Project overview

Pine Wood is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800007505. Pine Wood is located at 11/8. This is a Ongoing being developed by Rdc Ventures.

Pine Wood has 1 BHK & 2 BHK Apartments with carpet areas ranging from 336 to 648 Sq.ft. Carpet. The Project has total 76 of which 51 are currently available for sale.

Pine Wood is being developed on a total land area of 21743 Sq.ft. out of which 3703 Sq.ft. i.e 17% is reserved for recreational purposes. Pine Wood has 1 Wings / Towers Pinewood

ProjectDeveloperLocationPossession
Pushpanjali Residency Phase IiiShriraam Pioneer Developers Private Limited99/2, 99/4B, 101/3, 97/1, 58/1, 98/1A, 98/1B, 99/6 59/1A 99/4A, 59/230-12-2022 00:00:00
Ace Square Phase 1Anant SquareSurvey 2-28, 2-19, 2-3331-12-2017 00:00:00
Tokyo Bay Phase - 2APuranik Tokyo Bay Private Limited21/9-Pt 22/1-Pt 22/5-Pt 21/11A Pt 23/4 Pt30-12-2024 00:00:00
Platinum TowerHaware's Housing Development Finance Corporation Ltd.19/28 19/29 19/30 20/05 21/16 20/0630-09-2022 00:00:00
Pride Residency DaffodilSahil Developers36/2-A31-12-2018 00:00:00
Satgurus SolitaireBuildwell Land Developers Private Limited91, Owale, Thane31-12-2017 00:00:00
Rosa Oasis Phase 2Uma EnterprisesS.No. 124/2/3, 125/2, 125/3/131-12-2018 00:00:00
Tokyo Bay Phase - 1Puranik Tokyo Bay Private Limited20/1-Pt, 20/2B-Pt 30-10-2023 00:00:00
Rumahbali Phase 2Puranik Builders LimitedNew S No 100-15B, 17 Pt 18 Pt 19Pt And 23Pt, Old S No -197-15B 17 Pt 18 Pt 19Pt And 23Pt30-12-2023 00:00:00
Raunak HeightsUnnathi Associates67/8B 67/8A 66/5B30-12-2025 00:00:00
Ashok Smruti DefgM/S Keytech27/631-12-2019 00:00:00
Puranik City Reserva Phase 1Puranik Builders Limited67/1Pt 67/1Pt 1/12-7Pt 1/11-5Pt 1/4-12Pt 55/1Apt 55/1Bpt 54/4Pt 54/3Pt 53/2Pt, 3Pt30-03-2029 00:00:00
Fiama ResidencyFiama Construction CompanyMogharpada S No 57/2B, 57/2C, 57/330-12-2021 00:00:00
Shree Savali Wing BUmesh Raosaheb Pawar Patil HufS No 63 Hissa No 231-07-2019 00:00:00
Olive ResidencyGoodwill PropertiesOld S.No. 55 New S.No. 66 H.No. 1/230-12-2021 00:00:00
Mahavir Kalpavruksha - J WingDamji Shamji Realty Pvt.Ltd.Sno 86/1A,2,3A,86/3B,86/3C,87/1A,1B,1C,87/1D,4D,87/4D,77/1,87/1E,1F,1H,87/2,3,4A,4B30-12-2023 00:00:00
Aarambh - CM/S. Annapurna Lifespaces Llp21/11B Pt30-06-2026 00:00:00
Dahlia Bldg A D And EHaware Engineers And Builders Private Limited47/1 48/2 48/3 48/6Ap 48/6B30-04-2019 00:00:00
TaranganMaison Constructions Private LimitedSurvey No.6, Hissa No. 3A And 3B31-05-2018 00:00:00
Ace ParksideAarti Estates7/5/1, 7/5/2, 7/631-12-2029 00:00:00
Intelligentia Segment By Haware PropertiesSuresh Kashinath HawareSurvey No 47/231-12-2027 00:00:00
North Imperial Greens -Tower 2Skylark Buildspace Private Limited450 Pt.,449 Pt.,451,455/A Pt.,460Pt.,461 Pt.,464/1 Pt.,465/1,538/1,46331-12-2031 00:00:00
SubodhNew Homes Corporation17430-09-2020 00:00:00
PelicanM/S Ace Constructions27-2 27-3 27-830-06-2018 00:00:00
Horizon Classique-ISachin EnterprisesTika No-3 Chalta No- 13030-06-2018 00:00:00
Puraniks CapitolPuranik Builders Limited35/2, 3,4 And 530-12-2036 00:00:00
Mahavir Kalpavruksha - Oak, Tulip, Alcacia, AlmondDamji Shamji Realty Private Limited86/1A,2,3A,1B,1C, 87/1D,4D,87/4D, 77/1, 87/1E, 1F, 1H, 87/2, 3, 4A, 4B30-12-2021 00:00:00
Metropolis - Insignia TowersAnant Square4/4, 4/5 And 6/114-04-2026 00:00:00
Raunak 108Unnathi Associates73/1, 73/2, 73/3, 73/430-06-2026 00:00:00
Horizon Palms - IiiKm DevelopersOld S No 63, New S No 10130-12-2024 00:00:00
Sukur Enclave Phase 1Rajaram ConstructionSrno 7-22 7-23 7-25 7-26 Srno 11-7 Vadavli Srno 114-4 Owale Srno 242-1-1C Kavesar31-12-2018 00:00:00
Bhakti Pearl - CBhakti Corporation532, 53331-12-2017 00:00:00
Puranik Home Town - EPuranik Builders LimitedOld 75/Pt New 89/3C Pt And Old 76/5A Pt New 88/5A Pt30-12-2026 00:00:00
Sai PalaceSai DeveopersChalta No 71,7231-03-2018 00:00:00
Mukund NiwasNew Vegas DevelopersChalta No 1930-09-2020 00:00:00
Horizon Classique-2Sachin EnterprisesChalta No.128/129A, Tika No.330-06-2021 00:00:00
AnthuriumAarti EstatesPart Of - 7/15, 8/2/2, 8/4, 8/5, 8/630-10-2023 00:00:00
Shree SankalpShree ConstructionsS No 95/531-07-2019 00:00:00
Elita D3Vihang Infrastructure Pvt Ltd69/1/1,69/1/2,69/3A/1,A/2,4,5/1,5/2,6,72/4B,4C,4D,4E,74/1/1B, 1/2B,1/2A,1/3A,1/3B,3/1,3/2,5,2/B,2A/1,2A/2,4,75/1/A,1/B,2/B,2/C,77/2,3,1/2,1/3,78/3/B/1,3/B/2,3/B/3,4/A,4/B,3/A/1,3/A/231-12-2029 00:00:00
Commercial Building 10Vihang Infrastructure Pvt Ltd69/1/1,1/2,3A/1,A/2,4,5/1,5/26, 72/4B,4C,4D,4E,74/1/1B,1/2B,1/2A,1/3A,1/3B,3/1,3/2,5,2/B,2A/1,2A/2,4,75/1/A,1/B,2/B,2/C,77/2,3,1/2,1/3,78/3/B/1,3/B/2,3/B/3,4/A,4/B,3/A/1,3/A/2,1/B31-12-2024 00:00:00
Ace EnclaveAce Signature Homes Llp70/6, 53/631-12-2026 00:00:00
Rumah Bali Phase 4Puranik Builders LimitedS. No. Old 197 New 100 H. No. 11/1(P), 11/2(P), 12(P), 14(P), 15(P), 17(P), 18(P), 19(P), 19(P), 20(P), 21(P)31-12-2028 00:00:00
Mahavir Breeze Phase 1Damji Shamji Realty Pvt. Ltd.86/1A 2 3A 3C 84/1A 2 1C 1E 1F 4C 4B 1Z 1D 87/1B 3 4A 1D 4D 87 4D 86/3B 77/1 86/3/231-12-2024 00:00:00
Cascade Avenue BellagioAarsh Construction53/6, 54/5 Village Mogharpada & 70/6(Pt) Village Vadavali31-12-2026 00:00:00
Mahavir Estella - Wing A And BCityscape Construction CoNew S No 52, Hissa No 131-12-2018 00:00:00
Prity Park B And C Bldg Phase 2S D Bhalerao AssociatesOwala31-12-2017 00:00:00
Cosmos Enclave - ChestnutMonarch Developers10 H No 1A30-12-2023 00:00:00
Psk SkylarGururaj Developers118, 113/1630-12-2023 00:00:00
Kirans Shree SmaranKiran Vasant ThandreS No 24 H No 3A30-12-2021 00:00:00
Guru AshishShree Gurukrupa Ventures Llp126 Sector 1531-12-2018 00:00:00
Trimity AshwaTrimity Constructions60/531-12-2017 00:00:00
Vihang ValleyVihang Infrastructure Pvt Ltd 74/1/1,74/1/2, 74/1/3, 74/2/A, 2/B, 3,4,5 75/1,2, 72/4, 77/1,2,3 69/1,3A,4,5,6 78/1A,1B,3A30-12-2026 00:00:00
Delta Greenville - AsterDelta Synergy LlpCts No 258 259/1 260 261 268Pt31-01-2031 00:00:00
Delta Greenville - CedarDelta Synergy LlpCts No 258 259/1 260 261 268Pt31-12-2030 00:00:00
Horizon Pearl IiKm DevelopersOld Survey No 68/131-12-2028 00:00:00
Elysia D-4Vihang Infrastructure Pvt Ltd31-12-2031 00:00:00
FalconM/S Ace Constructions27-2, 27-3, 27-830-06-2018 00:00:00
Pristine TowerIdeal DevelopersThane, 40061531-12-2017 00:00:00
Tropical Lagoon - 4 -JacarandaSoham Estates240/2 Pt, 240/3, 240/6, 240/7, 240/9, 240/10 Pt31-05-2018 00:00:00
Prathamesh TowersShivam Developers42/131-03-2018 00:00:00
ShantaiJanardhan Sakharam BhoirS.No.42 H.No.5A31-12-2019 00:00:00
Trinity HeightsAnil Thakurdas KursijaS No 23/4,23/5,23/730-05-2023 00:00:00
Project Details
  • Project:
    Pine Wood
  • Location:
  • 11/8
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2017
Developer Details

  • Developer:
    Rdc Ventures
  • Phone:
  • Address:
  • Matoshree Chs Ltd
Project RERA Details
MAHA REARA No: P51800007505
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Ulhas G Pradhan
Funding Bank ICICI BANK LIMITED
Proposed Possession 31 Dec 2017
Revised Possession 31 Dec 2017
Extended Possession 30 Jun 2018
Litigations No Litigations
Last Modified 15 Jan 2018
Last Retrived 26 Jul 2025
Pine Wood QR Code
Pine Wood
MahaRERA - P51800007505
Apartment Details & Configuration
TypeArea
1 BHK31.22 Sq.mts. ( 336 Sq.ft. )
1 BHK39.66 Sq.mts. ( 427 Sq.ft. )
1 BHK42.26 Sq.mts. ( 455 Sq.ft. )
1 BHK44.91 Sq.mts. ( 483 Sq.ft. )
2 BHK55.71 Sq.mts. ( 600 Sq.ft. )
2 BHK60.16 Sq.mts. ( 648 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Pine Woodlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
N.A.
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
N.A.
Landscaping & Tree Planting100% completed
95% Complete
N.A.
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
N.A.
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
N.A.
Street Lighting100% completed
95% Complete
N.A.
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
N.A.
Water Supply100% completed
95% Complete
N.A.
Buildings / Wings in Pine Wood
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Pine Wood by Rdc Ventureslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

21743 Sq. ft.

Project Area

3703 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

76 apartments in total
Total
76
Booked
25
Available
51

Saleable Area Statistics (Sq. ft.)

37276 Total
Total
37276
Booked
12184
Available
25092
Total 76 apartments in project. 25 apartments booked. 32% apartments booked.
Total 37276 Sq.ft. saleable area. 12184 saleable area booked.
33% area booked.

Pinewood

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
PinewoodJan 1900141011554
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.22 Sq.mts. ( 336 Sq.ft. )13
1 BHK39.66 Sq.mts. ( 427 Sq.ft. )13
10 Booked76% Booked
76% Booked
1 BHK42.26 Sq.mts. ( 455 Sq.ft. )12
5 Booked41% Booked
41% Booked
1 BHK44.91 Sq.mts. ( 483 Sq.ft. )13
2 BHK55.71 Sq.mts. ( 600 Sq.ft. )12
2 BHK60.16 Sq.mts. ( 648 Sq.ft. )13
6 Booked46% Booked
46% Booked
76 total apartments / 25 apartments booked. 32% apartments booked.
Work Description in Building PinewoodCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Rdc Ventures
for Project
Pine Wood
last updated on 26 Jul 2025 as per information obtained from MARA RERA.