Project overview

Om Palace is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800002838. Om Palace is located at 344/1 To 16, 344, 342. This is a Ongoing being developed by P. G. Enterprises.

Om Palace has REHAB UNIT Apartments with carpet areas ranging from 269 to 269 Sq.ft. Carpet. The Project has total 140 of which 33 are currently available for sale.

Om Palace is being developed on a total land area of 17050 Sq.ft. out of which 1111 Sq.ft. i.e 7% is reserved for recreational purposes. Om Palace has 2 Wings / Towers Om Palace,Snehal Sadan Sra Chsl

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Om Palace
  • Location:
  • 344/1 To 16, 344, 342
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2019
Developer Details

  • Developer:
    P. G. Enterprises
  • Phone:
  • Address:
  • Om Shree Labh Chsl
Project RERA Details
MAHA REARA No: P51800002838
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Kahaanprojectconsultants
Funding Bank STATE BANK OF INDIA
Proposed Possession 30 Jun 2019
Revised Possession 30 Jun 2019
Extended Possession 31 Jul 2023
Litigations No Litigations
Last Modified 25 Aug 2022
Last Retrived 26 Jul 2025
Om Palace QR Code
Om Palace
MahaRERA - P51800002838
Apartment Details & Configuration
TypeArea
1 BHK36.25 Sq.mts. ( 390 Sq.ft. )
REHAB UNIT25 Sq.mts. ( 269 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Om Palacelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space50% completed
50% Complete
Work In Progress
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station40% completed
40% Complete
Work In Progress
Energy management
Na
Fire Protection And Fire Safety Requirements50% completed
50% Complete
Work In Progress
Landscaping & Tree Planting50% completed
50% Complete
Work In Progress
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Work In Progress
Solid Waste Management And Disposal
Na
Storm Water Drains50% completed
50% Complete
Work In Progress
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water50% completed
50% Complete
Work In Progress
Water Conservation, Rain water Harvesting100% completed
95% Complete
Work In Progress
Water Supply50% completed
50% Complete
Work In Progress
Buildings / Wings in Om Palace
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Om Palace by P. G. Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

17050 Sq. ft.

Project Area

1111 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

140 apartments in total
Total
140
Booked
107
Available
33

Saleable Area Statistics (Sq. ft.)

45424 Total
Total
45424
Booked
34122
Available
11302
Total 140 apartments in project. 107 apartments booked. 76% apartments booked.
Total 45424 Sq.ft. saleable area. 34122 saleable area booked.
75% area booked.

Om Palace

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Om PalaceJun 2019231000210
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.25 Sq.mts. ( 390 Sq.ft. )64
44 Booked68% Booked
68% Booked
64 total apartments / 44 apartments booked. 68% apartments booked.
Work Description in Building Om PalaceCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress50% done
50% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress60% done
60% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress60% done
60% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress65% done
65% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress40% done
40% Booked
Sanitary Fittings within the flats / premises
work-in-progress40% done
40% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress50% done
50% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Snehal Sadan Sra Chsl

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Snehal Sadan Sra ChslJun 201923105080
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
REHAB UNIT25 Sq.mts. ( 269 Sq.ft. )76
63 Booked82% Booked
82% Booked
76 total apartments / 63 apartments booked. 82% apartments booked.
Work Description in Building Snehal Sadan Sra ChslCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress98% done
98% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress98% done
98% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress98% done
98% Booked
Sanitary Fittings within the flats / premises
work-in-progress98% done
98% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
P. G. Enterprises
for Project
Om Palace
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation