Project overview

Nisarg Residency is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000013350. Nisarg Residency is located at S No.125 H No. 1/1. This is a Ongoing being developed by Panchratna Developers.

Nisarg Residency has 1 BHK Apartments with carpet areas ranging from 303 to 312 Sq.ft. Carpet. The Project has total 119 of which 5 are currently available for sale.

Nisarg Residency is being developed on a total land area of 53820 Sq.ft. out of which 7729 Sq.ft. i.e 14% is reserved for recreational purposes. Nisarg Residency has 5 Wings / Towers Nisarg Residency - Wing A,Nisarg Residency - Wing B,Nisarg Residency - Wing C,Nisarg Residency - Wing E,Nisarg Residncy- Wing D

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Nisarg Residency
  • Location:
  • S No.125 H No. 1/1
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    Panchratna Developers
  • Phone:
  • Address:
  • Nisarg Rsidency
Project RERA Details
MAHA REARA No: P99000013350
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sanjay Narang
Funding Bank
Proposed Possession 30 Dec 2023
Revised Possession 30 Dec 2023
Extended Possession 29 Dec 2024
Litigations No Litigations
Last Modified 10 Jun 2025
Last Retrived 28 Jul 2025
Nisarg Residency QR Code
Nisarg Residency
MahaRERA - P99000013350
Apartment Details & Configuration
TypeArea
1 BHK28.61 Sq.mts. ( 308 Sq.ft. )
1 BHK39.39 Sq.mts. ( 424 Sq.ft. )
2 BHK42.91 Sq.mts. ( 462 Sq.ft. )
2 BHK43.25 Sq.mts. ( 466 Sq.ft. )
2 BHK43.9 Sq.mts. ( 473 Sq.ft. )
1 BHK21.51 Sq.mts. ( 232 Sq.ft. )
1 BHK21.96 Sq.mts. ( 236 Sq.ft. )
1 BHK22.38 Sq.mts. ( 241 Sq.ft. )
1 BHK22.82 Sq.mts. ( 246 Sq.ft. )
1 BHK28.25 Sq.mts. ( 304 Sq.ft. )
1 BHK29.03 Sq.mts. ( 312 Sq.ft. )
1 BHK31.19 Sq.mts. ( 336 Sq.ft. )
1 BHK31.63 Sq.mts. ( 340 Sq.ft. )
2 BHK46.57 Sq.mts. ( 501 Sq.ft. )
2 BHK46.99 Sq.mts. ( 506 Sq.ft. )
1 BHK29.39 Sq.mts. ( 316 Sq.ft. )
1 BHK28.2 Sq.mts. ( 304 Sq.ft. )
1 BHK28.53 Sq.mts. ( 307 Sq.ft. )
1 BHK28.97 Sq.mts. ( 312 Sq.ft. )
2 BHK39.55 Sq.mts. ( 426 Sq.ft. )
2 BHK39.91 Sq.mts. ( 430 Sq.ft. )
1 BHK28.15 Sq.mts. ( 303 Sq.ft. )
1 BHK28.17 Sq.mts. ( 303 Sq.ft. )
1 BHK28.49 Sq.mts. ( 307 Sq.ft. )
1 BHK28.51 Sq.mts. ( 307 Sq.ft. )
1 BHK28.54 Sq.mts. ( 307 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nisarg Residencylast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings50% completed
50% Complete
0
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
0
Energy management50% completed
50% Complete
0
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting50% completed
50% Complete
0
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
0
Solid Waste Management And Disposal50% completed
50% Complete
0
Storm Water Drains50% completed
50% Complete
0
Street Lighting50% completed
50% Complete
0
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting50% completed
50% Complete
0
Water Supply50% completed
50% Complete
0
Buildings / Wings in Nisarg Residency
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nisarg Residency by Panchratna Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

53820 Sq. ft.

Project Area

7729 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

119 apartments in total
Total
119
Booked
114
Available
5

Saleable Area Statistics (Sq. ft.)

41503 Total
Total
41503
Booked
39986
Available
1517
Total 119 apartments in project. 114 apartments booked. 95% apartments booked.
Total 41503 Sq.ft. saleable area. 39986 saleable area booked.
96% area booked.

Nisarg Residency - Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Nisarg Residency - Wing ADec 20235101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.61 Sq.mts. ( 308 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK39.39 Sq.mts. ( 424 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK42.91 Sq.mts. ( 462 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK43.25 Sq.mts. ( 466 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK43.9 Sq.mts. ( 473 Sq.ft. )4
4 Booked100% Booked
100% Booked
19 total apartments / 19 apartments booked. 100% apartments booked.
Work Description in Building Nisarg Residency - Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress75% done
75% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress30% done
30% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Nisarg Residency - Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Nisarg Residency - Wing BDec 20225101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK21.51 Sq.mts. ( 232 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK21.96 Sq.mts. ( 236 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK22.38 Sq.mts. ( 241 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK22.82 Sq.mts. ( 246 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK28.25 Sq.mts. ( 304 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK29.03 Sq.mts. ( 312 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK31.19 Sq.mts. ( 336 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK31.63 Sq.mts. ( 340 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK46.57 Sq.mts. ( 501 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK46.99 Sq.mts. ( 506 Sq.ft. )4
4 Booked100% Booked
100% Booked
34 total apartments / 34 apartments booked. 100% apartments booked.
Work Description in Building Nisarg Residency - Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress75% done
75% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress62% done
62% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress30% done
30% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress40% done
40% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Nisarg Residency - Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Nisarg Residency - Wing CDec 20235101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.61 Sq.mts. ( 308 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK29.39 Sq.mts. ( 316 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK42.91 Sq.mts. ( 462 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK43.25 Sq.mts. ( 466 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK43.9 Sq.mts. ( 473 Sq.ft. )4
4 Booked100% Booked
100% Booked
18 total apartments / 18 apartments booked. 100% apartments booked.
Work Description in Building Nisarg Residency - Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress75% done
75% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress30% done
30% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Nisarg Residency - Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Nisarg Residency - Wing EDec 20235101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.2 Sq.mts. ( 304 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK28.53 Sq.mts. ( 307 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK28.97 Sq.mts. ( 312 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK39.55 Sq.mts. ( 426 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK39.91 Sq.mts. ( 430 Sq.ft. )4
4 Booked100% Booked
100% Booked
19 total apartments / 17 apartments booked. 89% apartments booked.
Work Description in Building Nisarg Residency - Wing ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress75% done
75% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress30% done
30% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Nisarg Residncy- Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Nisarg Residncy- Wing DDec 20235101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.15 Sq.mts. ( 303 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK28.17 Sq.mts. ( 303 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK28.2 Sq.mts. ( 304 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK28.49 Sq.mts. ( 307 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK28.51 Sq.mts. ( 307 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK28.54 Sq.mts. ( 307 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK28.97 Sq.mts. ( 312 Sq.ft. )8
8 Booked100% Booked
100% Booked
29 total apartments / 26 apartments booked. 89% apartments booked.
Work Description in Building Nisarg Residncy- Wing DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress75% done
75% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress30% done
30% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Panchratna Developers
for Project
Nisarg Residency
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation