Project overview

Pavapuri is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800053127. Pavapuri is located at 12. This is a New being developed by Kum Kum Enterprises.

Pavapuri has 1 BHK, 2 BHK, Multipurpose Room, Office space & Shop Apartments with carpet areas ranging from 0 to 709 Sq.ft. Carpet. The Project has total 72 of which 72 are currently available for sale.

Pavapuri is being developed on a total land area of 16467 Sq.ft. Pavapuri has 2 Wings / Towers Pavapuri Wing B,Pavapuri Wing C

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Pavapuri
  • Location:
  • 12
  • Const. Stage:
    New
  • Possession:
    31 Dec 2026
Developer Details

  • Developer:
    Kum Kum Enterprises
  • Phone:
  • Address:
  • Barsana Bldg(West)
Project RERA Details
MAHA REARA No: P51800053127
Project Type Others
RERA Project Status New
Architect Space Vision
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 31 Dec 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 16 Oct 2023
Last Retrived 26 Jul 2025
Pavapuri QR Code
Pavapuri
MahaRERA - P51800053127
Apartment Details & Configuration
TypeArea
1 BHK37.21 Sq.mts. ( 401 Sq.ft. )
1 BHK28.38 Sq.mts. ( 305 Sq.ft. )
2 BHK48.12 Sq.mts. ( 518 Sq.ft. )
2 BHK48.26 Sq.mts. ( 519 Sq.ft. )
2 BHK56.68 Sq.mts. ( 610 Sq.ft. )
Fitness Centre33.82 Sq.mts. ( 364 Sq.ft. )
Multipurpose Room0 Sq.mts. ( 0 Sq.ft. )
Shop12.26 Sq.mts. ( 132 Sq.ft. )
Shop13.39 Sq.mts. ( 144 Sq.ft. )
Shop15.95 Sq.mts. ( 172 Sq.ft. )
Shop16.82 Sq.mts. ( 181 Sq.ft. )
Shop16.96 Sq.mts. ( 183 Sq.ft. )
Shop17.69 Sq.mts. ( 190 Sq.ft. )
Shop25.21 Sq.mts. ( 271 Sq.ft. )
1 BHK32.61 Sq.mts. ( 351 Sq.ft. )
1 BHK37.07 Sq.mts. ( 399 Sq.ft. )
2 BHK65.83 Sq.mts. ( 709 Sq.ft. )
Shop12.23 Sq.mts. ( 132 Sq.ft. )
Shop29.6 Sq.mts. ( 319 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Pavapurilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
Only Electric Meter Rooms
Energy management
Na
Fire Protection And Fire Safety Requirements70% completed
70% Complete
As Per Cfo Norms
Landscaping & Tree Planting
As Per Tree Noc
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Only Chambers &Amp; Lids
Solid Waste Management And Disposal
Will Be Provide
Storm Water Drains90% completed
90% Complete
As Per Norms
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Will Be Provide
Water Supply
As Per Norms
Buildings / Wings in Pavapuri
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Pavapuri by Kum Kum Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

16467 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

72 apartments in total
Total
72
Booked
0
Available
72

Saleable Area Statistics (Sq. ft.)

31501 Total
Total
31501
Booked
0
Available
31501
Total 72 apartments in project. 0 apartments booked. 0% apartments booked.
Total 31501 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Pavapuri Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Pavapuri Wing BDec 20269100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.21 Sq.mts. ( 401 Sq.ft. )5
None Booked0% Booked
0% Booked
1 BHK28.38 Sq.mts. ( 305 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK48.12 Sq.mts. ( 518 Sq.ft. )9
None Booked0% Booked
0% Booked
2 BHK48.26 Sq.mts. ( 519 Sq.ft. )6
None Booked0% Booked
0% Booked
2 BHK56.68 Sq.mts. ( 610 Sq.ft. )9
None Booked0% Booked
0% Booked
Fitness Centre33.82 Sq.mts. ( 364 Sq.ft. )1
None Booked0% Booked
0% Booked
Multipurpose Room0 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Office space0 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Shop12.26 Sq.mts. ( 132 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop13.39 Sq.mts. ( 144 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop15.95 Sq.mts. ( 172 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.82 Sq.mts. ( 181 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.96 Sq.mts. ( 183 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop17.69 Sq.mts. ( 190 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop25.21 Sq.mts. ( 271 Sq.ft. )1
None Booked0% Booked
0% Booked
38 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Pavapuri Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress95% done
95% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress64% done
64% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
work-in-progress95% done
95% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Pavapuri Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Pavapuri Wing CDec 20268100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.61 Sq.mts. ( 351 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK37.07 Sq.mts. ( 399 Sq.ft. )8
None Booked0% Booked
0% Booked
1 BHK37.21 Sq.mts. ( 401 Sq.ft. )10
None Booked0% Booked
0% Booked
2 BHK56.68 Sq.mts. ( 610 Sq.ft. )8
None Booked0% Booked
0% Booked
2 BHK65.83 Sq.mts. ( 709 Sq.ft. )1
None Booked0% Booked
0% Booked
Multipurpose Room0 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Office space0 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Shop12.23 Sq.mts. ( 132 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop13.39 Sq.mts. ( 144 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.82 Sq.mts. ( 181 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.96 Sq.mts. ( 183 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop17.69 Sq.mts. ( 190 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop29.6 Sq.mts. ( 319 Sq.ft. )1
None Booked0% Booked
0% Booked
34 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Pavapuri Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress95% done
95% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress64% done
64% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
work-in-progress95% done
95% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Kum Kum Enterprises
for Project
Pavapuri
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation