Project overview

Pushp Vinod-3 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800003609. Pushp Vinod-3 is located at Mumbai Suburban, 400092. This is a On-Going Project being developed by Vas Infrastructure Ltd..

Pushp Vinod-3 has 1 BHK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 394 to 994 Sq.ft. Carpet. The Project has total 133 of which 62 are currently available for sale.

Pushp Vinod-3 is being developed on a total land area of 24845 Sq.ft. out of which 3764 Sq.ft. i.e 15% is reserved for recreational purposes. Pushp Vinod-3 has 4 Wings / Towers Phase 1,Phase 2,Phase 3,Phase 4

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Pushp Vinod-3
  • Location:
  • Mumbai Suburban, 400092
  • Const. Stage:
    On-Going Project
  • Possession:
    15 Dec 2015
Developer Details

  • Developer:
    Vas Infrastructure Ltd.
  • Phone:
  • Address:
  • 757 / 758, Jwala Estate, S.V. Road, Kora Kendra, Soniwadi, 400092
Project RERA Details
MAHA REARA No: P51800003609
Project Type Residential
RERA Project Status On-Going Project
Funding Bank Syndicate Bank
Proposed Possession 15 Dec 2015
Revised Possession 15 Dec 2021
Extended Possession
Litigations Yes
Last Modified
Last Retrived 28 Jul 2025
Pushp Vinod-3 QR Code
Pushp Vinod-3
MahaRERA - P51800003609
Apartment Details & Configuration
TypeArea
1 BHK33.41 Sq.mts. ( 360 Sq.ft. )
1 BHK45.47 Sq.mts. ( 489 Sq.ft. )
1 BHK47.55 Sq.mts. ( 512 Sq.ft. )
1 BHK57.26 Sq.mts. ( 616 Sq.ft. )
1 RK35.75 Sq.mts. ( 385 Sq.ft. )
1 Rk39.04 Sq.mts. ( 420 Sq.ft. )
1 RK42.18 Sq.mts. ( 454 Sq.ft. )
1 RK22.5 Sq.mts. ( 242 Sq.ft. )
1 RK24.76 Sq.mts. ( 267 Sq.ft. )
1 RK26.33 Sq.mts. ( 283 Sq.ft. )
1 RK27.96 Sq.mts. ( 301 Sq.ft. )
1 RK28.84 Sq.mts. ( 310 Sq.ft. )
1 RK32.3 Sq.mts. ( 348 Sq.ft. )
1 BHK47.06 Sq.mts. ( 507 Sq.ft. )
1 BHK53.03 Sq.mts. ( 571 Sq.ft. )
1 BHK57 Sq.mts. ( 614 Sq.ft. )
1 BHK59.78 Sq.mts. ( 643 Sq.ft. )
1 BHK59.98 Sq.mts. ( 646 Sq.ft. )
1 BHK60.89 Sq.mts. ( 655 Sq.ft. )
1 BHK63.73 Sq.mts. ( 686 Sq.ft. )
1 BHK67.89 Sq.mts. ( 731 Sq.ft. )
1 BHK68.36 Sq.mts. ( 736 Sq.ft. )
1 BHK71.12 Sq.mts. ( 766 Sq.ft. )
1RK59.14 Sq.mts. ( 637 Sq.ft. )
1RK59.38 Sq.mts. ( 639 Sq.ft. )
1RK53.22 Sq.mts. ( 573 Sq.ft. )
1RK53.38 Sq.mts. ( 575 Sq.ft. )
1RK52.82 Sq.mts. ( 569 Sq.ft. )
1RK41.19 Sq.mts. ( 443 Sq.ft. )
1 BHK33.34 Sq.mts. ( 359 Sq.ft. )
1 BHK33.6 Sq.mts. ( 362 Sq.ft. )
1 BHK36.6 Sq.mts. ( 394 Sq.ft. )
1 BHK39.89 Sq.mts. ( 429 Sq.ft. )
1 BHK64.42 Sq.mts. ( 693 Sq.ft. )
2 BHK67.45 Sq.mts. ( 726 Sq.ft. )
2 BHK68.6 Sq.mts. ( 738 Sq.ft. )
3 BHK89.73 Sq.mts. ( 966 Sq.ft. )
3 BHK92.36 Sq.mts. ( 994 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Pushp Vinod-3last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
As Mcgm Norms
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Mcgm Norms
Landscaping & Tree Planting100% completed
95% Complete
As Mcgm Norms
Open Parking100% completed
95% Complete
As Mcgm Norms
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
As Mcgm Norms
Solid Waste Management And Disposal100% completed
95% Complete
As Mcgm Norms
Storm Water Drains100% completed
95% Complete
As Mcgm Norms
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
As Mcgm Norms
Water Conservation, Rain water Harvesting100% completed
95% Complete
As Mcgm Norms
Water Supply100% completed
95% Complete
As Mcgm Norms
Buildings / Wings in Pushp Vinod-3
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Pushp Vinod-3 by Vas Infrastructure Ltd.last updated on 28 Jul 2025 as per information obtained from MARA RERA.

24845 Sq. ft.

Project Area

3764 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

133 apartments in total
Total
133
Booked
71
Available
62

Saleable Area Statistics (Sq. ft.)

68450 Total
Total
68450
Booked
28293
Available
40156
Total 133 apartments in project. 71 apartments booked. 53% apartments booked.
Total 68450 Sq.ft. saleable area. 28293 saleable area booked.
41% area booked.

Phase 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Phase 1Jan 19001411121236
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.41 Sq.mts. ( 360 Sq.ft. )11
11 Booked100% Booked
100% Booked
1 BHK45.47 Sq.mts. ( 489 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK47.55 Sq.mts. ( 512 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK57.26 Sq.mts. ( 616 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 RK35.75 Sq.mts. ( 385 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 Rk39.04 Sq.mts. ( 420 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 RK42.18 Sq.mts. ( 454 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 RK22.5 Sq.mts. ( 242 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 RK24.76 Sq.mts. ( 267 Sq.ft. )11
11 Booked100% Booked
100% Booked
1 RK26.33 Sq.mts. ( 283 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 RK27.96 Sq.mts. ( 301 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 RK28.84 Sq.mts. ( 310 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 RK32.3 Sq.mts. ( 348 Sq.ft. )10
10 Booked100% Booked
100% Booked
66 total apartments / 66 apartments booked. 100% apartments booked.
Work Description in Building Phase 1Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Phase 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Phase 2Jan 19000000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK47.06 Sq.mts. ( 507 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK53.03 Sq.mts. ( 571 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK57 Sq.mts. ( 614 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK59.78 Sq.mts. ( 643 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK59.98 Sq.mts. ( 646 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK60.89 Sq.mts. ( 655 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK63.73 Sq.mts. ( 686 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK67.89 Sq.mts. ( 731 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK68.36 Sq.mts. ( 736 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK71.12 Sq.mts. ( 766 Sq.ft. )1
None Booked0% Booked
0% Booked
1RK59.14 Sq.mts. ( 637 Sq.ft. )1
None Booked0% Booked
0% Booked
1RK59.38 Sq.mts. ( 639 Sq.ft. )1
None Booked0% Booked
0% Booked
1RK53.22 Sq.mts. ( 573 Sq.ft. )1
None Booked0% Booked
0% Booked
1RK53.38 Sq.mts. ( 575 Sq.ft. )1
None Booked0% Booked
0% Booked
1RK52.82 Sq.mts. ( 569 Sq.ft. )1
1 Booked100% Booked
100% Booked
1RK41.19 Sq.mts. ( 443 Sq.ft. )1
None Booked0% Booked
0% Booked
18 total apartments / 5 apartments booked. 27% apartments booked.
Work Description in Building Phase 2Completion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Phase 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Phase 3Jan 19004000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.34 Sq.mts. ( 359 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK33.6 Sq.mts. ( 362 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK36.6 Sq.mts. ( 394 Sq.ft. )3
None Booked0% Booked
0% Booked
1 BHK39.89 Sq.mts. ( 429 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK64.42 Sq.mts. ( 693 Sq.ft. )3
None Booked0% Booked
0% Booked
2 BHK67.45 Sq.mts. ( 726 Sq.ft. )3
None Booked0% Booked
0% Booked
2 BHK68.6 Sq.mts. ( 738 Sq.ft. )3
None Booked0% Booked
0% Booked
3 BHK89.73 Sq.mts. ( 966 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK92.36 Sq.mts. ( 994 Sq.ft. )2
None Booked0% Booked
0% Booked
19 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Phase 3Completion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Phase 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Phase 4Jan 19006000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.6 Sq.mts. ( 394 Sq.ft. )5
None Booked0% Booked
0% Booked
1 BHK39.89 Sq.mts. ( 429 Sq.ft. )5
None Booked0% Booked
0% Booked
1 BHK64.42 Sq.mts. ( 693 Sq.ft. )5
None Booked0% Booked
0% Booked
2 BHK67.45 Sq.mts. ( 726 Sq.ft. )5
None Booked0% Booked
0% Booked
2 BHK68.6 Sq.mts. ( 738 Sq.ft. )5
None Booked0% Booked
0% Booked
3 BHK92.36 Sq.mts. ( 994 Sq.ft. )5
None Booked0% Booked
0% Booked
30 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Phase 4Completion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Vas Infrastructure Ltd.
for Project
Pushp Vinod-3
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation