018 00:00:00
Gabadia HeightsGurdeep, Kuldeep, Nirmal, Jaswinder, Ranjeet221/1 To 4, Plot Bearing Cts No 22128-02-2021 00:00:00
Shreeji Atlantis Wing AShreeji Construction264, 265, 216A/1A, 1Pt, 26630-06-2020 00:00:00
Avenue Wing BDharmesh Constructions Private LimitedCts No 3A/1 Pt 467 Pt30-06-2021 00:00:00
Jay Shreenath Niwas Chs LtdShree Sai Consultants40006718-03-2018 00:00:00
Charkop Jinprem Co Op Housing Society LtdCharkop Jinprem Co. Op. Housing Society LtdPlot No 224 Cts 1C-1/578 Kandivali R/C Rdp 530-12-2021 00:00:00
73 EastDimple Realtors Private Limited722, 710, 721, 711-B/711-C, 69430-12-2025 00:00:00
Amrut TaraShree Ram Buildeers98530-12-2023 00:00:00
Rite BlissRite Developers Pvt. Ltd.40006730-12-2021 00:00:00
Satguru Chs LtdSai Tasveer DevelopersSurvey No.87 Hissa No13 Cts No115, 115/1 To 115/19 Bearing Malad Khots Plot No 4330-06-2018 00:00:00
Project Details
  • Project:
    Radhakrishna Chs Ltd
  • Location:
  • 1026 1026/1 To 6
  • Const. Stage:
    New
  • Possession:
    30 Dec 2022
Developer Details

  • Developer:
    Westin Sankalp Developers
  • Phone:
  • Address:
  • Shree Gokul Chs Ltd
Project RERA Details
MAHA REARA No: P51800018207
Project Type Residential / Group Housing
RERA Project Status New
Architect Suhas Murlidhar Borole
Funding Bank SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession 30 Dec 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 15 Oct 2018
Last Retrived 26 Jul 2025
Radhakrishna Chs Ltd QR Code
Radhakrishna Chs Ltd
MahaRERA - P51800018207
Apartment Details & Configuration
TypeArea
1 BHK30.88 Sq.mts. ( 332 Sq.ft. )
1 BHK43.07 Sq.mts. ( 464 Sq.ft. )
2 BHK45.07 Sq.mts. ( 485 Sq.ft. )
2 BHK48.55 Sq.mts. ( 523 Sq.ft. )
2 BHK49.42 Sq.mts. ( 532 Sq.ft. )
2 BHK50.73 Sq.mts. ( 546 Sq.ft. )
2 BHK50.91 Sq.mts. ( 548 Sq.ft. )
2 BHK58.58 Sq.mts. ( 631 Sq.ft. )
2 BHK60.4 Sq.mts. ( 650 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Radhakrishna Chs Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completed
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking100% completed
95% Complete
Completed
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Radhakrishna Chs Ltd
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Radhakrishna Chs Ltd by Westin Sankalp Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

7358 Sq. ft.

Project Area

6835 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

35 apartments in total
Total
35
Booked
31
Available
4

Saleable Area Statistics (Sq. ft.)

18344 Total
Total
18344
Booked
15891
Available
2453
Total 35 apartments in project. 31 apartments booked. 88% apartments booked.
Total 18344 Sq.ft. saleable area. 15891 saleable area booked.
87% area booked.

Radhakrishna Chs Ltd

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Radhakrishna Chs LtdDec 2021101010515
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.88 Sq.mts. ( 332 Sq.ft. )9
9 Booked100% Booked
100% Booked
1 BHK43.07 Sq.mts. ( 464 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK45.07 Sq.mts. ( 485 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK48.55 Sq.mts. ( 523 Sq.ft. )4
3 Booked75% Booked
75% Booked
2 BHK49.42 Sq.mts. ( 532 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK50.73 Sq.mts. ( 546 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK50.91 Sq.mts. ( 548 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK58.58 Sq.mts. ( 631 Sq.ft. )8
7 Booked87% Booked
87% Booked
2 BHK60.4 Sq.mts. ( 650 Sq.ft. )7
5 Booked71% Booked
71% Booked
35 total apartments / 31 apartments booked. 88% apartments booked.
Work Description in Building Radhakrishna Chs LtdCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Westin Sankalp Developers
for Project
Radhakrishna Chs Ltd
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation