Project overview

Nicon Infinity Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000003227. Nicon Infinity Phase 1 is located at Survey No.277 Hissa No. 2 And 3. This is a Ongoing being developed by Nicon Infra Llp.

Nicon Infinity Phase 1 has 1 BHK & 2 BHK Apartments with carpet areas ranging from 367 to 585 Sq.ft. Carpet. The Project has total 166 of which 104 are currently available for sale.

Nicon Infinity Phase 1 is being developed on a total land area of 7189 Sq.ft. out of which 14628 Sq.ft. i.e 203% is reserved for recreational purposes. Nicon Infinity Phase 1 has 2 Wings / Towers Nicon Infinity - Phase I - Tower C,Nicon Infinity - Phase I - Tower D

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Nicon Infinity Phase 1
  • Location:
  • Survey No.277 Hissa No. 2 And 3
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2019
Developer Details

  • Developer:
    Nicon Infra Llp
  • Phone:
  • Address:
  • Nootan Nagar
Project RERA Details
MAHA REARA No: P99000003227
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sanat Mehta
Funding Bank BANK OF BARODA
Proposed Possession 30 Jun 2019
Revised Possession 30 Jun 2019
Extended Possession 29 Dec 2020
Litigations No Litigations
Last Modified 13 Jun 2020
Last Retrived 28 Jul 2025
Nicon Infinity Phase 1 QR Code
Nicon Infinity Phase 1
MahaRERA - P99000003227
Apartment Details & Configuration
TypeArea
1 BHK33.15 Sq.mts. ( 357 Sq.ft. )
1 BHK35.12 Sq.mts. ( 378 Sq.ft. )
1 BHK35.18 Sq.mts. ( 379 Sq.ft. )
2 BHK46.63 Sq.mts. ( 502 Sq.ft. )
1 BHK34.09 Sq.mts. ( 367 Sq.ft. )
2 BHK54.34 Sq.mts. ( 585 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nicon Infinity Phase 1last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Terrace Garden &Amp; Open To Sky Gym
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains100% completed
95% Complete
Completed Of Building Area
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Facility Starts Once Vvcmc Water Supply Commences
Buildings / Wings in Nicon Infinity Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nicon Infinity Phase 1 by Nicon Infra Llplast updated on 28 Jul 2025 as per information obtained from MARA RERA.

7189 Sq. ft.

Project Area

14628 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

166 apartments in total
Total
166
Booked
62
Available
104

Saleable Area Statistics (Sq. ft.)

69713 Total
Total
69713
Booked
26597
Available
43117
Total 166 apartments in project. 62 apartments booked. 37% apartments booked.
Total 69713 Sq.ft. saleable area. 26597 saleable area booked.
38% area booked.

Nicon Infinity - Phase I - Tower C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Nicon Infinity - Phase I - Tower CJun 2019151010034
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.15 Sq.mts. ( 357 Sq.ft. )14
10 Booked71% Booked
71% Booked
1 BHK35.12 Sq.mts. ( 378 Sq.ft. )28
1 BHK35.18 Sq.mts. ( 379 Sq.ft. )28
9 Booked32% Booked
32% Booked
2 BHK46.63 Sq.mts. ( 502 Sq.ft. )14
11 Booked78% Booked
78% Booked
84 total apartments / 35 apartments booked. 41% apartments booked.
Work Description in Building Nicon Infinity - Phase I - Tower CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Nicon Infinity - Phase I - Tower D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Nicon Infinity - Phase I - Tower DJun 2019151010034
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.09 Sq.mts. ( 367 Sq.ft. )26
6 Booked23% Booked
23% Booked
1 BHK35.12 Sq.mts. ( 378 Sq.ft. )28
11 Booked39% Booked
39% Booked
2 BHK54.34 Sq.mts. ( 585 Sq.ft. )28
10 Booked35% Booked
35% Booked
82 total apartments / 27 apartments booked. 32% apartments booked.
Work Description in Building Nicon Infinity - Phase I - Tower DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Nicon Infra Llp
for Project
Nicon Infinity Phase 1
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation