Project overview

PEARL HERITAGE is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800010436. PEARL HERITAGE is located at 196 And 199. This is a New being developed by HARI OM CONSTRUCTION.

PEARL HERITAGE has 2 BHK Apartments with carpet areas ranging from 530 to 530 Sq.ft. Carpet. The Project has total 35 of which 27 are currently available for sale.

PEARL HERITAGE is being developed on a total land area of 15471 Sq.ft. PEARL HERITAGE has 2 Wings / Towers Pearl Heritage - Wing B,Pearl Heritage - Wing C

ProjectDeveloperLocationPossession
Project Details
  • Project:
    PEARL HERITAGE
  • Location:
  • 196 And 199
  • Const. Stage:
    New
  • Possession:
    30 Dec 2022
Developer Details

  • Developer:
    HARI OM CONSTRUCTION
  • Phone:
  • Address:
  • Pattathu Business Plaza
Project RERA Details
MAHA REARA No: P51800010436
Project Type Residential / Group Housing
RERA Project Status New
Architect Ar. Jatin Shah & Associates
Funding Bank SOUTH INDIAN BANK
Proposed Possession 30 Dec 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 26 Feb 2024
Last Retrived 13 Feb 2026
PEARL HERITAGE QR Code
PEARL HERITAGE
MahaRERA - P51800010436
Apartment Details & Configuration
TypeArea
3 BHK76.74 Sq.mts. ( 826 Sq.ft. )
3 BHK77.67 Sq.mts. ( 836 Sq.ft. )
3 BHK77.76 Sq.mts. ( 837 Sq.ft. )
3 BHK77.85 Sq.mts. ( 838 Sq.ft. )
2 BHK49.24 Sq.mts. ( 530 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of PEARL HERITAGElast updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Work To Commence No Req. Of Sub-Station
Energy management
Na
Fire Protection
Work To Commence
Fire Protection And Fire Safety Requirements
Na
Fitness Centre
Work To Commence
Landscaping & Tree Planting
Na
Open Parking
Work To Commence
Sewerage (Chamber, Lines, Septic Tank , STP)
Na
Solid Waste Management And Disposal
Na
Storm Water Drains80% completed
80% Complete
Work To Commence
Street Lighting
Na
Terrace Garden
Work To Commence
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Work To Commence
Water Supply10% completed
10% Complete
Work To Commence
Buildings / Wings in PEARL HERITAGE
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of PEARL HERITAGE by HARI OM CONSTRUCTIONlast updated on 13 Feb 2026 as per information obtained from MARA RERA.

15471 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

35 apartments in total
Total
35
Booked
8
Available
27

Saleable Area Statistics (Sq. ft.)

27070 Total
Total
27070
Booked
6071
Available
20998
Total 35 apartments in project. 8 apartments booked. 22% apartments booked.
Total 27070 Sq.ft. saleable area. 6071 saleable area booked.
22% area booked.

Pearl Heritage - Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Pearl Heritage - Wing BDec 202281010028
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK76.74 Sq.mts. ( 826 Sq.ft. )7
3 BHK77.67 Sq.mts. ( 836 Sq.ft. )7
3 BHK77.76 Sq.mts. ( 837 Sq.ft. )7
3 Booked42% Booked
42% Booked
3 BHK77.85 Sq.mts. ( 838 Sq.ft. )7
28 total apartments / 6 apartments booked. 21% apartments booked.
Work Description in Building Pearl Heritage - Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Pearl Heritage - Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Pearl Heritage - Wing CDec 20228101031
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK49.24 Sq.mts. ( 530 Sq.ft. )7
2 Booked28% Booked
28% Booked
7 total apartments / 2 apartments booked. 28% apartments booked.
Work Description in Building Pearl Heritage - Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress60% done
60% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress60% done
60% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress60% done
60% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress60% done
60% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
HARI OM CONSTRUCTION
for Project
PEARL HERITAGE
last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation