Project overview

PRAJAPATI ORNATE is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000019057. PRAJAPATI ORNATE is located at Plot No 191 To 197 And Plot No 199 To 206. This is a New being developed by PRAJAPATI CONSTRUCTIONS LIMITED.

PRAJAPATI ORNATE has 2 BHK, 3 BHK, SHOP FIRST FLOOR & SHOP GROUND FLOOR Apartments with carpet areas ranging from 314 to 1025 Sq.ft. Carpet. The Project has total 120 of which 35 are currently available for sale.

PRAJAPATI ORNATE is being developed on a total land area of 39732 Sq.ft. out of which 12938 Sq.ft. i.e 33% is reserved for recreational purposes. PRAJAPATI ORNATE has 3 Wings / Towers A Wing,B Wing,C Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    PRAJAPATI ORNATE
  • Location:
  • Plot No 191 To 197 And Plot No 199 To 206
  • Const. Stage:
    New
  • Possession:
    30 Dec 2025
Developer Details

  • Developer:
    PRAJAPATI CONSTRUCTIONS LIMITED
  • Phone:
  • Address:
  • Prajapati Constructions Ltd
Project RERA Details
MAHA REARA No: P52000019057
Project Type Others
RERA Project Status New
Architect Ms Soyuz Talib Architect
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Dec 2025
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 28 Dec 2018
Last Retrived 14 Feb 2026
PRAJAPATI ORNATE QR Code
PRAJAPATI ORNATE
MahaRERA - P52000019057
Apartment Details & Configuration
TypeArea
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )
3 BHK82.91 Sq.mts. ( 892 Sq.ft. )
SHOP FIRST FLOOR29.14 Sq.mts. ( 314 Sq.ft. )
SHOP FIRST FLOOR25.39 Sq.mts. ( 273 Sq.ft. )
SHOP FIRST FLOOR28.53 Sq.mts. ( 307 Sq.ft. )
SHOP FIRST FLOOR28.96 Sq.mts. ( 312 Sq.ft. )
SHOP GROUND FLOOR29.03 Sq.mts. ( 312 Sq.ft. )
SHOP GROUND FLOOR29.46 Sq.mts. ( 317 Sq.ft. )
SHOP GROUND FLOOR34.62 Sq.mts. ( 373 Sq.ft. )
SHOP GROUND FLOOR36.12 Sq.mts. ( 389 Sq.ft. )
3 BHK82.92 Sq.mts. ( 893 Sq.ft. )
SHOP FIRST FLOOR95.25 Sq.mts. ( 1025 Sq.ft. )
SHOP FIRST FLOOR29.94 Sq.mts. ( 322 Sq.ft. )
SHOP FIRST FLOOR42.75 Sq.mts. ( 460 Sq.ft. )
SHOP GROUND FLOOR49.57 Sq.mts. ( 534 Sq.ft. )
SHOP GROUND FLOOR37.14 Sq.mts. ( 400 Sq.ft. )
SHOP GROUND FLOOR29.31 Sq.mts. ( 315 Sq.ft. )
SHOP GROUND FLOOR62.29 Sq.mts. ( 670 Sq.ft. )
SHOP GROUND FLOOR69.2 Sq.mts. ( 745 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of PRAJAPATI ORNATElast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
In Later Scope Of Work
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station85% completed
85% Complete
In Later Scope Of Work
Energy management100% completed
95% Complete
In Later Scope Of Work
Fire Protection And Fire Safety Requirements95% completed
95% Complete
In Later Scope Of Work
Landscaping & Tree Planting85% completed
85% Complete
In Later Scope Of Work
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Chambers And Lines Upto Municipal Drain
Solid Waste Management And Disposal100% completed
95% Complete
In Later Scope Of Work
Storm Water Drains90% completed
90% Complete
Terrace And Open Area Storm Water To Rwh Tank Over
Street Lighting
In Later Scope Of Work
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
In Later Scope Of Work
Water Conservation, Rain water Harvesting100% completed
95% Complete
Rain Water Harvesting Tank In Later Scope Of Work
Water Supply85% completed
85% Complete
In Later Scope Of Work
Buildings / Wings in PRAJAPATI ORNATE
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of PRAJAPATI ORNATE by PRAJAPATI CONSTRUCTIONS LIMITEDlast updated on 14 Feb 2026 as per information obtained from MARA RERA.

39732 Sq. ft.

Project Area

12938 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

120 apartments in total
Total
120
Booked
85
Available
35

Saleable Area Statistics (Sq. ft.)

72326 Total
Total
72326
Booked
53844
Available
18481
Total 120 apartments in project. 85 apartments booked. 70% apartments booked.
Total 72326 Sq.ft. saleable area. 53844 saleable area booked.
74% area booked.

A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A WingDec 2024151023540
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )12
9 Booked75% Booked
75% Booked
3 BHK82.91 Sq.mts. ( 892 Sq.ft. )12
12 Booked100% Booked
100% Booked
SHOP FIRST FLOOR29.14 Sq.mts. ( 314 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP FIRST FLOOR25.39 Sq.mts. ( 273 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP FIRST FLOOR28.53 Sq.mts. ( 307 Sq.ft. )4
2 Booked50% Booked
50% Booked
SHOP FIRST FLOOR28.96 Sq.mts. ( 312 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP GROUND FLOOR29.03 Sq.mts. ( 312 Sq.ft. )7
4 Booked57% Booked
57% Booked
SHOP GROUND FLOOR29.46 Sq.mts. ( 317 Sq.ft. )1
1 Booked100% Booked
100% Booked
40 total apartments / 30 apartments booked. 75% apartments booked.
Work Description in Building A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked

B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B WingDec 2024151023435
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )24
20 Booked83% Booked
83% Booked
SHOP FIRST FLOOR29.14 Sq.mts. ( 314 Sq.ft. )8
8 Booked100% Booked
100% Booked
SHOP GROUND FLOOR34.62 Sq.mts. ( 373 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP GROUND FLOOR36.12 Sq.mts. ( 389 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP GROUND FLOOR29.03 Sq.mts. ( 312 Sq.ft. )5
5 Booked100% Booked
100% Booked
40 total apartments / 33 apartments booked. 82% apartments booked.
Work Description in Building B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingDec 2024151023439
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )12
10 Booked83% Booked
83% Booked
3 BHK82.91 Sq.mts. ( 892 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK82.92 Sq.mts. ( 893 Sq.ft. )12
12 Booked100% Booked
100% Booked
SHOP FIRST FLOOR95.25 Sq.mts. ( 1025 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP FIRST FLOOR29.14 Sq.mts. ( 314 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP FIRST FLOOR29.94 Sq.mts. ( 322 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP FIRST FLOOR42.75 Sq.mts. ( 460 Sq.ft. )4
None Booked0% Booked
0% Booked
SHOP GROUND FLOOR49.57 Sq.mts. ( 534 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP GROUND FLOOR37.14 Sq.mts. ( 400 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP GROUND FLOOR29.31 Sq.mts. ( 315 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP GROUND FLOOR62.29 Sq.mts. ( 670 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP GROUND FLOOR69.2 Sq.mts. ( 745 Sq.ft. )1
None Booked0% Booked
0% Booked
40 total apartments / 22 apartments booked. 55% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
PRAJAPATI CONSTRUCTIONS LIMITED
for Project
PRAJAPATI ORNATE
last updated on 14 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation