Project overview

Proxima Residences is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800005153. Proxima Residences is located at 1651A/1. This is a Ongoing being developed by Aviation Hotels Pvt. Ltd..

Proxima Residences has 2 BHK & 3 BHK Apartments with carpet areas ranging from 1104 to 1072 Sq.ft. Carpet. The Project has total 335 of which 82 are currently available for sale.

Proxima Residences is being developed on a total land area of 161630 Sq.ft. out of which 40036 Sq.ft. i.e 25% is reserved for recreational purposes. Proxima Residences has 7 Wings / Towers A Wing,B Wing,C Wing,D Wing,E Wing,F Wing,G Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Proxima Residences
  • Location:
  • 1651A/1
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2022
Developer Details

  • Developer:
    Aviation Hotels Pvt. Ltd.
  • Phone:
  • Address:
  • Dudhwala Complex
Project RERA Details
MAHA REARA No: P51800005153
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Mandviwala Qutub & Associates
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2022
Revised Possession 30 Dec 2022
Extended Possession 30 Dec 2023
Litigations No Litigations
Last Modified 21 Aug 2023
Last Retrived 26 Jul 2025
Proxima Residences QR Code
Proxima Residences
MahaRERA - P51800005153
Apartment Details & Configuration
TypeArea
2 BHK75.9 Sq.mts. ( 817 Sq.ft. )
2 BHK77.75 Sq.mts. ( 837 Sq.ft. )
2 BHK78.66 Sq.mts. ( 847 Sq.ft. )
2 BHK80.51 Sq.mts. ( 867 Sq.ft. )
3 BHK99.58 Sq.mts. ( 1072 Sq.ft. )
3 BHK102.57 Sq.mts. ( 1104 Sq.ft. )
1 BHK40.91 Sq.mts. ( 440 Sq.ft. )
2 BHK77.93 Sq.mts. ( 839 Sq.ft. )
3 BHK101.38 Sq.mts. ( 1091 Sq.ft. )
3 BHK105.43 Sq.mts. ( 1135 Sq.ft. )
MPR20.47 Sq.mts. ( 220 Sq.ft. )
MPR24.72 Sq.mts. ( 266 Sq.ft. )
MPR25.92 Sq.mts. ( 279 Sq.ft. )
MPR31.43 Sq.mts. ( 338 Sq.ft. )
2 BHK75.86 Sq.mts. ( 817 Sq.ft. )
3 BHK124.76 Sq.mts. ( 1343 Sq.ft. )
2 BHK77.67 Sq.mts. ( 836 Sq.ft. )
2 BHK80.17 Sq.mts. ( 863 Sq.ft. )
3 BHK99.83 Sq.mts. ( 1075 Sq.ft. )
4 BHK118.89 Sq.mts. ( 1280 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Proxima Residenceslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space25% completed
25% Complete
In Process
Community Buildings50% completed
50% Complete
Club House
Electrical Meter Room, Sub-Station, Receiving Station60% completed
60% Complete
In Process
Energy management30% completed
30% Complete
In Process
Fire Protection And Fire Safety Requirements40% completed
40% Complete
In Process
Landscaping & Tree Planting
In Process
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
In Process
Solid Waste Management And Disposal
In Process
Storm Water Drains20% completed
20% Complete
In Process
Street Lighting
In Process
SWIMMING POOL50% completed
50% Complete
In Process
Treatment And Disposal Of Sewage And Sullage Water58% completed
58% Complete
In Process
Water Conservation, Rain water Harvesting70% completed
70% Complete
In Process
Water Supply70% completed
70% Complete
In Process
Buildings / Wings in Proxima Residences
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Proxima Residences by Aviation Hotels Pvt. Ltd.last updated on 26 Jul 2025 as per information obtained from MARA RERA.

161630 Sq. ft.

Project Area

40036 Sq. ft.

Recreational Open Space

Total 7

Wings / Towers in Project

Apartments Statistics

335 apartments in total
Total
335
Booked
253
Available
82

Saleable Area Statistics (Sq. ft.)

290558 Total
Total
290558
Booked
234308
Available
56250
Total 335 apartments in project. 253 apartments booked. 75% apartments booked.
Total 290558 Sq.ft. saleable area. 234308 saleable area booked.
81% area booked.

A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A WingJan 19001313100132
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.9 Sq.mts. ( 817 Sq.ft. )13
9 Booked69% Booked
69% Booked
2 BHK77.75 Sq.mts. ( 837 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK78.66 Sq.mts. ( 847 Sq.ft. )13
9 Booked69% Booked
69% Booked
2 BHK80.51 Sq.mts. ( 867 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK99.58 Sq.mts. ( 1072 Sq.ft. )12
10 Booked83% Booked
83% Booked
3 BHK102.57 Sq.mts. ( 1104 Sq.ft. )11
9 Booked81% Booked
81% Booked
51 total apartments / 39 apartments booked. 76% apartments booked.
Work Description in Building A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress40% done
40% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress81% done
81% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress75% done
75% Booked
Sanitary Fittings within the flats / premises
work-in-progress75% done
75% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B WingJan 19001313100100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.91 Sq.mts. ( 440 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK77.93 Sq.mts. ( 839 Sq.ft. )13
13 Booked100% Booked
100% Booked
3 BHK101.38 Sq.mts. ( 1091 Sq.ft. )13
11 Booked84% Booked
84% Booked
3 BHK105.43 Sq.mts. ( 1135 Sq.ft. )2
1 Booked50% Booked
50% Booked
MPR20.47 Sq.mts. ( 220 Sq.ft. )10
3 Booked30% Booked
30% Booked
MPR24.72 Sq.mts. ( 266 Sq.ft. )11
3 Booked27% Booked
27% Booked
MPR25.92 Sq.mts. ( 279 Sq.ft. )10
3 Booked30% Booked
30% Booked
MPR31.43 Sq.mts. ( 338 Sq.ft. )10
3 Booked30% Booked
30% Booked
70 total apartments / 38 apartments booked. 54% apartments booked.
Work Description in Building B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress30% done
30% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress70% done
70% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress74% done
74% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress90% done
90% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingJan 19001313100132
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.9 Sq.mts. ( 817 Sq.ft. )13
9 Booked69% Booked
69% Booked
2 BHK77.75 Sq.mts. ( 837 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK78.66 Sq.mts. ( 847 Sq.ft. )13
12 Booked92% Booked
92% Booked
2 BHK80.51 Sq.mts. ( 867 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK99.58 Sq.mts. ( 1072 Sq.ft. )12
11 Booked91% Booked
91% Booked
3 BHK102.57 Sq.mts. ( 1104 Sq.ft. )11
10 Booked90% Booked
90% Booked
51 total apartments / 43 apartments booked. 84% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress50% done
50% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress50% done
50% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress75% done
75% Booked
Sanitary Fittings within the flats / premises
work-in-progress75% done
75% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

D Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
D WingJan 19001313100132
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.9 Sq.mts. ( 817 Sq.ft. )13
12 Booked92% Booked
92% Booked
2 BHK77.75 Sq.mts. ( 837 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK78.66 Sq.mts. ( 847 Sq.ft. )13
12 Booked92% Booked
92% Booked
2 BHK80.51 Sq.mts. ( 867 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK99.58 Sq.mts. ( 1072 Sq.ft. )12
12 Booked100% Booked
100% Booked
3 BHK102.57 Sq.mts. ( 1104 Sq.ft. )11
10 Booked90% Booked
90% Booked
51 total apartments / 48 apartments booked. 94% apartments booked.
Work Description in Building D WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress60% done
60% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress60% done
60% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress84% done
84% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress80% done
80% Booked
Sanitary Fittings within the flats / premises
work-in-progress80% done
80% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

E Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
E WingJan 19001313100100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.86 Sq.mts. ( 817 Sq.ft. )24
18 Booked75% Booked
75% Booked
3 BHK124.76 Sq.mts. ( 1343 Sq.ft. )13
13 Booked100% Booked
100% Booked
37 total apartments / 31 apartments booked. 83% apartments booked.
Work Description in Building E WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress20% done
20% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress50% done
50% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress50% done
50% Booked

F Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
F WingJan 1900131310070
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK77.67 Sq.mts. ( 836 Sq.ft. )11
9 Booked81% Booked
81% Booked
2 BHK80.17 Sq.mts. ( 863 Sq.ft. )11
8 Booked72% Booked
72% Booked
3 BHK99.83 Sq.mts. ( 1075 Sq.ft. )1
1 Booked100% Booked
100% Booked
4 BHK118.89 Sq.mts. ( 1280 Sq.ft. )1
1 Booked100% Booked
100% Booked
24 total apartments / 19 apartments booked. 79% apartments booked.
Work Description in Building F WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress20% done
20% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress50% done
50% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress50% done
50% Booked

G Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
G WingJan 19001313100132
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.9 Sq.mts. ( 817 Sq.ft. )13
8 Booked61% Booked
61% Booked
2 BHK77.75 Sq.mts. ( 837 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK78.66 Sq.mts. ( 847 Sq.ft. )13
8 Booked61% Booked
61% Booked
2 BHK80.51 Sq.mts. ( 867 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK99.58 Sq.mts. ( 1072 Sq.ft. )12
10 Booked83% Booked
83% Booked
3 BHK102.57 Sq.mts. ( 1104 Sq.ft. )11
7 Booked63% Booked
63% Booked
51 total apartments / 35 apartments booked. 68% apartments booked.
Work Description in Building G WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress20% done
20% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress50% done
50% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress50% done
50% Booked
Channel Partners
Channel Partners Registered by Developer
Aviation Hotels Pvt. Ltd.
for Project
Proxima Residences
last updated on 26 Jul 2025 as per information obtained from MARA RERA.