Project overview

Prajapati Ornate Phase - Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000035186. Prajapati Ornate Phase - Ii is located at Plot No 191 To 197 And Plot No 199 To 206. This is a New being developed by Prajapati Constructions Limited.

Prajapati Ornate Phase - Ii has 2 BHK, 3 BHK & DUPLEX Apartments with carpet areas ranging from 1974 to 893 Sq.ft. Carpet. The Project has total 17 of which 6 are currently available for sale.

Prajapati Ornate Phase - Ii is being developed on a total land area of 39732 Sq.ft. out of which 12938 Sq.ft. i.e 33% is reserved for recreational purposes. Prajapati Ornate Phase - Ii has 3 Wings / Towers A Wing,B Wing,C Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Prajapati Ornate Phase - Ii
  • Location:
  • Plot No 191 To 197 And Plot No 199 To 206
  • Const. Stage:
    New
  • Possession:
    30 Jun 2026
Developer Details

  • Developer:
    Prajapati Constructions Limited
  • Phone:
  • Address:
  • Prajapati Constructions Ltd
Project RERA Details
MAHA REARA No: P52000035186
Project Type Residential / Group Housing
RERA Project Status New
Architect Stapl Soyuz Talib Architects
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Jun 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 10 May 2022
Last Retrived 28 Jul 2025
Prajapati Ornate Phase - Ii QR Code
Prajapati Ornate Phase - Ii
MahaRERA - P52000035186
Apartment Details & Configuration
TypeArea
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )
3 BHK82.91 Sq.mts. ( 892 Sq.ft. )
DUPLEX183.39 Sq.mts. ( 1974 Sq.ft. )
3 BHK91.17 Sq.mts. ( 981 Sq.ft. )
3 BHK82.92 Sq.mts. ( 893 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Prajapati Ornate Phase - Iilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
In Later Scope Of Work
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station85% completed
85% Complete
In Later Scope Of Work
Energy management100% completed
95% Complete
In Later Scope Of Work
Fire Protection And Fire Safety Requirements85% completed
85% Complete
In Later Scope Of Work
Landscaping & Tree Planting85% completed
85% Complete
In Later Scope Of Work
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
In Later Scope Of Work
Solid Waste Management And Disposal100% completed
95% Complete
In Later Scope Of Work
Storm Water Drains95% completed
95% Complete
In Later Scope Of Work
Street Lighting
In Later Scope Of Work
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
In Later Scope Of Work
Water Conservation, Rain water Harvesting95% completed
95% Complete
In Later Scope Of Work
Water Supply85% completed
85% Complete
In Later Scope Of Work
Buildings / Wings in Prajapati Ornate Phase - Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Prajapati Ornate Phase - Ii by Prajapati Constructions Limitedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

39732 Sq. ft.

Project Area

12938 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

17 apartments in total
Total
17
Booked
11
Available
6

Saleable Area Statistics (Sq. ft.)

15060 Total
Total
15060
Booked
8162
Available
6898
Total 17 apartments in project. 11 apartments booked. 64% apartments booked.
Total 15060 Sq.ft. saleable area. 8162 saleable area booked.
54% area booked.

A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A WingJun 20264000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )2
2 Booked100% Booked
100% Booked
3 BHK82.91 Sq.mts. ( 892 Sq.ft. )2
2 Booked100% Booked
100% Booked
DUPLEX183.39 Sq.mts. ( 1974 Sq.ft. )1
None Booked0% Booked
0% Booked
5 total apartments / 4 apartments booked. 80% apartments booked.
Work Description in Building A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B WingJun 20264000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )6
3 Booked50% Booked
50% Booked
3 BHK91.17 Sq.mts. ( 981 Sq.ft. )1
None Booked0% Booked
0% Booked
7 total apartments / 3 apartments booked. 42% apartments booked.
Work Description in Building B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingJun 20264000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK60.95 Sq.mts. ( 656 Sq.ft. )2
2 Booked100% Booked
100% Booked
3 BHK82.92 Sq.mts. ( 893 Sq.ft. )2
2 Booked100% Booked
100% Booked
DUPLEX183.39 Sq.mts. ( 1974 Sq.ft. )1
None Booked0% Booked
0% Booked
5 total apartments / 4 apartments booked. 80% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Prajapati Constructions Limited
for Project
Prajapati Ornate Phase - Ii
last updated on 28 Jul 2025 as per information obtained from MARA RERA.