Project overview

Radha Madhav Chsl is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800005539. Radha Madhav Chsl is located at Cts No 173. This is a Ongoing being developed by Shri Krishna Chaitanya Enterprises.

Radha Madhav Chsl has 2 BHK Apartments with carpet areas ranging from 663 to 873 Sq.ft. Carpet. The Project has total 104 of which 2 are currently available for sale.

Radha Madhav Chsl is being developed on a total land area of 53589 Sq.ft. Radha Madhav Chsl has 2 Wings / Towers Wing A,Wing B

ProjectDeveloperLocationPossession
Palkhi AuraKcd And Synergy Ventures29731-12-2019 00:00:00
Shambhav DarshanAavishkar EnterprisesMumbai Suburban, 40006630-06-2020 00:00:00
Sbi Employees Prashant ChsAditya Developers40006618-05-2020 00:00:00
Target The MallMahendra Jamnadas Kara590/1 To 6 F P No 33, Cts No 59031-12-2017 00:00:00
Star PlazaSevenstar Developers68, 66/1 To 12, 67/1 To 24, 6730-12-2022 00:00:00
Ratna Mohan Triveni ChslAtul Corporates72 A / 7431-12-2018 00:00:00
Navkar AtlantisNavkar Lifespaces Private LimitedDaulat Nagar30-11-2017 00:00:00
Redevelopment Of Sanjog Chs LtdHeritage Lifestyles LlpPlot No 135 Cts No 250131-12-2018 00:00:00
Sai LeelaLaxmi Associates2488, 2488/1 To 2131-12-2019 00:00:00
Shiv AaradhanaBrightmen Buildspaces Llp281, 281/1 To 930-12-2023 00:00:00
Sanghvi SolitaireSanghvi Premises Private LimitedCts No 31B Part31-12-2018 00:00:00
Borivali Dipti Co-Op Hsg LtdShree Riddhi Siddhi Builders213030-06-2019 00:00:00
Marina Enclave Wing J,K,L Phase -IGurukrupa Developers D N Nagar Project507 / 44-130-12-2020 00:00:00
Sbi Ragvihar ChsTuvin Consultancy Llp41210-12-2020 00:00:00
Swayambhu ResidencyYogiraj Builders And Developers226A130-09-2021 00:00:00
Shree KrishnaShakuntala BhoirMumbai Suburban, 40006831-12-2018 00:00:00
Torna ApartmentRajmudra Construction Pvt Ltd211831-01-2018 00:00:00
The Borivali Neel Akash ChslTriveni Developers400066, Mumbai Suburban31-12-2018 00:00:00
Redevelopment Of Divya Jyoti Co-Operative Housing Society LimitedD V Developers LlpPlot No 51, Cts Nos. 2575 And 2575 1 To 430-12-2021 00:00:00
Kumbhavati NiwasKrishna Bhooraram Purohit465, 4652, 465130-12-2021 00:00:00
Gaurishankar Bungalow RedevelopmentS S RealityCts No.211931-12-2019 00:00:00
Rooprajat EnclaveSiddhivinayak Developers55 5730-12-2021 00:00:00
RudranshSpa Jain Real Estate Private LimitedPlot No 122 Cts No 2527 2527 1 To 4 Village Eksar31-12-2017 00:00:00
TatvaGitanjali Infratech Limited68/A/131-12-2018 00:00:00
Shri Hari BuildingShri Neelkanth DevelopersCts No 265531-01-2019 00:00:00
Vklal Hari Phase IVeekaylal Investment Company Private Limited230830-12-2025 00:00:00
Samet Sikar MahalKothari Construction Company353, 351, 351/1 To 1631-12-2018 00:00:00
Parmarth Niketan - Redevelopment Of Mani BhuvanJ V Constructions & Developers2688/ 1 To 9, 268831-12-2019 00:00:00
Shashwat ResidencyRushi Realty India Pvt Ltd8, 13, 14/1, 14, 9, Cts No 7, 14/2, 10/1 To 6, 15/1 Cts No 2770 Final Plot No 7-B30-12-2022 00:00:00
Signature-IChaubey Realties Private LimitedC.T.S No. 2698/2697/2700/2699/2699-1 To331-12-2021 00:00:00
Navkar HeightsNavkar Groups Private Limited214130-12-2021 00:00:00
Maa EnrichDhanish Jitendra Shah46/1To431-05-2018 00:00:00
Bldg No.1 Dahisar Sai Sadan Chs LtdTrumph Developers2334 Pt31-12-2019 00:00:00
Dahisar Sunderbaug Co-Op Housing Society Ltd.Rishabraj Estate Developers Pvt Ltd951 And 951/131-12-2018 00:00:00
Sbies Geetanjali ChslB.Chopda Construction Pvt LtdCts No. 2710 A, Old Cts 2710 And 271131-07-2019 00:00:00
Aditya Aryan / EjajDinesh C Agarwal2334/2/A And B, 2303/1, Cts 2301/5 To C, 2334/1 And 331-03-2018 00:00:00
SanskritiJem And Associates2497, 2497/1 To 431-01-2021 00:00:00
Park ResidencyPavan Sheth And Associates Aop105-A And 10631-01-2021 00:00:00
Rakhi Tower Phase 2 9Th To 11Th Floor PartWestern DevelopmentsMumbai Suburban, 40006621-12-2020 00:00:00
Rakhi Tower Phase 1Western Developments332A 332B 332C 332D 332E21-12-2019 00:00:00
Radha Madhav ChslShri Krishna Chaitanya EnterprisesCts No 17330-09-2018 00:00:00
Sankeshwar DarshanM/S. Rishabraj Balaji Infra267930-10-2023 00:00:00
Rite Nectar Phase IiRite Developers Pvt. Ltd.Cts No 212 B30-09-2022 00:00:00
Sky City Tower FIncline Realty Private LimitedCts No 107 E Of Village Magathane30-06-2027 00:00:00
Ashtavinayak NxAshtavinayak InfrastructureGut No 19 Cts No 932331-03-2019 00:00:00
Unicorn HeightsTeoama Infrastructure Private LimitedCts No 19/327, Plot No Am-330-06-2025 00:00:00
Shiv LilamNavkarmik Infra & Development Private Limited285 B 101-03-2025 00:00:00
KrishnaSunit EnterpriseCts No 1142 1143 114730-12-2028 00:00:00
Aakasha ChslTrivenidevelopers462 462/1 To 531-12-2017 00:00:00
Shree Sai Prasad Sra Chs LtdArjun WaghmareBorivali West31-12-2018 00:00:00
Shri Vallabh ResidencySwadhinta Builders Llp 1326/A/126-01-2022 00:00:00
Rite PerintoRite Developers Pvt. Ltd.Cts No 225 Part30-03-2021 00:00:00
New Shiv Krupa Chsl Triveni ContourTriveni DevelopersMumbai Suburban, 40006631-03-2018 00:00:00
ZenonEntity Developers Private LimitedDattapada Road, Opp Dattapada Bmc School31-12-2025 00:00:00
Borivali New Roma Sadan ChslSumukh Infraproject659.2030-06-2023 00:00:00
Proposed Redevelopment Of Prakashkunj ChslYash Realtors & Developers2637 1 - 5, 263730-12-2023 00:00:00
Redevelopment Of Pravesh ChslPranav Constructions LimitedF P No 2428-11-2023 00:00:00
Rishabraj DivineM/S. Rishabraj Balaji Infra2758, 2758/1 To 630-10-2023 00:00:00
Construction Of 86 Tenements Out Of 430 Mig Tenements Of Old Magathane Village BorivaliMaharashtra Housing And Area Development AuthorityCts No 183 Pt 184 Pt 185 Pt 186 Pt 187 Pt 196 Pt 197 Pt And 201 Pt13-12-2018 00:00:00
Adinath HeightsShri Neelkanth Developers2740 ,274131-03-2026 00:00:00
Kashi BhuvanBharat V Kenny1011/A31-12-2024 00:00:00
Apurva Vaishali ChslDiravya Developers Llp263630-09-2025 00:00:00
Bhavik Darshan Chs Ltd And Gajmukh Chs LtdKonark Structural Engineers Private Limited2456/A, 2456/B, 2456/B/1, 2456/B/2, 2456/B/331-12-2027 00:00:00
Teenmurty SummitM/S Teenmurty Summit Realty Llp19731-07-2022 00:00:00
Elite TowerElite Construction Co.400066, Mumbai Suburban31-07-2023 00:00:00
Suresh SadanJaverben Nenshi ChhadvaPlot No 22 Of Dadar Matunga Estate Cs No 444/10 Of Matunga Division31-12-2018 00:00:00
AudumbarVas Builder & Developers265831-12-2019 00:00:00
Patel Associates A/C New BelevuePatel Associates A/C New BelevueTps Ii Borivali, Cts No.11, F.P. 8A30-06-2021 00:00:00
Jaliyan Heights BorivaliJaliyan Developer2507, 2506/1, 2508, 2507/1, 2509, 2509/1, Plot No.134 And 184 Ol S No.177, 250630-07-2021 00:00:00
Borivali Sai Smruti Cooperative Housing Society LimitedM/S Sapphire Developers2351A30-06-2027 00:00:00
Harsiddhi Sadan Chs LtdRk Construction20830-06-2025 00:00:00
Arvind NiwasHridyaa Infraprojects LlpFp No. 71J Of Tps Ii Cts No 457, 457/1 To 457/430-06-2025 00:00:00
Nl Park ViewBeautiful Properties Private Limited80G ,80H30-05-2028 00:00:00
Pratham - By ShraddhaShraddha Prime Projects LimitedCts No.-197(Pt),Survey No.-5131-12-2029 00:00:00
66 Aventus AvenueAventus Infrastructure Llp2696, 2696/1 To 2531-12-2029 00:00:00
Nicco Vanashri And Nicco HeightsNew India Construction CompanyF.P.No. 109 Of Tps Borivali No Iii31-12-2028 00:00:00
Shiv Guru TowerRajlaxmi Developers905A ,90631-12-2027 00:00:00
Opal AvenueGhori Developers312, 312/1 To 731-12-2026 00:00:00
Poonam ChslDigam Lifespaces Llp2718, 2718/1, 2718/2, 2718/331-10-2027 00:00:00
Dahisar Sagar Co-Operative Housing Society LimitedM/S. Trilogy Realtors Private Limited282431-12-2029 00:00:00
101 BoulevardH M Developers117 ,118, 118/ 1 To 330-06-2026 00:00:00
PavapuriKum Kum Enterprises1231-12-2026 00:00:00
Borivali Kesar Kripa Chs LtdBorivali Kesar Kripa Chs Ltd1731-12-2027 00:00:00
Chaitanya Om Shivam - Om Shivam Premises CslChaitanya Enterprises680A/1/ 831-05-2024 00:00:00
Monte Verita West TowerB G Shirke Redevelopment And Gas P L259 26031-03-2027 00:00:00
MatruchhayaM/S. Rishabraj Balaji Infra2680/1 To 9, 268031-12-2024 00:00:00
Project Details
  • Project:
    Radha Madhav Chsl
  • Location:
  • Cts No 173
  • Const. Stage:
    Ongoing
  • Possession:
    30 Sep 2018
Developer Details

  • Developer:
    Shri Krishna Chaitanya Enterprises
  • Phone:
  • Address:
  • Radhakunj Bunglow
Project RERA Details
MAHA REARA No: P51800005539
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Neocon Infrastructure Services Pvt Ltd
Funding Bank
Proposed Possession 30 Sep 2018
Revised Possession 30 Sep 2018
Extended Possession 30 Sep 2019
Litigations No Litigations
Last Modified 03 Oct 2018
Last Retrived 26 Jul 2025
Radha Madhav Chsl QR Code
Radha Madhav Chsl
MahaRERA - P51800005539
Apartment Details & Configuration
TypeArea
2 BHK61.75 Sq.mts. ( 665 Sq.ft. )
2 BHK63.1 Sq.mts. ( 679 Sq.ft. )
2 BHK68.42 Sq.mts. ( 736 Sq.ft. )
2 BHK69.47 Sq.mts. ( 748 Sq.ft. )
4 BHK130.17 Sq.mts. ( 1401 Sq.ft. )
4 BHK133.07 Sq.mts. ( 1432 Sq.ft. )
2 BHK61.61 Sq.mts. ( 663 Sq.ft. )
2 BHK67.66 Sq.mts. ( 728 Sq.ft. )
2 BHK69.49 Sq.mts. ( 748 Sq.ft. )
2 BHK81.08 Sq.mts. ( 873 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Radha Madhav Chsllast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
--
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
--
Landscaping & Tree Planting100% completed
95% Complete
--
Open Parking100% completed
95% Complete
--
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
--
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
--
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
--
Water Supply100% completed
95% Complete
--
Buildings / Wings in Radha Madhav Chsl
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Radha Madhav Chsl by Shri Krishna Chaitanya Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

53589 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

104 apartments in total
Total
104
Booked
102
Available
2

Saleable Area Statistics (Sq. ft.)

77282 Total
Total
77282
Booked
75744
Available
1537
Total 104 apartments in project. 102 apartments booked. 98% apartments booked.
Total 77282 Sq.ft. saleable area. 75744 saleable area booked.
98% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJan 1900151010241
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK61.75 Sq.mts. ( 665 Sq.ft. )13
12 Booked92% Booked
92% Booked
2 BHK63.1 Sq.mts. ( 679 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK68.42 Sq.mts. ( 736 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK69.47 Sq.mts. ( 748 Sq.ft. )12
12 Booked100% Booked
100% Booked
4 BHK130.17 Sq.mts. ( 1401 Sq.ft. )1
1 Booked100% Booked
100% Booked
4 BHK133.07 Sq.mts. ( 1432 Sq.ft. )1
1 Booked100% Booked
100% Booked
53 total apartments / 52 apartments booked. 98% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJan 1900141010141
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK61.61 Sq.mts. ( 663 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK67.66 Sq.mts. ( 728 Sq.ft. )12
12 Booked100% Booked
100% Booked
2 BHK69.49 Sq.mts. ( 748 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK81.08 Sq.mts. ( 873 Sq.ft. )13
12 Booked92% Booked
92% Booked
51 total apartments / 50 apartments booked. 98% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shri Krishna Chaitanya Enterprises
for Project
Radha Madhav Chsl
last updated on 26 Jul 2025 as per information obtained from MARA RERA.