Project overview

Nine Star Prestige Building No. 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000030824. Nine Star Prestige Building No. 2 is located at Gut No 199Pt. This is a New being developed by Nine Home Creators.

Nine Star Prestige Building No. 2 has 1 BHK, 1RK & 2 BHK Apartments with carpet areas ranging from 251 to 503 Sq.ft. Carpet. The Project has total 70 of which 50 are currently available for sale.

Nine Star Prestige Building No. 2 is being developed on a total land area of 65883 Sq.ft. out of which 5818 Sq.ft. i.e 9% is reserved for recreational purposes. Nine Star Prestige Building No. 2 has 1 Wings / Towers Building No 2

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Nine Star Prestige Building No. 2
  • Location:
  • Gut No 199Pt
  • Const. Stage:
    New
  • Possession:
    31 Dec 2026
Developer Details

  • Developer:
    Nine Home Creators
  • Phone:
  • Address:
  • Nine Star Prestige
Project RERA Details
MAHA REARA No: P99000030824
Project Type Others
RERA Project Status New
Architect Roshan R Patil
Funding Bank VASAI VIKAS SAHAKARI BANK LIMITED
Proposed Possession 31 Dec 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 18 Jul 2025
Last Retrived 28 Jul 2025
Nine Star Prestige Building No. 2 QR Code
Nine Star Prestige Building No. 2
MahaRERA - P99000030824
Apartment Details & Configuration
TypeArea
1 BHK36.2 Sq.mts. ( 390 Sq.ft. )
1 BHK36.43 Sq.mts. ( 392 Sq.ft. )
1RK23.3 Sq.mts. ( 251 Sq.ft. )
2 BHK46.2 Sq.mts. ( 497 Sq.ft. )
2 BHK46.75 Sq.mts. ( 503 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nine Star Prestige Building No. 2last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
.Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
.Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
.Na
Open Parking
.Na
Sewerage (Chamber, Lines, Septic Tank , STP)
.Na
Solid Waste Management And Disposal
Na
Storm Water Drains
.Na
Street Lighting
.Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
.Na
Water Supply
.Na
Buildings / Wings in Nine Star Prestige Building No. 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nine Star Prestige Building No. 2 by Nine Home Creatorslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

65883 Sq. ft.

Project Area

5818 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

70 apartments in total
Total
70
Booked
20
Available
50

Saleable Area Statistics (Sq. ft.)

26898 Total
Total
26898
Booked
6581
Available
20317
Total 70 apartments in project. 20 apartments booked. 28% apartments booked.
Total 26898 Sq.ft. saleable area. 6581 saleable area booked.
24% area booked.

Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2Dec 2026810110111
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.2 Sq.mts. ( 390 Sq.ft. )35
1 BHK36.43 Sq.mts. ( 392 Sq.ft. )7
None Booked0% Booked
0% Booked
1RK23.3 Sq.mts. ( 251 Sq.ft. )14
12 Booked85% Booked
85% Booked
2 BHK46.2 Sq.mts. ( 497 Sq.ft. )7
None Booked0% Booked
0% Booked
2 BHK46.75 Sq.mts. ( 503 Sq.ft. )7
4 Booked57% Booked
57% Booked
70 total apartments / 20 apartments booked. 28% apartments booked.
Work Description in Building Building No 2Completion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress60% done
60% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress25% done
25% Booked
Channel Partners
Channel Partners Registered by Developer
Nine Home Creators
for Project
Nine Star Prestige Building No. 2
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation