Project overview

Ornate Kallisto Phase Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700018908. Ornate Kallisto Phase Ii is located at 120/2 P And 120/3 P. This is a New being developed by Ornate Buildcon Developers.

Ornate Kallisto Phase Ii has 1 BHK & 2 BHK Apartments with carpet areas ranging from 327 to 620 Sq.ft. Carpet. The Project has total 174 of which 107 are currently available for sale.

Ornate Kallisto Phase Ii is being developed on a total land area of 72980 Sq.ft. out of which 3769 Sq.ft. i.e 5% is reserved for recreational purposes. Ornate Kallisto Phase Ii has 1 Wings / Towers Ornate Kallisto Phase Ii

ProjectDeveloperLocationPossession
Hubtown Sunstone A WingSunstone Developers Joint Venture629 Pt30-12-2025 00:00:00
Hubtown Sunstone B WingSunstone Developers Joint Venture629 Pt30-12-2025 00:00:00
Rustomjee Seasons - Wing CKeystone Realtors Limited2, 6, 648, 330-12-2021 00:00:00
Rustomjee Seasons - Wing BKeystone Realtors Limited3, 6, 648, 230-12-2021 00:00:00
Rustomjee Seasons - Wing AKeystone Realtors Limited6, 2, 3, 648-130-12-2022 00:00:00
Planning, Designing And Construction Of 196 Mig T/S And 2 Amenties At Mira RoadMaharashtra Housing And Area Development AuthorityKalanagar, Mumbai Suburban, 40005131-12-2019 00:00:00
Ornate Kallisto Phase IiOrnate Buildcon Developers120/2 P And 120/3 P30-12-2024 00:00:00
Aarc ResidencyAarc Housing Co14830-03-2021 00:00:00
A And O EstadoAshapura Builders And DevelopersMumbai Suburban31-12-2021 00:00:00
Vinayak Shraddha TowerK K Krishnan Construction Company Pvt Ltd617 62930-03-2023 00:00:00
Kalpataru MagnusKalpataru Properties Pvt. Ltd.629 Part Of Village Bandra East30-06-2024 00:00:00
Ten BkcMig (Bandra) Realtors & Builders Private Limited649, 649/1 To 649/4806-06-2023 00:00:00
64 Lig, 80 Mig, 16Hig And 20 Shops At Sr. No. 491, Res. No. 23 Part, Vengurla, Dist. SindhudurgMaharashtra Housing And Area Development Authority49131-05-2018 00:00:00
Construction Of Lig And Mig Tenement At Virar BolinjKonkan Housing And Area Development BoardS No 392 P 376 P Virar Bolinj Dist Palghar29-03-2018 00:00:00
Project Details
  • Project:
    Ornate Kallisto Phase Ii
  • Location:
  • 120/2 P And 120/3 P
  • Const. Stage:
    New
  • Possession:
    30 Dec 2024
Developer Details

  • Developer:
    Ornate Buildcon Developers
  • Phone:
  • Address:
  • Pramukh Plaza Premises
Project RERA Details
MAHA REARA No: P51700018908
Project Type Residential / Group Housing
RERA Project Status New
Architect K K & Associates
Funding Bank INDUSIND BANK
Proposed Possession 30 Dec 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 12 Dec 2018
Last Retrived 26 Jul 2025
Ornate Kallisto Phase Ii QR Code
Ornate Kallisto Phase Ii
MahaRERA - P51700018908
Apartment Details & Configuration
TypeArea
1 BHK30.38 Sq.mts. ( 327 Sq.ft. )
1 BHK33.03 Sq.mts. ( 356 Sq.ft. )
1 BHK35.69 Sq.mts. ( 384 Sq.ft. )
2 BHK51.02 Sq.mts. ( 549 Sq.ft. )
2 BHK52.71 Sq.mts. ( 567 Sq.ft. )
2 BHK54.38 Sq.mts. ( 585 Sq.ft. )
2 BHK57.6 Sq.mts. ( 620 Sq.ft. )
2 BHK57.61 Sq.mts. ( 620 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Ornate Kallisto Phase Iilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
As Per Bncmc
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
As Per Bncmc
Energy management100% completed
95% Complete
As Per Bncmc
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Bncmc
Landscaping & Tree Planting60% completed
60% Complete
As Per Bncmc
Open Parking
As Per Bncmc
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
As Per Bncmc
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
As Per Bncmc
Street Lighting70% completed
70% Complete
As Per Bncmc
Treatment And Disposal Of Sewage And Sullage Water30% completed
30% Complete
As Per Bncmc
Water Conservation, Rain water Harvesting100% completed
95% Complete
As Per Bncmc
Water Supply65% completed
65% Complete
As Per Bncmc
Buildings / Wings in Ornate Kallisto Phase Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Ornate Kallisto Phase Ii by Ornate Buildcon Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

72980 Sq. ft.

Project Area

3769 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

174 apartments in total
Total
174
Booked
67
Available
107

Saleable Area Statistics (Sq. ft.)

80439 Total
Total
80439
Booked
26561
Available
53878
Total 174 apartments in project. 67 apartments booked. 38% apartments booked.
Total 80439 Sq.ft. saleable area. 26561 saleable area booked.
33% area booked.

Ornate Kallisto Phase Ii

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Ornate Kallisto Phase IiJun 2023171010036
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.38 Sq.mts. ( 327 Sq.ft. )32
21 Booked65% Booked
65% Booked
1 BHK33.03 Sq.mts. ( 356 Sq.ft. )32
22 Booked68% Booked
68% Booked
1 BHK35.69 Sq.mts. ( 384 Sq.ft. )30
10 Booked33% Booked
33% Booked
2 BHK51.02 Sq.mts. ( 549 Sq.ft. )16
2 BHK52.71 Sq.mts. ( 567 Sq.ft. )16
11 Booked68% Booked
68% Booked
2 BHK54.38 Sq.mts. ( 585 Sq.ft. )16
None Booked0% Booked
0% Booked
2 BHK57.6 Sq.mts. ( 620 Sq.ft. )16
2 BHK57.61 Sq.mts. ( 620 Sq.ft. )16
174 total apartments / 67 apartments booked. 38% apartments booked.
Work Description in Building Ornate Kallisto Phase IiCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Ornate Buildcon Developers
for Project
Ornate Kallisto Phase Ii
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation