Project overview

Promenade - The Address is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800000201. Promenade - The Address is located at Bk/0Svgkxv6euhzlqf3n2ly6+2Hiu+Opdejycbkgkm3rtfxir0hzxw6yjnwlqfwpd8igyrdzp7n6pau5vmcwua==. This is a Ongoing being developed by Wadhwa Residency Pvt Ltd.

Promenade - The Address has 2 BHK Apartments with carpet areas ranging from 652 to 659 Sq.ft. Carpet. The Project has total 507 of which 10 are currently available for sale.

Promenade - The Address is being developed on a total land area of 22243 Sq.ft. Promenade - The Address has 4 Wings / Towers Promenade 1,Promenade 2,Promenade 3,Promenade 4

ProjectDeveloperLocationPossession
The Trees, OriginsGodrej Properties LimitedRvaorlvtchbhxr7nb6iipa==30-06-2023 00:00:00
The Trees Residential Phase 2Godrej Properties LimitedJphl/0Ldoq8lp9ijqpcwhq==30-06-2022 00:00:00
The Trees, Residential Phase 1Godrej Properties LimitedAqh1konudk+Waisk3cod9w==30-06-2022 00:00:00
Prime VistaRupvakula Properties Pvt. LtdDlmqw5/2Kg8e24eg0241qkpcdi0y/Alqppz7dpuosia=30-03-2023 00:00:00
Mayfair The ViewMayfair Housing1Gqekzyxshbbvm91ji5hc77sk6txhxunrmr1+Lwuohaoytqeyqz/A8lrriafw3xj30-12-2024 00:00:00
Bhuvneshwar VintageS P InfraXyh1kjyee44oznopqsil0sr1ru8pydbjalrlxokzudsxi6q3wouhg3dwrfrvhf07xwpultlglxzdnepvgw7ivg==30-03-2023 00:00:00
Promenade - The AddressWadhwa Residency Pvt LtdBk/0Svgkxv6euhzlqf3n2ly6+2Hiu+Opdejycbkgkm3rtfxir0hzxw6yjnwlqfwpd8igyrdzp7n6pau5vmcwua==31-12-2019 00:00:00
Bhaveshwar Arcade AnnexeBhaveshwar Properties Pvt Ltd082Bd14eqih6sptvcepbfxeya4opu4mwtggdqbuqp4q=30-11-2018 00:00:00
Neelkanth Enclave C Wing ArihantBhaveshwar Properties Pvt LtdNc3ev6f1vgscbaxpmlkwzg==30-11-2019 00:00:00
Kashish Park GhatkoparLadam Homes Pvt Ltd.Yzwr+Ann9wryoz9ycnfkwnvlhzermqk8ui0idxy3wfu=30-06-2021 00:00:00
Ashok Odyssey - B WingSanyam Realtors Private LimitedUpl+Y5uj5nk9cn26t0azjg==30-12-2023 00:00:00
Om PriyadarshaniAakruti EnterprisesL57vgw9nujvkas0+T/Nl1a==30-09-2026 00:00:00
Redevlopement Of Sbi Madhur Milan ChslHeritage Lifestyles And Developers Pvt. Ltd.Eu0k4tp/9Vmkz4fsa54neiymjgsrotykqgx5pgxrpaucgsgap9dop/L+V7pbbsfb44wghcolyqaurvajygxeua==31-05-2026 00:00:00
Suvarnatula Chs Sai AdityarajAdityaraj Builders And DevelopersZu85hfkrjznimuzffh0j/W==31-12-2025 00:00:00
Swastik ShivaaySwastik RealtorsEd5/O/L1i9x1wyyxvpoo9co5abjgpsxenxj/Doqjzajtcksf/X1qjyodbserx4ii31-12-2027 00:00:00
SARVODAYA HEIGHTSCMG ENTERPRISES2243-A/9, 2243A/7, 2243-A/801-09-2025 00:00:00
Alag OliveAlag Olive LlpFayx1pmj4/9Psqrjh0dkma==31-12-2024 00:00:00
Kaveri HeightsShree Mishal Sundaram Realty Ventures LlpSant Gyaneshwar Marg, Pant Nagar31-12-2024 00:00:00
Swastik AvighnaSwastik RealtorsL4tk2gnukpflmugqhkzq/Pd03vqkbfk4p34t3alt6vk=31-12-2026 00:00:00
Royal OrchidShri Ganesh DevelopersW1lus3/Dkgczfc1rpo16rb+7Ogqccjzb93ak4mbidws=31-12-2019 00:00:00
Atmiya LuxuriaAkshar Builders And DeveloperPqakqbhgkrjnk521yh3a4g==16-10-2021 00:00:00
Neelkanth Enclave D Wing SiddharthaBhaveshwar Properties Pvt LtdNc3ev6f1vgscbaxpmlkwzg==30-06-2024 00:00:00
Prime Vista Phase - 2Paan Infra LlpWxhiv+M/Yjmppemyfdtntg==30-06-2028 00:00:00
Neelyog RegentRatan Builders0Z0uunv70y55bmaoaffzub3441nwlqmmjkhr6xdqxh0=31-03-2028 00:00:00
Ashok Odyssey - C WingSanyam Realtors Private LimitedUpl+Y5uj5nk9cn26t0azjg==30-12-2023 00:00:00
Ashok Odyssey - A WingSanyam Realtors Private LimitedUpl+Y5uj5nk9cn26t0azjg==30-12-2023 00:00:00
Arihant Neminath SkyS. P. Infra31-12-2028 00:00:00
Damji Shamji Corporate Square - A WingCoronate ConstructionsCihqvgkzh/3Hkamxxpqpma==31-05-2019 00:00:00
Neelyog VeydaantaRatan Builders7Ftghssnhfiousvqcal/Bjrrpby3yxukxxdrydbe0gf9cpvfu7npsd8w//Qjwdgfqmwy+W5rdx1/Tupje/Hcjw==30-03-2023 00:00:00
Damji Shamji Corporate Square - Wing CCoronate ConstructionsZyty42rejntcjdlwy2iqha==30-12-2024 00:00:00
Swastik Disa Corporate Park- 5Th To 9Th FloorSwastik RealtorsHcccklzwssgi8h2u1aokka==31-12-2017 00:00:00
Avis Vraj A Paradise Avi HousingVc4z1gn8pso/Bwwdna1hdw==31-12-2019 00:00:00
Manthan AcropolisManthan Development Corporation5Ky6vi1+Iq9fyww2jt12hq==30-12-2022 00:00:00
Project Details
  • Project:
    Promenade - The Address
  • Location:
  • Bk/0Svgkxv6euhzlqf3n2ly6+2Hiu+Opdejycbkgkm3rtfxir0hzxw6yjnwlqfwpd8igyrdzp7n6pau5vmcwua==
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Wadhwa Residency Pvt Ltd
  • Phone:
  • Address:
  • Platina
Project RERA Details
MAHA REARA No: P51800000201
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sandeep Shikre & Associates
Funding Bank IDFC First Bank Ltd
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession
Litigations No Litigations
Last Modified 10 Jul 2017
Last Retrived 13 Feb 2026
Promenade - The Address QR Code
Promenade - The Address
MahaRERA - P51800000201
Apartment Details & Configuration
TypeArea
2 BHK60.28 Sq.mts. ( 649 Sq.ft. )
2 BHK60.6 Sq.mts. ( 652 Sq.ft. )
2 BHK61.23 Sq.mts. ( 659 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Promenade - The Addresslast updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space95% completed
95% Complete
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Substation/Transformer
Energy management90% completed
90% Complete
Service Provided By Tata
Fire Protection And Fire Safety Requirements95% completed
95% Complete
As Per Cfo Noc
Landscaping & Tree Planting95% completed
95% Complete
As Per Architect Design
Open Parking90% completed
90% Complete
Rcc Work Completed
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
Sewage Treatment Plant
Solid Waste Management And Disposal90% completed
90% Complete
Organic Waste Composter
Storm Water Drains100% completed
95% Complete
As Per Swd Remark
Street Lighting90% completed
90% Complete
As Per Architect Design
Treatment And Disposal Of Sewage And Sullage Water95% completed
95% Complete
Sewage Treatment Plant
Water Conservation, Rain water Harvesting90% completed
90% Complete
Rain Water Harvesting As Per Consultant
Water Supply95% completed
95% Complete
Connection Will Be Received After Oc
Buildings / Wings in Promenade - The Address
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Promenade - The Address by Wadhwa Residency Pvt Ltdlast updated on 13 Feb 2026 as per information obtained from MARA RERA.

22243 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

507 apartments in total
Total
507
Booked
497
Available
10

Saleable Area Statistics (Sq. ft.)

329662 Total
Total
329662
Booked
323173
Available
6489
Total 507 apartments in project. 497 apartments booked. 98% apartments booked.
Total 329662 Sq.ft. saleable area. 323173 saleable area booked.
98% area booked.

Promenade 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Promenade 1Dec 20192312101195
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.28 Sq.mts. ( 649 Sq.ft. )85
85 Booked100% Booked
100% Booked
85 total apartments / 85 apartments booked. 100% apartments booked.
Work Description in Building Promenade 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Promenade 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Promenade 2Dec 201923121024190
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.28 Sq.mts. ( 649 Sq.ft. )171
171 Booked100% Booked
100% Booked
171 total apartments / 171 apartments booked. 100% apartments booked.
Work Description in Building Promenade 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Promenade 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Promenade 3Dec 201923121024189
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.28 Sq.mts. ( 649 Sq.ft. )170
160 Booked94% Booked
94% Booked
170 total apartments / 160 apartments booked. 94% apartments booked.
Work Description in Building Promenade 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Promenade 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Promenade 4Dec 20192312101190
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.6 Sq.mts. ( 652 Sq.ft. )20
20 Booked100% Booked
100% Booked
2 BHK61.23 Sq.mts. ( 659 Sq.ft. )61
61 Booked100% Booked
100% Booked
81 total apartments / 81 apartments booked. 100% apartments booked.
Work Description in Building Promenade 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Wadhwa Residency Pvt Ltd
for Project
Promenade - The Address
last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation