Project overview

Prayag City Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000004381. Prayag City Phase I is located at 100/5 B. This is a New being developed by Prayag Builders And Developers.

Prayag City Phase I has 1 BHK & 2 BHK Apartments with carpet areas ranging from 315 to 458 Sq.ft. Carpet. The Project has total 393 of which 1 are currently available for sale.

Prayag City Phase I is being developed on a total land area of 117328 Sq.ft. out of which 14838 Sq.ft. i.e 13% is reserved for recreational purposes. Prayag City Phase I has 8 Wings / Towers Building 1 Wing A B,Building 2 Wing C D,Building 3 Wing E F,Building 4 Wing G H,Building 5 Wing I J,Building 6 Wing K L,Building 7 Wing M N,Building 8 Wing O

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Prayag City Phase I
  • Location:
  • 100/5 B
  • Const. Stage:
    New
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Prayag Builders And Developers
  • Phone:
  • Address:
  • Shree Sai Sharda Chs
Project RERA Details
MAHA REARA No: P52000004381
Project Type Residential / Group Housing
RERA Project Status New
Architect Swapnil Kalyankar Architects
Funding Bank DCB BANK LIMITED
Proposed Possession 31 Dec 2019
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 09 Sep 2021
Last Retrived 28 Jul 2025
Prayag City Phase I QR Code
Prayag City Phase I
MahaRERA - P52000004381
Apartment Details & Configuration
TypeArea
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )
1 BHK30 Sq.mts. ( 323 Sq.ft. )
1 BHK31.5 Sq.mts. ( 339 Sq.ft. )
1 BHK32.02 Sq.mts. ( 345 Sq.ft. )
1RK20.29 Sq.mts. ( 218 Sq.ft. )
1RK20.82 Sq.mts. ( 224 Sq.ft. )
1RK22.99 Sq.mts. ( 247 Sq.ft. )
2 BHK43.7 Sq.mts. ( 470 Sq.ft. )
1 BHK31.53 Sq.mts. ( 339 Sq.ft. )
1 RK19.95 Sq.mts. ( 215 Sq.ft. )
1RK29.02 Sq.mts. ( 312 Sq.ft. )
1RK29.03 Sq.mts. ( 312 Sq.ft. )
Shop8.09 Sq.mts. ( 87 Sq.ft. )
Shop8.19 Sq.mts. ( 88 Sq.ft. )
Shop8.4 Sq.mts. ( 90 Sq.ft. )
SHOP8.5 Sq.mts. ( 91 Sq.ft. )
SHOP8.51 Sq.mts. ( 92 Sq.ft. )
SHOP9.19 Sq.mts. ( 99 Sq.ft. )
SHOP9.74 Sq.mts. ( 105 Sq.ft. )
SHOP9.92 Sq.mts. ( 107 Sq.ft. )
1 BHK33.08 Sq.mts. ( 356 Sq.ft. )
1 RK16.1 Sq.mts. ( 173 Sq.ft. )
1 BHK31.35 Sq.mts. ( 337 Sq.ft. )
1 BHK33.16 Sq.mts. ( 357 Sq.ft. )
1 BHK33.8 Sq.mts. ( 364 Sq.ft. )
1 BHK35.98 Sq.mts. ( 387 Sq.ft. )
1 BHK33.1 Sq.mts. ( 356 Sq.ft. )
2 BHK38.77 Sq.mts. ( 417 Sq.ft. )
2 BHK41.65 Sq.mts. ( 448 Sq.ft. )
2 BHK42.6 Sq.mts. ( 459 Sq.ft. )
2 BHK45.42 Sq.mts. ( 489 Sq.ft. )
1 BHK29.78 Sq.mts. ( 321 Sq.ft. )
1 BHK30.23 Sq.mts. ( 325 Sq.ft. )
1 BHK31.7 Sq.mts. ( 341 Sq.ft. )
2 BHK39.7 Sq.mts. ( 427 Sq.ft. )
2 BHK42.53 Sq.mts. ( 458 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Prayag City Phase Ilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completetd
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completetd
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking100% completed
95% Complete
Completed
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Prayag City Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Prayag City Phase I by Prayag Builders And Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

117328 Sq. ft.

Project Area

14838 Sq. ft.

Recreational Open Space

Total 8

Wings / Towers in Project

Apartments Statistics

393 apartments in total
Total
393
Booked
392
Available
1

Saleable Area Statistics (Sq. ft.)

120725 Total
Total
120725
Booked
120402
Available
323
Total 393 apartments in project. 392 apartments booked. 99% apartments booked.
Total 120725 Sq.ft. saleable area. 120402 saleable area booked.
100% area booked.

Building 1 Wing A B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 1 Wing A BDec 20195101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )25
25 Booked100% Booked
100% Booked
1 BHK30 Sq.mts. ( 323 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK31.5 Sq.mts. ( 339 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK32.02 Sq.mts. ( 345 Sq.ft. )1
1 Booked100% Booked
100% Booked
1RK20.29 Sq.mts. ( 218 Sq.ft. )10
10 Booked100% Booked
100% Booked
1RK20.82 Sq.mts. ( 224 Sq.ft. )21
21 Booked100% Booked
100% Booked
1RK22.99 Sq.mts. ( 247 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK43.7 Sq.mts. ( 470 Sq.ft. )7
7 Booked100% Booked
100% Booked
74 total apartments / 74 apartments booked. 100% apartments booked.
Work Description in Building Building 1 Wing A BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building 2 Wing C D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 2 Wing C DDec 20195101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )28
28 Booked100% Booked
100% Booked
1 BHK30 Sq.mts. ( 323 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 RK20.29 Sq.mts. ( 218 Sq.ft. )5
5 Booked100% Booked
100% Booked
1RK20.82 Sq.mts. ( 224 Sq.ft. )8
8 Booked100% Booked
100% Booked
45 total apartments / 45 apartments booked. 100% apartments booked.
Work Description in Building Building 2 Wing C DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building 3 Wing E F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 3 Wing E FDec 20195101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )17
17 Booked100% Booked
100% Booked
1 BHK31.5 Sq.mts. ( 339 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK31.53 Sq.mts. ( 339 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 RK19.95 Sq.mts. ( 215 Sq.ft. )4
4 Booked100% Booked
100% Booked
1RK20.82 Sq.mts. ( 224 Sq.ft. )3
3 Booked100% Booked
100% Booked
1RK29.02 Sq.mts. ( 312 Sq.ft. )3
3 Booked100% Booked
100% Booked
1RK29.03 Sq.mts. ( 312 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK43.7 Sq.mts. ( 470 Sq.ft. )7
7 Booked100% Booked
100% Booked
Shop8.09 Sq.mts. ( 87 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop8.19 Sq.mts. ( 88 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop8.4 Sq.mts. ( 90 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP8.5 Sq.mts. ( 91 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP8.51 Sq.mts. ( 92 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP9.19 Sq.mts. ( 99 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP9.74 Sq.mts. ( 105 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP9.92 Sq.mts. ( 107 Sq.ft. )3
3 Booked100% Booked
100% Booked
53 total apartments / 53 apartments booked. 100% apartments booked.
Work Description in Building Building 3 Wing E FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building 4 Wing G H

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 4 Wing G HDec 20195101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.02 Sq.mts. ( 312 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )17
17 Booked100% Booked
100% Booked
1 BHK31.5 Sq.mts. ( 339 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK31.53 Sq.mts. ( 339 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK33.08 Sq.mts. ( 356 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 RK16.1 Sq.mts. ( 173 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 RK19.95 Sq.mts. ( 215 Sq.ft. )5
5 Booked100% Booked
100% Booked
1RK20.82 Sq.mts. ( 224 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK43.7 Sq.mts. ( 470 Sq.ft. )8
8 Booked100% Booked
100% Booked
46 total apartments / 46 apartments booked. 100% apartments booked.
Work Description in Building Building 4 Wing G HCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building 5 Wing I J

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 5 Wing I JDec 20195101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )28
28 Booked100% Booked
100% Booked
1 BHK30 Sq.mts. ( 323 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK31.35 Sq.mts. ( 337 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK33.08 Sq.mts. ( 356 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 RK20.29 Sq.mts. ( 218 Sq.ft. )10
10 Booked100% Booked
100% Booked
1 RK20.82 Sq.mts. ( 224 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 RK22.99 Sq.mts. ( 247 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK43.7 Sq.mts. ( 470 Sq.ft. )4
4 Booked100% Booked
100% Booked
57 total apartments / 57 apartments booked. 100% apartments booked.
Work Description in Building Building 5 Wing I JCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building 6 Wing K L

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 6 Wing K LDec 20195101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )28
28 Booked100% Booked
100% Booked
1 BHK31.35 Sq.mts. ( 337 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK33.16 Sq.mts. ( 357 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK33.8 Sq.mts. ( 364 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK35.98 Sq.mts. ( 387 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 RK30 Sq.mts. ( 323 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 RK22.99 Sq.mts. ( 247 Sq.ft. )2
2 Booked100% Booked
100% Booked
1RK20.29 Sq.mts. ( 218 Sq.ft. )9
9 Booked100% Booked
100% Booked
1RK20.82 Sq.mts. ( 224 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK43.7 Sq.mts. ( 470 Sq.ft. )4
4 Booked100% Booked
100% Booked
57 total apartments / 56 apartments booked. 98% apartments booked.
Work Description in Building Building 6 Wing K LCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building 7 Wing M N

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 7 Wing M NDec 20195101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )24
24 Booked100% Booked
100% Booked
1 BHK30 Sq.mts. ( 323 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK33.1 Sq.mts. ( 356 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK38.77 Sq.mts. ( 417 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK41.65 Sq.mts. ( 448 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK42.6 Sq.mts. ( 459 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK45.42 Sq.mts. ( 489 Sq.ft. )1
1 Booked100% Booked
100% Booked
40 total apartments / 40 apartments booked. 100% apartments booked.
Work Description in Building Building 7 Wing M NCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked

Building 8 Wing O

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 8 Wing ODec 20194101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.31 Sq.mts. ( 315 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK29.78 Sq.mts. ( 321 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK30 Sq.mts. ( 323 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK30.23 Sq.mts. ( 325 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK31.7 Sq.mts. ( 341 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK38.77 Sq.mts. ( 417 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK39.7 Sq.mts. ( 427 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK41.65 Sq.mts. ( 448 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK42.53 Sq.mts. ( 458 Sq.ft. )1
1 Booked100% Booked
100% Booked
21 total apartments / 21 apartments booked. 100% apartments booked.
Work Description in Building Building 8 Wing OCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Prayag Builders And Developers
for Project
Prayag City Phase I
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation