Project overview

Ossia Enclave is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800005753. Ossia Enclave is located at 304/1 And 304/2. This is a Ongoing being developed by R. B. Developers.

Ossia Enclave has 1 BHK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 310 to 697 Sq.ft. Carpet. The Project has total 27 of which 7 are currently available for sale.

Ossia Enclave is being developed on a total land area of 5335 Sq.ft. Ossia Enclave has 1 Wings / Towers Ossia Enclave

ProjectDeveloperLocationPossession
Ganeshyog ChsAaruni Harishchandra PatilPlot No 2 Cts 10 10/1 To 731-12-2018 00:00:00
Anise GroveBhagya CorporationSector Ib-I Cts No 374B/3 Part31-12-2018 00:00:00
Neeta Niwas ChslC H Patil And Sons LlpFinal Plot No 35731-12-2018 00:00:00
Ashwini Residency Borivali Ashwini ChslEthics Infra Development Pvt LtdCts No 36031-12-2018 00:00:00
Navkar DevdattMuktistar RealtorsCts 766 767 76230-12-2023 00:00:00
Veena Santoor Phase IiVeena Developers128/A/66/A/3/B31-12-2019 00:00:00
Madhav BaugRajyog ProjectsF.P.No.9330-12-2023 00:00:00
Icon Belle VueIcon Developers535 / 1 To 6, Fp 64, 53528-02-2021 00:00:00
Avirahi Homes Building 3V.M.AssociatesCts No 613-A-131-12-2018 00:00:00
Gorai Shree Ram Tower Chs LtdJagannath Laxman MorePlot 21 Cts No.19/65430-06-2018 00:00:00
Vijaya HeightsVighnahatra Builders And Projects Private Limited472 Pt28-08-2023 00:00:00
Anamika Niwas ChsAditya DevelopersMumbai Suburban, 40009218-12-2018 00:00:00
Patel AssociatesPurshottam Kalubhai Patel125 1 To 4, F P No 305 Tps Iii Cts No 12531-12-2018 00:00:00
Address IiGlorious Construction Company Private Limited38530-09-2020 00:00:00
New Gopal Premises Co-Operative Society LimitedKamla Realty (Bombay)Final Plot No. 212 Of Tps No. Iii30-12-2021 00:00:00
Laxmi ChsAditya Developers16718-01-2021 00:00:00
Dahisar Snehal ChsAditya Developers5512-02-2020 00:00:00
Avirahi HeightsAbhigna Enterprises337/A 350/A31-12-2019 00:00:00
Laxmi Narayan MansionAtharva DevelopersPlot No 35 Of Tps Ii Cts No 16330-01-2022 00:00:00
KathaTanvi Constructions727 Tps Iii31-12-2019 00:00:00
Gayatri ChslKhushi Associates268B30-09-2018 00:00:00
Rbi Employees Ashish ChslTriveni DevelopersFp No 62031-12-2018 00:00:00
Shree MadhuvandhamSunder Corporation436/1-B To 436/1-D30-12-2022 00:00:00
Acharya Ashram Sahakari Griha Rachana Sanstha MaryaditPrarthana Constructions14631-12-2018 00:00:00
Sbi Staff Trinity Chs LtdRajshree Enterprise2 B 331-12-2019 00:00:00
NeelrekhaTasmai Spaces62931-12-2018 00:00:00
Urvashi ChsAditya Developers16516-03-2021 00:00:00
Nutan DreamNootan Associates Llp20230-12-2023 00:00:00
Bt Sujata ChslC H Patil And Sons LlpCts No 1B-1-B31-01-2021 00:00:00
Nayana NiwasH.D.AssociatesC.T.S No 633, 633/1To6 Of Village Borivali31-03-2018 00:00:00
Sanskruti SplendourSanskruti Nirman Pvt. Ltd.251030-12-2022 00:00:00
Morya HeightsShree Varadvinayak Enterprises240/A/1/C30-12-2022 00:00:00
Hari Smruti ChsRamniyati Aditya Developers Llp554B18-08-2022 00:00:00
Sai DeepShree DevelopersBorivali East, 2220B Pt 2231 2232 Of Village Dahisar31-07-2018 00:00:00
JmdvardhamCostal Vincom Pvt LtdCts No 106 107 108 Village Malad31-12-2019 00:00:00
Gorai MitasuSumit Woods Pvt. Ltd.19/545, 19/54631-12-2017 00:00:00
Om Vithal Coop Hsg Soc LtKishor ShahMumbai Suburban, 40009201-09-2019 00:00:00
Central Palace Redevlopment Of Borivali Jitendra Bhavan Co-Op Hsg LtdJesal Damji DedhiaCts No 611 611 1 To12 Of Village Borivali Fp No 5 Tps I30-12-2023 00:00:00
Project Details
  • Project:
    Ossia Enclave
  • Location:
  • 304/1 And 304/2
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2018
Developer Details

  • Developer:
    R. B. Developers
  • Phone:
  • Address:
  • Victory Park
Project RERA Details
MAHA REARA No: P51800005753
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Modi Bhavin Arvind
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 30 Jun 2018
Revised Possession 30 Jun 2018
Extended Possession 30 Jun 2022
Litigations No Litigations
Last Modified 09 Sep 2021
Last Retrived 26 Jul 2025
Ossia Enclave QR Code
Ossia Enclave
MahaRERA - P51800005753
Apartment Details & Configuration
TypeArea
1 BHK28.79 Sq.mts. ( 310 Sq.ft. )
1 BHK32.7 Sq.mts. ( 352 Sq.ft. )
2 BHK54.53 Sq.mts. ( 587 Sq.ft. )
3 BHK57.6 Sq.mts. ( 620 Sq.ft. )
3 BHK63.63 Sq.mts. ( 685 Sq.ft. )
3 BHK64.75 Sq.mts. ( 697 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Ossia Enclavelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station60% completed
60% Complete
Work In Progress
Energy management80% completed
80% Complete
Work In Progress
Fire Protection And Fire Safety Requirements
Work In Progress
Landscaping & Tree Planting
Work In Progress
Open Parking
Work In Progress
Sewerage (Chamber, Lines, Septic Tank , STP)80% completed
80% Complete
Work In Progress
Solid Waste Management And Disposal80% completed
80% Complete
Work In Progress
Storm Water Drains80% completed
80% Complete
Work In Progress
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water80% completed
80% Complete
Work In Progress
Water Conservation, Rain water Harvesting80% completed
80% Complete
Work In Progress
Water Supply80% completed
80% Complete
Upto 5Th Floor
Buildings / Wings in Ossia Enclave
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Ossia Enclave by R. B. Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

5335 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

27 apartments in total
Total
27
Booked
20
Available
7

Saleable Area Statistics (Sq. ft.)

15775 Total
Total
15775
Booked
10997
Available
4778
Total 27 apartments in project. 20 apartments booked. 74% apartments booked.
Total 15775 Sq.ft. saleable area. 10997 saleable area booked.
70% area booked.

Ossia Enclave

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Ossia EnclaveJun 201881020030
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.79 Sq.mts. ( 310 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK32.7 Sq.mts. ( 352 Sq.ft. )5
5 Booked100% Booked
100% Booked
2 BHK54.53 Sq.mts. ( 587 Sq.ft. )7
7 Booked100% Booked
100% Booked
3 BHK57.6 Sq.mts. ( 620 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK63.63 Sq.mts. ( 685 Sq.ft. )7
5 Booked71% Booked
71% Booked
3 BHK64.75 Sq.mts. ( 697 Sq.ft. )6
2 Booked33% Booked
33% Booked
27 total apartments / 20 apartments booked. 74% apartments booked.
Work Description in Building Ossia EnclaveCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress69% done
69% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress85% done
85% Booked
Sanitary Fittings within the flats / premises
work-in-progress85% done
85% Booked
Slabs of Super Structure
work-in-progress70% done
70% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress65% done
65% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress70% done
70% Booked
Channel Partners
Channel Partners Registered by Developer
R. B. Developers
for Project
Ossia Enclave
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation