Project overview
Opulence is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800002068. Opulence is located at Cts No 256A/1A, 256A/1C, 256A/1B. This is a Ongoing being developed by Sidhivinayak Constructions.
Opulence has 1 BHK & 2 BHK Apartments with carpet areas ranging from 452 to 667 Sq.ft. Carpet. The Project has total 68 of which 16 are currently available for sale.
Opulence is being developed on a total land area of 16832 Sq.ft. out of which 2559 Sq.ft. i.e 15% is reserved for recreational purposes. Opulence has 1 Wings / Towers Opulence
| Project | Developer | Location | Possession |
| S R Scheme At Turbhe Mandale Mankhurd | Shivshahi Punarvasan Prakalp Ltd | 6/1 Part Of Mandale Village | 30-12-2023 00:00:00 |
| Sabari Horizon | Sabari Developers Llp | Cts No 422, 422 A1 Deonar | 31-05-2019 00:00:00 |
| Shakti Unicus | Raheja & Co | 7B/4 | 31-12-2018 00:00:00 |
| Good Relation -Wing B | Skyrise Enterpirses | Cts 396 398 | 31-12-2018 00:00:00 |
| MAHA REARA No: |
P51800002068 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
Bansi Wadhwa |
| Funding Bank |
DCB BANK LIMITED |
| Proposed Possession |
31 Dec 2018 |
| Revised Possession |
31 Dec 2018 |
| Extended Possession |
30 Dec 2020 |
| Litigations |
No Litigations |
| Last Modified |
17 Jun 2020 |
| Last Retrived |
26 Jul 2025 |
Opulence QR Code
Opulence
MahaRERA - P51800002068
| Type | Area |
| 1 BHK | 42 Sq.mts. ( 452 Sq.ft. ) |
| 2 BHK | 62 Sq.mts. ( 667 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Opulencelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Na |
Energy management100% completed
|
|
Na |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Na |
Landscaping & Tree Planting
|
|
Na |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Na |
Solid Waste Management And Disposal100% completed
|
|
Na |
Storm Water Drains100% completed
|
|
Na |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water10% completed
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
Na |
Water Supply100% completed
|
|
Na |
Buildings / Wings in Opulence
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Opulence by Sidhivinayak Constructionslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
68
apartments in total
Saleable Area Statistics (Sq. ft.)
41721
Total
Total 68 apartments in project. 52 apartments booked. 76% apartments booked.
Total 41721 Sq.ft. saleable area. 31259 saleable area booked.
75% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Opulence | Dec 2018 | 20 | 1 | 0 | 1 | 3 | 2 | 62 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 42 Sq.mts. ( 452 Sq.ft. ) | 17 | |
| 2 BHK | 62 Sq.mts. ( 667 Sq.ft. ) | 51 | |
68 total apartments / 52 apartments booked. 76% apartments booked. |
| Work Description in Building Opulence | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Sidhivinayak Constructions
for Project
Opulence
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |