Project overview
Parmarth Niketan - Redevelopment Of Mani Bhuvan is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800001745. Parmarth Niketan - Redevelopment Of Mani Bhuvan is located at 2688/ 1 To 9, 2688. This is a Ongoing being developed by J V Constructions & Developers.
Parmarth Niketan - Redevelopment Of Mani Bhuvan has 1 BHK & 2 BHK Apartments with carpet areas ranging from 331 to 553 Sq.ft. Carpet. The Project has total 51 of which 26 are currently available for sale.
Parmarth Niketan - Redevelopment Of Mani Bhuvan is being developed on a total land area of 8666 Sq.ft. Parmarth Niketan - Redevelopment Of Mani Bhuvan has 1 Wings / Towers Parmarth Niketan - Redevelopment Of Mani Bhuvan
| Project | Developer | Location | Possession |
| MAHA REARA No: |
P51800001745 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
A R Mehta & Associates |
| Funding Bank |
IDBI BANK |
| Proposed Possession |
31 Dec 2019 |
| Revised Possession |
31 Dec 2019 |
| Extended Possession |
30 Jun 2023 |
| Litigations |
No Litigations |
| Last Modified |
09 Sep 2021 |
| Last Retrived |
26 Jul 2025 |
Parmarth Niketan - Redevelopment Of Mani Bhuvan QR Code
Parmarth Niketan - Redevelopment Of Mani Bhuvan
MahaRERA - P51800001745
| Type | Area |
| 1 BHK | 30.76 Sq.mts. ( 331 Sq.ft. ) |
| 1 BHK | 30.96 Sq.mts. ( 333 Sq.ft. ) |
| 1 BHK | 33.71 Sq.mts. ( 363 Sq.ft. ) |
| 1 BHK | 33.74 Sq.mts. ( 363 Sq.ft. ) |
| 1 BHK | 36.6 Sq.mts. ( 394 Sq.ft. ) |
| 2 BHK | 51.42 Sq.mts. ( 553 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Parmarth Niketan - Redevelopment Of Mani Bhuvanlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Na |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Na |
Landscaping & Tree Planting100% completed
|
|
Na |
Open Parking100% completed
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Na |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains100% completed
|
|
Na |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
Na |
|
|
|
Na |
Buildings / Wings in Parmarth Niketan - Redevelopment Of Mani Bhuvan
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Parmarth Niketan - Redevelopment Of Mani Bhuvan by J V Constructions & Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
51
apartments in total
Saleable Area Statistics (Sq. ft.)
20863
Total
Total 51 apartments in project. 25 apartments booked. 49% apartments booked.
Total 20863 Sq.ft. saleable area. 10285 saleable area booked.
49% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Parmarth Niketan - Redevelopment Of Mani Bhuvan | Dec 2020 | 14 | 1 | 0 | 1 | 0 | 6 | 18 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 30.76 Sq.mts. ( 331 Sq.ft. ) | 10 | |
| 1 BHK | 30.96 Sq.mts. ( 333 Sq.ft. ) | 5 | |
| 1 BHK | 33.71 Sq.mts. ( 363 Sq.ft. ) | 4 | |
| 1 BHK | 33.74 Sq.mts. ( 363 Sq.ft. ) | 8 | |
| 1 BHK | 36.6 Sq.mts. ( 394 Sq.ft. ) | 11 | |
| 2 BHK | 51.42 Sq.mts. ( 553 Sq.ft. ) | 13 | |
51 total apartments / 25 apartments booked. 49% apartments booked. |
| Work Description in Building Parmarth Niketan - Redevelopment Of Mani Bhuvan | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
J V Constructions & Developers
for Project
Parmarth Niketan - Redevelopment Of Mani Bhuvan
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |