Project overview

Nisarg Greens- Phase Ii A is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700008839. Nisarg Greens- Phase Ii A is located at Rh 1. This is a Ongoing being developed by Nnd Ambernath Llp.

Nisarg Greens- Phase Ii A has 1 BHK, 2 BHK COMPACT & Shop Apartments with carpet areas ranging from 224 to 432 Sq.ft. Carpet. The Project has total 540 of which 15 are currently available for sale.

Nisarg Greens- Phase Ii A is being developed on a total land area of 189326 Sq.ft. Nisarg Greens- Phase Ii A has 6 Wings / Towers Daffodil A Bldg No 15,Daffodil B Bldg No 16,Lotus A Bldg No 7,Lotus B Bldg No 8,Sunflower E Bldg No 13,Sunflower F Bldg No 14

ProjectDeveloperLocationPossession
G Square Commercial HubM/S. Gandhi Builders & Developers39 Pt31-10-2024 00:00:00
Madhuban ParkRajnb Housing LlpPlot No 21 Gut No 55 P31-03-2023 00:00:00
Nisarg Greens Phase - 2 FNnd Ambernath LlpRh 130-06-2025 00:00:00
Nisarg Greens Phase - 2 ENnd Ambernath LlpRh 130-06-2025 00:00:00
Nisarg Greens Phase - 2 DNnd Ambernath LlpRh 130-06-2025 00:00:00
Panvelkar Crown B WingRahul Vijay PanvelkarG No 18 P No 16 1731-12-2024 00:00:00
Sadashiv PuramSatyabhama DevelopersGut No 10 Cts 928515-03-2018 00:00:00
Namaskar Co-Op Hsg SocietyV. R. BuildersPlot No 4 Gut No 5330-03-2023 00:00:00
Sai ResidencyKalpavruksha DevelopersSurvey No 19 Hisssa No 231-12-2017 00:00:00
Charms Global City - Type B2 - EiffelCharms GlobalGut No.42 43 Pt30-06-2025 00:00:00
Morivali Richmand ParkShree Khodiyar BuildconSurvey No 41 Plot No H430-11-2024 00:00:00
Morivali PrarambhShree Khodiyar BuildconSurvey No 41 Plot No H 530-11-2024 00:00:00
Sai ImperiaSadashiv InfraGut No 1 Cts No 930110-08-2018 00:00:00
Vardhaman HomesJay Ambe DevelopersGut No.22-Cts No.9317, Gut No 24-Cts No.932031-12-2018 00:00:00
Nisarg Greens- Phase Ii ANnd Ambernath LlpRh 130-12-2021 00:00:00
Parshuram ResidencyShree Radha DevelopersGut No 13 Cts No 928731-05-2019 00:00:00
Anita Cooperative Housing Society Ltd.Gyandev Builders & DevelopersPlot No. 7, Cts No. 9000, S. No. 33 6 Pt30-11-2020 00:00:00
Nisarg Greens - Commercial Phase-INnd Ambernath LlpRh-131-12-2019 00:00:00
Sai HeritageShashank EnterprisesGut No 54 Plot No 931-12-2025 00:00:00
Radhe Govind PlazaShree Radha ConstructionGut No- 59 (P), Cts No- 900431-12-2026 00:00:00
Anand Upvan NxAmeya DevelopersGat No - 5 , Cts No - 9297 Part31-12-2029 00:00:00
Project Details
  • Project:
    Nisarg Greens- Phase Ii A
  • Location:
  • Rh 1
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Nnd Ambernath Llp
  • Phone:
  • Address:
  • Devavrata Building
Project RERA Details
MAHA REARA No: P51700008839
Project Type Others
RERA Project Status Ongoing
Architect Homework
Funding Bank RBL Bank Limited
Proposed Possession 30 Dec 2021
Revised Possession 30 Dec 2021
Extended Possession
Litigations No Litigations
Last Modified 23 Dec 2020
Last Retrived 26 Jul 2025
Nisarg Greens- Phase Ii A QR Code
Nisarg Greens- Phase Ii A
MahaRERA - P51700008839
Apartment Details & Configuration
TypeArea
1 BHK34.27 Sq.mts. ( 369 Sq.ft. )
2 BHK COMPACT39.4 Sq.mts. ( 424 Sq.ft. )
2 BHK COMPACT40.16 Sq.mts. ( 432 Sq.ft. )
2 BHK59.6 Sq.mts. ( 642 Sq.ft. )
3 BHK97.23 Sq.mts. ( 1047 Sq.ft. )
2 BHK44.88 Sq.mts. ( 483 Sq.ft. )
2 BHK45.43 Sq.mts. ( 489 Sq.ft. )
Shop20.93 Sq.mts. ( 225 Sq.ft. )
Shop21.06 Sq.mts. ( 227 Sq.ft. )
Shop22.95 Sq.mts. ( 247 Sq.ft. )
Shop26.38 Sq.mts. ( 284 Sq.ft. )
Shop29.08 Sq.mts. ( 313 Sq.ft. )
Shop30.27 Sq.mts. ( 326 Sq.ft. )
Shop20.79 Sq.mts. ( 224 Sq.ft. )
Shop21.46 Sq.mts. ( 231 Sq.ft. )
Shop23.42 Sq.mts. ( 252 Sq.ft. )
Shop27.39 Sq.mts. ( 295 Sq.ft. )
Shop28.78 Sq.mts. ( 310 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nisarg Greens- Phase Ii Alast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Work Not Yet Started
Energy management
Work Not Yet Started
Fire Protection And Fire Safety Requirements
Work Not Yet Started
Landscaping & Tree Planting
Work Not Yet Started
Open Parking
Work Not Yet Started
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
Stp Completed
Solid Waste Management And Disposal
Na
Storm Water Drains
Work Not Yet Started
Street Lighting
Work Not Yet Started
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting10% completed
10% Complete
Work Not Yet Started
Water Supply
Water Connection From Midc
Buildings / Wings in Nisarg Greens- Phase Ii A
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nisarg Greens- Phase Ii A by Nnd Ambernath Llplast updated on 26 Jul 2025 as per information obtained from MARA RERA.

189326 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 6

Wings / Towers in Project

Apartments Statistics

540 apartments in total
Total
540
Booked
525
Available
15

Saleable Area Statistics (Sq. ft.)

260665 Total
Total
260665
Booked
254088
Available
6577
Total 540 apartments in project. 525 apartments booked. 97% apartments booked.
Total 260665 Sq.ft. saleable area. 254088 saleable area booked.
97% area booked.

Daffodil A Bldg No 15

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Daffodil A Bldg No 15Dec 20201910101328
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.27 Sq.mts. ( 369 Sq.ft. )36
35 Booked97% Booked
97% Booked
2 BHK COMPACT39.4 Sq.mts. ( 424 Sq.ft. )18
18 Booked100% Booked
100% Booked
2 BHK COMPACT40.16 Sq.mts. ( 432 Sq.ft. )48
47 Booked97% Booked
97% Booked
102 total apartments / 100 apartments booked. 98% apartments booked.
Work Description in Building Daffodil A Bldg No 15Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress63% done
63% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Daffodil B Bldg No 16

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Daffodil B Bldg No 16Dec 20201910101328
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.27 Sq.mts. ( 369 Sq.ft. )36
36 Booked100% Booked
100% Booked
2 BHK COMPACT39.4 Sq.mts. ( 424 Sq.ft. )18
18 Booked100% Booked
100% Booked
2 BHK COMPACT40.16 Sq.mts. ( 432 Sq.ft. )48
45 Booked93% Booked
93% Booked
102 total apartments / 99 apartments booked. 97% apartments booked.
Work Description in Building Daffodil B Bldg No 16Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress63% done
63% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Lotus A Bldg No 7

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Lotus A Bldg No 7Dec 2020191010724
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59.6 Sq.mts. ( 642 Sq.ft. )36
36 Booked100% Booked
100% Booked
3 BHK97.23 Sq.mts. ( 1047 Sq.ft. )18
18 Booked100% Booked
100% Booked
54 total apartments / 54 apartments booked. 100% apartments booked.
Work Description in Building Lotus A Bldg No 7Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress63% done
63% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Lotus B Bldg No 8

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Lotus B Bldg No 8Dec 2020191010724
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59.6 Sq.mts. ( 642 Sq.ft. )36
36 Booked100% Booked
100% Booked
3 BHK97.23 Sq.mts. ( 1047 Sq.ft. )18
17 Booked94% Booked
94% Booked
54 total apartments / 53 apartments booked. 98% apartments booked.
Work Description in Building Lotus B Bldg No 8Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress63% done
63% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Sunflower E Bldg No 13

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sunflower E Bldg No 13Dec 20201910101620
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.27 Sq.mts. ( 369 Sq.ft. )36
34 Booked94% Booked
94% Booked
2 BHK44.88 Sq.mts. ( 483 Sq.ft. )18
18 Booked100% Booked
100% Booked
2 BHK45.43 Sq.mts. ( 489 Sq.ft. )48
48 Booked100% Booked
100% Booked
Shop20.93 Sq.mts. ( 225 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop21.06 Sq.mts. ( 227 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop22.95 Sq.mts. ( 247 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop26.38 Sq.mts. ( 284 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop29.08 Sq.mts. ( 313 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop30.27 Sq.mts. ( 326 Sq.ft. )2
2 Booked100% Booked
100% Booked
114 total apartments / 110 apartments booked. 96% apartments booked.
Work Description in Building Sunflower E Bldg No 13Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress63% done
63% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Sunflower F Bldg No 14

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sunflower F Bldg No 14Dec 20201910101516
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.27 Sq.mts. ( 369 Sq.ft. )36
35 Booked97% Booked
97% Booked
2 BHK COMPACT39.4 Sq.mts. ( 424 Sq.ft. )18
18 Booked100% Booked
100% Booked
2 BHK COMPACT40.16 Sq.mts. ( 432 Sq.ft. )48
44 Booked91% Booked
91% Booked
Shop20.79 Sq.mts. ( 224 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop21.46 Sq.mts. ( 231 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop22.95 Sq.mts. ( 247 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop23.42 Sq.mts. ( 252 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop27.39 Sq.mts. ( 295 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop28.78 Sq.mts. ( 310 Sq.ft. )2
2 Booked100% Booked
100% Booked
114 total apartments / 109 apartments booked. 95% apartments booked.
Work Description in Building Sunflower F Bldg No 14Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress63% done
63% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Nnd Ambernath Llp
for Project
Nisarg Greens- Phase Ii A
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation