Project overview

Ostwal Paradise Building No.9 Wing A - B - C is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700048041. Ostwal Paradise Building No.9 Wing A - B - C is located at Old S No 364 New S No 67 H No 4B Old S No 365 New S No 71 Hissa No 17. This is a New being developed by Shree Ostwal Builders Ltd.

Ostwal Paradise Building No.9 Wing A - B - C has 1 BHK & 2 BHK Apartments with carpet areas ranging from 410 to 631 Sq.ft. Carpet. The Project has total 194 of which 107 are currently available for sale.

Ostwal Paradise Building No.9 Wing A - B - C is being developed on a total land area of 27556 Sq.ft. Ostwal Paradise Building No.9 Wing A - B - C has 3 Wings / Towers Ostwal Paradise Building No 9 Wing - A,Ostwal Paradise Building No 9 Wing - B,Ostwal Paradise Building No 9 Wing - C

ProjectDeveloperLocationPossession
ArcadiaJangid PropertiesNew Survey Number 60/230-04-2018 00:00:00
12Th AvenueSadguru Baba Developers LlpMira Road31-12-2021 00:00:00
BhargavR N EnterprisesS.N 191 H.N.2B31-12-2019 00:00:00
Mangal Pushp HeightsSunil Mangilal JainOld Sno 668 New Sno 257 Hno 1 /7 Village Bhayander Dist Thane30-12-2023 00:00:00
Ideal ParkIdeal Builder & Developers84 Hissa No 115-08-2019 00:00:00
Balaji HeightsShree Balaji RealityOld Sno 2217 New Sno 195730-04-2018 00:00:00
Anand Park D WingR K DevelopmentOld S.N.223 N.S.No.191 H.No.178631-07-2018 00:00:00
Shree Ambesh Complex And Ambesh BhavanShree Ambesh ConstructionThane, 40110531-07-2020 00:00:00
Shubham GardenShubham Drashti EnterprisesNew 1712 30-04-2022 00:00:00
Raj EnclaveRatna Priya BuildersOld Sno 331 New Sno 27 Hno 5 Of Village Goddev30-12-2022 00:00:00
Keystone ClassicKeystone Classic401107, Thane30-04-2020 00:00:00
Shalom JoveCottadiyil EnterprisesOld Sno 563, 566 New Sno 205,219 Hno 1 And 5 Village Bhayander Dist Thane31-12-2018 00:00:00
Sheetal Complex Wing D EAbhay Builders401107, Thane05-08-2018 00:00:00
Lodha Mira Road Project 1Macrotech Developers Limited90/3, 91/2, 98/228-11-2022 00:00:00
MahadevshreeM.M.Construction3308,9, 3311A31-01-2021 00:00:00
Sai PlazaShree Sai Shakti Developers19 New Hissa No 1 6B And 15 Hissa No 1030-12-2023 00:00:00
Sector Vi/E-6Shantistar Builders736 Bhayander Village30-09-2020 00:00:00
N G Silver SpringRna Builders (Ng)3102P, 3111115-12-2018 00:00:00
Salasar GreensSalasar Estate Developers LlpOld 299 New 180 H.No 425-12-2022 00:00:00
N G BavenoRna Builders (Ng)Survey No 336 Hissa No 215-12-2019 00:00:00
Medtiya RavirajS.N. BuildersOld Sno 316/2 New Sno 40/230-12-2022 00:00:00
Ruheena AppartmentSairajdevelop401104, Thane31-12-2020 00:00:00
V. M. HeightsSwayam DevelopersThane, 40110731-12-2018 00:00:00
Nida Amisha HeightsSai Krupa DevelopersOld Survey No 21 Part And New Survey No 76 Hissa No 401-07-2026 00:00:00
Deepak ApartmentSilver & Rashi ConstructionsNew 54 H No 6 And 725-12-2018 00:00:00
Shreenath AvenueShreenath Enterprises1031-03-2018 00:00:00
Rishita ApartmentShanti EnterpriseOld Survey No 308/9 New Survey No 54/931-12-2018 00:00:00
Unique Orbit-IUnique Shanti RealtorsS No. 401 H No 4B Off Village Ghoddev Mira Road East Thane 30-12-2020 00:00:00
Sagar AccordM/ S. S A RealtyThane30-12-2021 00:00:00
Usha Kiran HeightsSai Sparsh DevelopersNear Vinayak Temple30-12-2022 00:00:00
Walchand Nagar - 2Prakash Hamirmal JainOld S No 220 New S No 430-04-2018 00:00:00
Unique Orbit IiUnique Shanti RealtorsS No 401 Hissa No 3A 3B 3C And S No 401 Hissa No 630-12-2020 00:00:00
Heeru SadanHemant JainThane, 40110101-09-2018 00:00:00
Mini MarketHemant S JainOld Survey 136/1Pt New Survey 98/1 A And C31-12-2018 00:00:00
Skywards RegencySkywards Vision Developers119 1N 1C 1D Mauje Davle Thane30-06-2020 00:00:00
YashshantiSiddhivinayak DevelopersOld Sno 2102 New 95218-10-2018 00:00:00
Ramdev VillaRamdev VillaOld Survey No.376, Hissa No.231-01-2018 00:00:00
Arihant PlazaArihant DevelopersOld Sno 2508 New Sno 46831-12-2019 00:00:00
N G AvenueRna Builders (Ng)40110131-12-2023 00:00:00
N G Silver Spring Phase IiiRna Builders (Ng)Old S No 310 New S No 56 H No 2P Old S No 311 New S No 43 H No 131-12-2024 00:00:00
Poonam SquareRohit Devendra GoyalOld S No 45230-12-2021 00:00:00
The Address Building No.7/8/9Strawberry Constructions Pvt. Ltd.S.No.407/3, 411/3,6,9, 412/1,2,4,6, 413/3P, 4, 5P, 6,7, 414/1,2Pt30-06-2021 00:00:00
Balaji HeightBalaji BuildconThane01-05-2020 00:00:00
Imperial Heights Phase I - A And B WingAkshar Shanti Realtors Private Limited12/130-12-2024 00:00:00
The Address Building No.5Strawberry Constructions Pvt. Ltd.S.No.407/3, 411/3,6,9, 412/1,2,4,6, 413/3P,6,7, 414/1/,Pt30-12-2022 00:00:00
Raviraj SpringMira Housing Development Corporation15215-12-2018 00:00:00
Prithvi SnehPrithvi Buildworth Constructions401107, Thane31-12-2025 00:00:00
Silver SpringM/S. Shri Venkatesh Ramdev HomesNew Survey No 11 Hissa No 2B30-03-2022 00:00:00
Kakad Paradise Phase 2Kakad Housing CorporationPart Of 48/4 48/5 48/10 48/11 48/14 48/22 48/23 48/20 48/15 48/18 48/19 48/21 46/3 46/2 45/130-06-2024 00:00:00
Project Details
  • Project:
    Ostwal Paradise Building No.9 Wing A - B - C
  • Location:
  • Old S No 364 New S No 67 H No 4B Old S No 365 New S No 71 Hissa No 17
  • Const. Stage:
    New
  • Possession:
    31 Dec 2028
Developer Details

  • Developer:
    Shree Ostwal Builders Ltd
  • Phone:
  • Address:
  • Ostwal House
Project RERA Details
MAHA REARA No: P51700048041
Project Type Residential / Group Housing
RERA Project Status New
Architect Amit Kumar Jha
Funding Bank INDUSIND BANK
Proposed Possession 31 Dec 2028
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 19 Jul 2025
Last Retrived 26 Jul 2025
Ostwal Paradise Building No.9 Wing A - B - C QR Code
Ostwal Paradise Building No.9 Wing A - B - C
MahaRERA - P51700048041
Apartment Details & Configuration
TypeArea
1 BHK37.48 Sq.mts. ( 403 Sq.ft. )
1 BHK38.16 Sq.mts. ( 411 Sq.ft. )
1 BHK39.78 Sq.mts. ( 428 Sq.ft. )
1 BHK39.97 Sq.mts. ( 430 Sq.ft. )
2 BHK53.18 Sq.mts. ( 572 Sq.ft. )
2 BHK56.54 Sq.mts. ( 609 Sq.ft. )
1 BHK38.05 Sq.mts. ( 410 Sq.ft. )
1 BHK38.87 Sq.mts. ( 418 Sq.ft. )
2 BHK58.66 Sq.mts. ( 631 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Ostwal Paradise Building No.9 Wing A - B - Clast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
As Per Plan
Energy management
As Per Plan
Fire Protection And Fire Safety Requirements
As Per Plan
Landscaping & Tree Planting
Na
Open Parking
As Per Plan
Sewerage (Chamber, Lines, Septic Tank , STP)
As Per Plan
Solid Waste Management And Disposal
As Per Plan
Storm Water Drains
As Per Plan
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
As Per Plan
Water Conservation, Rain water Harvesting
As Per Plan
Water Supply
Mbmc
Buildings / Wings in Ostwal Paradise Building No.9 Wing A - B - C
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Ostwal Paradise Building No.9 Wing A - B - C by Shree Ostwal Builders Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

27556 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

194 apartments in total
Total
194
Booked
87
Available
107

Saleable Area Statistics (Sq. ft.)

95696 Total
Total
95696
Booked
41449
Available
54247
Total 194 apartments in project. 87 apartments booked. 44% apartments booked.
Total 95696 Sq.ft. saleable area. 41449 saleable area booked.
43% area booked.

Ostwal Paradise Building No 9 Wing - A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Ostwal Paradise Building No 9 Wing - ADec 202823101101
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.48 Sq.mts. ( 403 Sq.ft. )21
16 Booked76% Booked
76% Booked
1 BHK38.16 Sq.mts. ( 411 Sq.ft. )21
16 Booked76% Booked
76% Booked
1 BHK39.78 Sq.mts. ( 428 Sq.ft. )18
1 BHK39.97 Sq.mts. ( 430 Sq.ft. )21
15 Booked71% Booked
71% Booked
81 total apartments / 50 apartments booked. 61% apartments booked.
Work Description in Building Ostwal Paradise Building No 9 Wing - ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress56% done
56% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure

Ostwal Paradise Building No 9 Wing - B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Ostwal Paradise Building No 9 Wing - BDec 202822101101
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK53.18 Sq.mts. ( 572 Sq.ft. )17
4 Booked23% Booked
23% Booked
2 BHK56.54 Sq.mts. ( 609 Sq.ft. )19
11 Booked57% Booked
57% Booked
36 total apartments / 15 apartments booked. 41% apartments booked.
Work Description in Building Ostwal Paradise Building No 9 Wing - BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress59% done
59% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure

Ostwal Paradise Building No 9 Wing - C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Ostwal Paradise Building No 9 Wing - CDec 202822101101
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK38.05 Sq.mts. ( 410 Sq.ft. )20
7 Booked35% Booked
35% Booked
1 BHK38.87 Sq.mts. ( 418 Sq.ft. )17
2 BHK58.66 Sq.mts. ( 631 Sq.ft. )40
12 Booked30% Booked
30% Booked
77 total apartments / 22 apartments booked. 28% apartments booked.
Work Description in Building Ostwal Paradise Building No 9 Wing - CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress59% done
59% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Shree Ostwal Builders Ltd
for Project
Ostwal Paradise Building No.9 Wing A - B - C
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation