Project overview

Pink City Trident Phase 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700001716. Pink City Trident Phase 2 is located at Thane, 421501. This is a On-Going Project being developed by Ami Infra.

Pink City Trident Phase 2 has 1 BHK, 2 BHK, SHOP & SHOPS Apartments with carpet areas ranging from 125 to 445 Sq.ft. Carpet. The Project has total 116 of which 44 are currently available for sale.

Pink City Trident Phase 2 is being developed on a total land area of 41172 Sq.ft. out of which 4117 Sq.ft. i.e 10% is reserved for recreational purposes. Pink City Trident Phase 2 has 3 Wings / Towers Wing A,Wing B,Wing C

ProjectDeveloperLocationPossession
Shree Sai LeelaShree Sai Builders & DevelopersPlot No.6, S.No. 86/330-06-2018 00:00:00
NiloyShree Sai Builders & DevelopersCts No 437831-12-2019 00:00:00
Shree Sai PanacheGyandev Builders & DevelopersCts No 142 Hissa No 530-12-2020 00:00:00
Manas ResidencyManas EnterprisesSurvey No 57 Hissa No 231-12-2018 00:00:00
Shiv Parvati ResidencyShrikrishna DevelopersPardi No 193B Cts 6016 To 6026 6057 To 6073 6133 To 6134 9662 Mouje Kohoj Khutavali31-03-2019 00:00:00
Britto HouseShree Sai Builders & DevelopersPlot No 5 Cts No 2269 To 2274 S No 166 Hisa No 1231-12-2018 00:00:00
Panvelkar CrownRahul Vijay PanvelkarCts No 932131-12-2018 00:00:00
Pramukh SadanSahajanand DevelopersSurvey No - 39A Hissa No-1A, 1B31-03-2019 00:00:00
Patel Residency NxNavnirman DevelopersSurvey No 2 Hissa No 4B30-07-2018 00:00:00
Patels ResidencyParam Builders And DevelopersSurvey No 5 Hissa No 19 Plot B31-03-2018 00:00:00
Patels PridePride InfrastructureSurveyno 25 Hissa No 23 Plot A And B31-12-2018 00:00:00
Ashapura Builders And DevelopersAshapura Builders And DevelopersGut No. 54 Part, Plot No. 831-12-2017 00:00:00
Neels ResidencyS.A. Singh Builders And DevelopersSurvey No 85 Hissa No 2 B21-11-2018 00:00:00
Vedant VatikaVedant VentureSurvey No 63, Hissa No 4A8, Plot No 1331-12-2019 00:00:00
Project Details
  • Project:
    Pink City Trident Phase 2
  • Location:
  • Thane, 421501
  • Const. Stage:
    On-Going Project
  • Possession:
    30 Apr 2020
Developer Details

  • Developer:
    Ami Infra
  • Phone:
  • Address:
  • Gut No 48, Pink City, Near Royal Park, Navare Nagar, Navare Nagar, 421501
Project RERA Details
MAHA REARA No: P51700001716
Project Type Others
RERA Project Status On-Going Project
Funding Bank BANK OF MAHARASHTRA
Proposed Possession 30 Apr 2020
Revised Possession 30 Oct 2020
Extended Possession 30 Apr 2022
Litigations No Litigations
Last Modified 15 Jul 2021
Last Retrived 28 Jul 2025
Pink City Trident Phase 2 QR Code
Pink City Trident Phase 2
MahaRERA - P51700001716
Apartment Details & Configuration
TypeArea
1 BHK31.29 Sq.mts. ( 337 Sq.ft. )
1 BHK32.93 Sq.mts. ( 354 Sq.ft. )
2 BHK42.95 Sq.mts. ( 462 Sq.ft. )
SHOP15.4 Sq.mts. ( 166 Sq.ft. )
SHOP16.27 Sq.mts. ( 175 Sq.ft. )
SHOP20.62 Sq.mts. ( 222 Sq.ft. )
SHOP21.31 Sq.mts. ( 229 Sq.ft. )
1 BHK35.18 Sq.mts. ( 379 Sq.ft. )
2 BHK41.32 Sq.mts. ( 445 Sq.ft. )
SHOP11.61 Sq.mts. ( 125 Sq.ft. )
SHOP12.29 Sq.mts. ( 132 Sq.ft. )
SHOP20.47 Sq.mts. ( 220 Sq.ft. )
SHOPS16.2 Sq.mts. ( 174 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Pink City Trident Phase 2last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
385.202 Sq. Mt
Community Buildings
Society Office And Fitness Centre
Electrical Meter Room, Sub-Station, Receiving Station
Electric Meter Room Proposed
Energy management
Na
Fire Protection And Fire Safety Requirements
-
Landscaping & Tree Planting
Tree Planting Proposed No Landscaping
Open Parking
337.500 Sq. Mt
Sewerage (Chamber, Lines, Septic Tank , STP)
-
Solid Waste Management And Disposal
Na
Storm Water Drains
-
Street Lighting
-
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Rain Water Harvesting Proposed
Water Supply
Will Be Provided By Concerned Dep
Buildings / Wings in Pink City Trident Phase 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Pink City Trident Phase 2 by Ami Infralast updated on 28 Jul 2025 as per information obtained from MARA RERA.

41172 Sq. ft.

Project Area

4117 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

116 apartments in total
Total
116
Booked
72
Available
44

Saleable Area Statistics (Sq. ft.)

45296 Total
Total
45296
Booked
29833
Available
15463
Total 116 apartments in project. 72 apartments booked. 62% apartments booked.
Total 45296 Sq.ft. saleable area. 29833 saleable area booked.
66% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AApr 20208101005
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.29 Sq.mts. ( 337 Sq.ft. )14
13 Booked92% Booked
92% Booked
1 BHK32.93 Sq.mts. ( 354 Sq.ft. )14
8 Booked57% Booked
57% Booked
28 total apartments / 21 apartments booked. 75% apartments booked.
Work Description in Building Wing ACompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress70% done
70% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BApr 202013101004
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK42.95 Sq.mts. ( 462 Sq.ft. )47
34 Booked72% Booked
72% Booked
SHOP15.4 Sq.mts. ( 166 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP16.27 Sq.mts. ( 175 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP20.62 Sq.mts. ( 222 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP21.31 Sq.mts. ( 229 Sq.ft. )2
None Booked0% Booked
0% Booked
55 total apartments / 34 apartments booked. 61% apartments booked.
Work Description in Building Wing BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress60% done
60% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CApr 20208101006
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK35.18 Sq.mts. ( 379 Sq.ft. )14
10 Booked71% Booked
71% Booked
2 BHK41.32 Sq.mts. ( 445 Sq.ft. )14
7 Booked50% Booked
50% Booked
SHOP11.61 Sq.mts. ( 125 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP12.29 Sq.mts. ( 132 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP20.47 Sq.mts. ( 220 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOPS16.2 Sq.mts. ( 174 Sq.ft. )1
None Booked0% Booked
0% Booked
33 total apartments / 17 apartments booked. 51% apartments booked.
Work Description in Building Wing CCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress70% done
70% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Ami Infra
for Project
Pink City Trident Phase 2
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation