Pearl Heaven Iv is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800029797. Pearl Heaven Iv is located at 57, 58 And 100. This is a New being developed by Chandiwala Enterprises.

Pearl Heaven Iv has 1 BHK, 1RK & 2 BHK Apartments with carpet areas ranging from 230 to 500 Sq.ft. Carpet. The Project has total 236 of which 38 are currently available for sale.

Pearl Heaven Iv is being developed on a total land area of 20736 Sq.ft. Pearl Heaven Iv has 1 Wings / Towers Pearl Heaven Iv Bldg No 4

ProjectDeveloperLocationPossession
Azad Nagar Shubham ChslPrathamesh Krupa Buildcon Private Limited183 Part31-12-2017 00:00:00
Unity By LotusLotus Logistics And Developers Private Limited1217B30-09-2020 00:00:00
Pearl Residency - Wing-B, Residential Phase - IiiGiriraj Enterprises817 Part And 818 Part, 808 Part01-08-2024 00:00:00
SunbeamSharayu Developers Aop400053, Mumbai Suburban30-09-2023 00:00:00
Seksaria EnclaveB K Seksaria And OthersMumbai Suburban, 40005931-12-2018 00:00:00
Lodha Supremus - AndheriMacrotech Developers LimitedCts No.76, 81, 7728-08-2022 00:00:00
Omkar Chs LtdLakshmi Builders And Developers835 Pt01-07-2023 00:00:00
RudrakshaRaj UniversalCts No 2776/B, 2776/D31-01-2021 00:00:00
Neelgagan Chs LtdSwastik Realty Pvt Ltd195 Pt31-12-2018 00:00:00
Pearl Residency - Wing-A, Commercial Phase-IiGiriraj Enterprises808 Part, 817 Part And 818 Part25-07-2019 00:00:00
Silver SkylinePrabhav Realty And Infrastructure Pvt LtdJp Road31-07-2021 00:00:00
10 SquareVijay Kamdar100/1/230-06-2018 00:00:00
Platinum LifeSamudra Darshan Gruhpravesh Llp1/6A, 195 Pt, Survey No 106/1A30-12-2025 00:00:00
ChambersFairmont Lifespaces Llp310, 310/1 To 310/1130-06-2021 00:00:00
Blue SapphireBlue Canyon Realty Pvt Ltd146/5630-04-2020 00:00:00
Eleganzia RoyaleAnmol Alliance195 Part 828 Part30-06-2021 00:00:00
Chitralekha HerritageH.K.Pujara BuildersA-1/ 690A/ 4131-03-2019 00:00:00
The Business HubAnkur Mayflower Associates657/1-19, 65730-12-2020 00:00:00
AshokheightsNew India Construction Company166/1To2631-12-2019 00:00:00
KarmayogWestin Developers Pvt. LtdAndheri30-06-2017 00:00:00
Basera Chs LtdLakshmi Builders And Developers835 Pt01-07-2023 00:00:00
Orchid ResidencesH.K.Pujara BuildersB-51 / 666A / 5131-12-2018 00:00:00
Everglades - IiFalcon Dwellers Private LimitedMumbai Suburban, 40005330-09-2017 00:00:00
ArpitTista Impex Private Limited64A131-12-2019 00:00:00
Neelam Chs LtdJai Shree Krishna Builders And Developers400053, Mumbai Suburban31-12-2023 00:00:00
Nirmal Anand ChsNirmal Anand Chs Ltd142/A18-09-2022 00:00:00
Everglades - IFalcon Dwellers Private LimitedMumbai Suburban, 40005330-06-2017 00:00:00
Sai IconicShree Krishna Sai Development CorporationS.No. 111-D, Plot No-9, Cts.No.-825/1/2331-03-2019 00:00:00
Sterling Court Wing DApraulic Construction Investment And Finance Private LimitedCts No 55/5A Part30-09-2020 00:00:00
VedaSrujan Development And Construction Division207A, 207A/1 To 30, 8830-06-2021 00:00:00
Saideep ApartmentDarshan Infra284 Of Village Kondivate31-03-2025 00:00:00
Amber ViharShah & Shah Construction Corporation365A 365/2A 365/431-03-2025 00:00:00
Shyam KunjBasons Constructions29418-07-2024 00:00:00
Dlh MetroviewDev Land & Housing Private LimitedCts No 195 Pt30-04-2018 00:00:00
Cd Plot No 69 LumiereSd Svp Nagar Redevelopment Private Limited1374/B/17730-09-2019 00:00:00
Satyam Chs LtdSwastik Realty Pvt Ltd82131-12-2018 00:00:00
Matri SadanSwastik DevelopersPlot No 53 Cts No 315 Village Kondivita31-12-2019 00:00:00
Al-Burhan Chs-Phase-IiRaj Romell RealtorsAndheri East, Mumbai30-12-2020 00:00:00
Al-Burhan Chs-Phase-IRaj Romell RealtorsAndheri East, Plot No 25, Cts-12973 Village Marol30-12-2020 00:00:00
Redevelopment Of Bldg 5 And 6 Samrat And Pulkit Chs Ltd Cts No 195 Pt D N Ngr Mhada Layout Andheri WA A Estates Pvt LtdCts No 195 Pt D N Nagar Mhada Layout Andheri W Mumbai 5330-12-2022 00:00:00
Azad Nagar Suyog Chs Society LtdRajvi Builders And DevelopersMumbai Suburban, 40005308-03-2013 00:00:00
PrideSalasar Construction33430-06-2023 00:00:00
Pearl Heaven IvChandiwala Enterprises57, 58 And 10031-12-2026 00:00:00
Sky VistaDelta AssociatesC.T.S. No. 222, 222/17, 22305-01-2029 00:00:00
Citi NestBasons Investments Private Limited292/1 To 3, 29231-12-2024 00:00:00
La GraceEcohomes Ventures1337, 133931-12-2026 00:00:00
Second Avenue Phase 1Atul Projects Realty Private Limited17/2A/131-12-2025 00:00:00
Safavi Chs LtdRaj Builders1209A/ Plot No. 1731-10-2018 00:00:00
Hari Om Chs ProposedHari Om Developers40006931-12-2020 00:00:00
Sai PrasadSumit Snehashish Joint Venture740, 740/1 To 530-09-2018 00:00:00
Gaurav LegendMonarch And Querish Builders581 To 58530-12-2023 00:00:00
EleganceJaycee Homes Private LimitedSurvey No 106 Part And Cts No 195 Part31-07-2018 00:00:00
Nandini ChslMehta GroupMumbai Suburban, 40005331-12-2018 00:00:00
Jyoti SkylineJyoti Shelter115/1 To 9, C.T.S No. 11531-12-2026 00:00:00
Heritage HouseGreen Tree Lifescapes Llp20124-12-2024 00:00:00
MohammedimanzilJem Developers And Builders1297/1531-12-2025 00:00:00
Gateway ResidencesInfinity Narayani Associates31731-12-2025 00:00:00
Parkway ManorGautam Ekanath Thakur29231-08-2026 00:00:00
Rishabraj TridentH Rishabraj RealtySub Plot No 22 Cts No 195 /173/2Pt31-08-2028 00:00:00
A-2Parikh Enterprise626/3 Part30-12-2025 00:00:00
ElegancePawankumar PrabhuCts No 1182 A Part28-02-2021 00:00:00
Kaatyayni Heights Phase 1Starwing Developers Private Limited199Pt, 215/23 T0 32, 213, 198Pt, 214/1 To 12, 199/1 To 19, 214Pt, 215/1 To 1230-06-2023 00:00:00
Giriraj ApartmentsMetro Dwellers Private LimitedCts No 863 863 1 To 863 1325-12-2018 00:00:00
Cosmopolis Phase 1Cosmos Homes India Pvt. Ltd.41 Pt, 1 190A31-12-2017 00:00:00
PhilipaRavikant SakaskarAndheri30-06-2018 00:00:00
Safal ArcadeSafal Sanjana Builders And Developers Pvt Ltd400069, Mumbai Suburban31-12-2018 00:00:00
Metropolis ResidencesHousing Development And Infrastructure Ltd866/B/1Pt31-12-2017 00:00:00
ExoticaHilal Merchant9531, Cts No 950A, 9532A31-12-2017 00:00:00
Shivam CentriumGlobal Buildcon Pvt LtdCts Nos 38 38/1 To 3 40 40/1 To 64 And 40/73 To 129 And Cts No 453 Part30-09-2020 00:00:00
N G Eclat A Wing Phase IiiNarinderpal Roshanlal GuptaCts No.1195, 1196 New 1190 A30-12-2021 00:00:00
OrionSheth & Sonal DevelopersCts No 135/A30-07-2021 00:00:00
Crystal HarmonyCrystal Builders & Developers10315-11-2021 00:00:00
Sky VueSamyakth Realties65B30-06-2018 00:00:00
Ashirwad Chs LtdAshirwad Co-Operative Housing Society Ltd14/5 A30-12-2021 00:00:00
Project Details
  • Project:
    Pearl Heaven Iv
  • Location:
  • 57, 58 And 100
  • Const. Stage:
    New
  • Possession:
    31 Dec 2026
Developer Details

  • Developer:
    Chandiwala Enterprises
  • Phone:
  • Address:
  • Al-Moonaz Arcade
Project RERA Details
MAHA REARA No: P51800029797
Project Type Residential / Group Housing
RERA Project Status New
Architect Ashish Solanki
Funding Bank UNION BANK OF INDIA
Proposed Possession 31 Dec 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 04 Jul 2021
Last Retrived 26 Jul 2025
Pearl Heaven Iv QR Code
Pearl Heaven Iv
MahaRERA - P51800029797
Apartment Details & Configuration
TypeArea
1 BHK46.45 Sq.mts. ( 500 Sq.ft. )
1 BHK30.94 Sq.mts. ( 333 Sq.ft. )
1 BHK33.79 Sq.mts. ( 364 Sq.ft. )
1 BHK34.14 Sq.mts. ( 367 Sq.ft. )
1 BHK36.04 Sq.mts. ( 388 Sq.ft. )
1RK21.33 Sq.mts. ( 230 Sq.ft. )
2 BHK41.44 Sq.mts. ( 446 Sq.ft. )
2 BHK41.83 Sq.mts. ( 450 Sq.ft. )
2 BHK42.22 Sq.mts. ( 454 Sq.ft. )
2 BHK42.29 Sq.mts. ( 455 Sq.ft. )
2 BHK43.66 Sq.mts. ( 470 Sq.ft. )
2 BHK44.06 Sq.mts. ( 474 Sq.ft. )
2 BHK44.13 Sq.mts. ( 475 Sq.ft. )
2 BHK45.29 Sq.mts. ( 488 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Pearl Heaven Ivlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Proportionate Area 308.21 Sq
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
As Per Requirement By Electricity Supply Company
Energy management
As Per Moef Noc &Amp; Mep Consultants
Fire Protection And Fire Safety Requirements85% completed
85% Complete
As Per Cfo Noc
Landscaping & Tree Planting40% completed
40% Complete
Tree Plantation To Be Done As Per Tree Noc
Open Parking
Mtr. For Build No 4R
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
Internal Chambers &Amp; Lines Prop Along With Stp
Solid Waste Management And Disposal35% completed
35% Complete
Vermiculture Bin Will Be Prov As Per Req By Mcgm
Storm Water Drains90% completed
90% Complete
Will Be Connected To Municipal Storm Water Drain
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
As Per Moef Noc &Amp; Mep Consultants
Water Conservation, Rain water Harvesting55% completed
55% Complete
Recharge Pit Proposed As Per Rwh Consultants Remar
Water Supply100% completed
95% Complete
On Completion Of The Building
Buildings / Wings in Pearl Heaven Iv
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Pearl Heaven Iv by Chandiwala Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

20736 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

236 apartments in total
Total
236
Booked
198
Available
38

Saleable Area Statistics (Sq. ft.)

104444 Total
Total
104444
Booked
87475
Available
16969
Total 236 apartments in project. 198 apartments booked. 83% apartments booked.
Total 104444 Sq.ft. saleable area. 87475 saleable area booked.
84% area booked.

Pearl Heaven Iv Bldg No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Pearl Heaven Iv Bldg No 4Dec 20261911102452
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK46.45 Sq.mts. ( 500 Sq.ft. )18
15 Booked83% Booked
83% Booked
1 BHK30.94 Sq.mts. ( 333 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK33.79 Sq.mts. ( 364 Sq.ft. )19
17 Booked89% Booked
89% Booked
1 BHK34.14 Sq.mts. ( 367 Sq.ft. )19
17 Booked89% Booked
89% Booked
1 BHK36.04 Sq.mts. ( 388 Sq.ft. )18
16 Booked88% Booked
88% Booked
1RK21.33 Sq.mts. ( 230 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK41.44 Sq.mts. ( 446 Sq.ft. )17
14 Booked82% Booked
82% Booked
2 BHK41.83 Sq.mts. ( 450 Sq.ft. )38
33 Booked86% Booked
86% Booked
2 BHK42.22 Sq.mts. ( 454 Sq.ft. )16
14 Booked87% Booked
87% Booked
2 BHK42.29 Sq.mts. ( 455 Sq.ft. )18
14 Booked77% Booked
77% Booked
2 BHK43.66 Sq.mts. ( 470 Sq.ft. )18
15 Booked83% Booked
83% Booked
2 BHK44.06 Sq.mts. ( 474 Sq.ft. )16
12 Booked75% Booked
75% Booked
2 BHK44.13 Sq.mts. ( 475 Sq.ft. )19
16 Booked84% Booked
84% Booked
2 BHK45.29 Sq.mts. ( 488 Sq.ft. )18
14 Booked77% Booked
77% Booked
236 total apartments / 198 apartments booked. 83% apartments booked.
Work Description in Building Pearl Heaven Iv Bldg No 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress98% done
98% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress96% done
96% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Chandiwala Enterprises
for Project
Pearl Heaven Iv
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation