Project overview

Nine Star Landmark Phase Iii Bldg-5 Tulip is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000004650. Nine Star Landmark Phase Iii Bldg-5 Tulip is located at 198/1A. This is a New being developed by Nine Homemakers.

Nine Star Landmark Phase Iii Bldg-5 Tulip has RESIDENTIAL Apartments with carpet areas ranging from 7298 to 7298 Sq.ft. Carpet. The Project has total 114 of which 114 are currently available for sale.

Nine Star Landmark Phase Iii Bldg-5 Tulip is being developed on a total land area of 37093 Sq.ft. Nine Star Landmark Phase Iii Bldg-5 Tulip has 4 Wings / Towers Tulip Wing-A,Tulip Wing-B,Tulip Wing-C,Tulip Wing-D

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Nine Star Landmark Phase Iii Bldg-5 Tulip
  • Location:
  • 198/1A
  • Const. Stage:
    New
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Nine Homemakers
  • Phone:
  • Address:
  • .
Project RERA Details
MAHA REARA No: P99000004650
Project Type Residential / Group Housing
RERA Project Status New
Architect Ar Roshan Ravindra Patil
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2021
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 09 Aug 2017
Last Retrived 28 Jul 2025
Nine Star Landmark Phase Iii Bldg-5 Tulip QR Code
Nine Star Landmark Phase Iii Bldg-5 Tulip
MahaRERA - P99000004650
Apartment Details & Configuration
TypeArea
RESIDENTIAL678 Sq.mts. ( 7298 Sq.ft. )
RESIDENTIAL753 Sq.mts. ( 8105 Sq.ft. )
RESIDENTIAL619 Sq.mts. ( 6663 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nine Star Landmark Phase Iii Bldg-5 Tuliplast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Electric Work As Per Msedcl
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
.
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
.
Street Lighting
.
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Rain Water Harvesting
Water Supply
Borewell / Grampanchayat
Buildings / Wings in Nine Star Landmark Phase Iii Bldg-5 Tulip
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nine Star Landmark Phase Iii Bldg-5 Tulip by Nine Homemakerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

37093 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

114 apartments in total
Total
114
Booked
0
Available
114

Saleable Area Statistics (Sq. ft.)

838408 Total
Total
838408
Booked
0
Available
838408
Total 114 apartments in project. 0 apartments booked. 0% apartments booked.
Total 838408 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Tulip Wing-A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tulip Wing-AJan 19005100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL678 Sq.mts. ( 7298 Sq.ft. )28
None Booked0% Booked
0% Booked
28 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Tulip Wing-ACompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Tulip Wing-B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tulip Wing-BJan 19005100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL753 Sq.mts. ( 8105 Sq.ft. )30
None Booked0% Booked
0% Booked
30 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Tulip Wing-BCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Tulip Wing-C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tulip Wing-CJan 19005100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL619 Sq.mts. ( 6663 Sq.ft. )28
None Booked0% Booked
0% Booked
28 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Tulip Wing-CCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Tulip Wing-D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tulip Wing-DJan 19005100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL678 Sq.mts. ( 7298 Sq.ft. )28
None Booked0% Booked
0% Booked
28 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Tulip Wing-DCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Nine Homemakers
for Project
Nine Star Landmark Phase Iii Bldg-5 Tulip
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation