Project overview

New Kirtikar Proposed is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700004963. New Kirtikar Proposed is located at 400602. This is a On-Going Project being developed by Chaturthi Developers.

New Kirtikar Proposed has resedential and offi Apartments with carpet areas ranging from 9015 to 9015 Sq.ft. Carpet. The Project has total 33 of which 9 are currently available for sale.

New Kirtikar Proposed is being developed on a total land area of 10064 Sq.ft. out of which 6598 Sq.ft. i.e 66% is reserved for recreational purposes. New Kirtikar Proposed has 2 Wings / Towers New Kirtikar Building A,New Kirtikar Proposed Building B

ProjectDeveloperLocationPossession
Royal Height - Building BNew Royal Construction Company.1025 Part And 112030-12-2021 00:00:00
GiriviharAbhinandan Enterprise77-A/4 And 631-05-2019 00:00:00
Auralis The TwinsDeep Homes & Constructions LlpF.P. No- 136 B01-03-2019 00:00:00
New Kirtikar ProposedChaturthi Developers40060201-07-2025 00:00:00
Shanti KunjShreyas Enterprises616,617,61831-12-2017 00:00:00
AtlantisAshwamedh Builders & DevelopersT P Scheme No 1, F P No 32030-06-2021 00:00:00
Empire TowersLakhani Realty Llp208/4 214/631-07-2024 00:00:00
Manorama ChsRupa Properties & Securities Pvt. Ltd.Cts No 926 To 933 And 94231-12-2019 00:00:00
Vaikunth Cluster 4APiramal Estate Private Limited100/24-30,100/31A,31B31-07-2024 00:00:00
AudumberAadyashakti EnterprisesSn 6631-12-2018 00:00:00
ShivkrupaAnant Arjun Madhavi3931-03-2018 00:00:00
Snehadeep Co-Operative Housing Society LtdJoshi EnterprisesSurvey No.8, Tikka No.2 Part Corresponding Totikka No.16, Cts No. 6031-12-2017 00:00:00
Redevelopment Of Manas ChsArvij Builders And Developers Private LimitedCts No 118/B Of Naupada, M G Road, Thane07-05-2022 00:00:00
Dreamland Co-Op. Hsg. Soc. Ltd.Vaastusukh DevelopersTika No.2130-12-2021 00:00:00
Viraj HeightsV-Raj BuildconTika No 20 Part, City Survey No 1025 A Part30-12-2026 00:00:00
Sandhya BuildingS D Bhalerao Constructions Pvt Ltd - Sandhya3 Cts No 27 Tikka No 2131-03-2019 00:00:00
Sahakar NiwasJnm EnterprisesCts 147/2, Tika 12, Fp 262 Part31-08-2018 00:00:00
Ghantali Sainath PlazaKalpataru EnterprisesTika No.15 Cts No 13A Pt10-08-2022 00:00:00
Nandishwar PlazaNandishwar Cons CoS No 13 Hissa No 410-08-2023 00:00:00
Gautam Co-Operative Housing SocietyMahesh Shriram BorkarCts No.867/B Final Plot No.34831-07-2018 00:00:00
Indira Niwas AnnexShree Swami Krupa Builders And DevelopersCts 785 To 795 230 233 839 Tika No 10 11 Naupada Thane31-12-2018 00:00:00
Rameshwar Co-Op Housing Society Ltd.Aditya AssociatesFinal Plot No 327 Of T.P.S. No. 110-03-2027 00:00:00
Blue BerryAshwamedh CorporationFinal Plot No 318 & 319 Of T.P. Sheme 130-06-2026 00:00:00
Matru MandirParnad Anil GupteTika No21 Cts No4f31-12-2026 00:00:00
Rahul Co.Op. Housing Society LtdSna Build-Tech7 339/1 34815-02-2025 00:00:00
Shree Krishna ChsVaibhav Developers4031-12-2025 00:00:00
Satyabhama Chs LtdMahesh Shriram BorkarCts No 8830-06-2024 00:00:00
CrossvillaShreeya EnterprisesCts 25,16130-06-2021 00:00:00
Shree SadanShrinivas Dattatray Kale761 Tika No 1131-01-2020 00:00:00
Rajesh Co-Operative Housing SocietyJoshi EnterprisesThane, 40060208-08-2019 00:00:00
Dhanashree Co-Operative Housing SocietyL. K. Realtors400602, Thane31-12-2019 00:00:00
Laabh NeelkanthLaabh BuildtechCts No 2931-12-2019 00:00:00
Godrej Alive AModella Textile Industries Limited40060231-12-2020 00:00:00
PadmalaxmiKedar Bhikaji Bapat945 946 947 And 94831-03-2018 00:00:00
Ashwa PlatinumAshwamedh Builders And Developers75531-12-2019 00:00:00
Redevelopment Of Parijat Building Of Sanksriti Nagar Coop Hsg Soc LtdOjass ConstructionsTps 1, Final Plot No 226, Sub Plot No 1719-12-2021 00:00:00
Highland Sky Towers A BuildingProvidence Realty LlpCts No 15,47,4831-12-2026 00:00:00
Highland Sky Tower Damani B BuildingProvidence Realty LlpCts No 15,47,4830-04-2025 00:00:00
TarabaugVidyadhar Achyut VaishampayanCts 114. 7A, 1A Of Tika No. 2120-12-2024 00:00:00
Madan VilasIshaan Enterprise24/1 27/2 31/131-03-2018 00:00:00
Thana Co-Op Housing Society SopanAditya AssociatesCts Nos 108 / 8, 110A / 4, 108/9 Part Veer Savarkar Path Old Bombay Agra Road Thane West31-12-2019 00:00:00
Valencia ParkPrakash Trading Company140B31-12-2019 00:00:00
Suyog Society ChsDream Realtors168/331-12-2019 00:00:00
Tropical EliteSchema Enterprises Private Limited88A,88B,9131-05-2018 00:00:00
White RoseM/S Eeshan EnterprisesCts No 134 Part30-03-2024 00:00:00
Sai DarshanShree Sai EnterprisesGut No 11230-12-2022 00:00:00
Devdatta Co-Op. Hsg. Soc. Ltd.Shree Swami Krupa Builders And Developers400602, Thane, Naupada30-12-2023 00:00:00
Ashwa AnnexAshwamedh Construction31731-05-2018 00:00:00
Anmol SapphireM/S Ekdant Housing53/B/701-08-2019 00:00:00
Oasis RoyaleMagestic Premises Private LimitedF P No 338 T P S No. 131-12-2018 00:00:00
Redevelopment Of The Bombay Thana ChsGaurang Properties Pvt. Ltd.Shivaji Nagar, 40060231-12-2019 00:00:00
MaithiliSharda Vastu Nirmitee Pvt. Ltd.25/Fp 145/341 -10/345 - 2 -3/350-5 P31-03-2019 00:00:00
RhythmAradhana Lifespace LlpCts 247/230-06-2026 00:00:00
Annapurna NiwasShree Swami Krupa DevelopersThane, Bhaskar Colony30-06-2025 00:00:00
Geeta PlazaRoyal DevelopersCts No243,244,24830-06-2026 00:00:00
Orchid Square Phase 2M/S Squarefeet Eco Housing Llp128/631-12-2018 00:00:00
SindhusmrutiYogiraj Powertech Pvt LtdTikka No 22 Cts No 5/130-11-2018 00:00:00
New Thana ChsGaurang Properties Pvt. Ltd.Eastern Express Highway, 40060223-09-2018 00:00:00
Vaikunth Cluster 4Piramal Estate Private LimitedNo 7/1 To 14, 8/1To37, 39To42, 9/1To17, 10/2To9, 10/10A,10/10B,10/11To18, 99/13B, 15B30-12-2023 00:00:00
StarlivingTheme Developers Private LimitedT No 21 Cts No 7 Pt And 8 Pt T No 19 Cts No 30 And 3130-12-2025 00:00:00
Sapphire HeightsSpace Corporation25225-12-2024 00:00:00
Vaikunth Cluster 1Piramal Estate Private LimitedNo 7/1 To 14 8/1To37 39To42 9/1To17 10/2To9 10/10A 10/10B 10/11To18 99/13B 15B 100/14A30-12-2022 00:00:00
Mai Kripa Co. Op. Hsg. Soc.Ojass ConstructionsFinal Plot No. 164/A31-03-2024 00:00:00
Shahs AvenueShah EnterprisesNaupada31-12-2025 00:00:00
Ramchandra Co-Operative Housing Society LimitedShree Ganeshay Developers45831-12-2025 00:00:00
MaansarovarMeridian Buildpro Private LimitedFp No 394/A 394/C Tps No 130-12-2022 00:00:00
Gaurang RoyaleGaurang Properties Pvt. Ltd.Gokhale Road31-12-2019 00:00:00
Laxmi KeshavAditya AssociatesTika No.22, Cts No. 63/2/A At Gokhale Road, Naupada Thane West31-12-2019 00:00:00
PrabhatSamay Homes423 To 42731-01-2021 00:00:00
Abhijeet Co-Op Hsg SocietyContinental Maniratna Builders &Amp; Developers400602, Thane30-11-2020 00:00:00
TrividhCosmos Skyline Green View Llp60/A28-02-2029 00:00:00
Debonair ClassicAnant Square DevelopersT.P.S.No. 1, Final Plot No. 365/B30-04-2029 00:00:00
AshirwadGautam Shanti EnterprisesTika No.23, Cts91/231-07-2027 00:00:00
Arvind Co-Op Housing Society LtdAditya AssociatesCts 75/A/2 Tika No. 15, Sector No. 2, Mouje Naupada08-06-2027 00:00:00
The Vivek Flat Owners Chs LtdYash AshokaFinalplot No-226, Sub Plot.1825-12-2022 00:00:00
Madhuban Co-Operative Housing Society Ltd.Mahesh Shriram BorkarFinal Plot No.297, Survey No.34430-12-2020 00:00:00
Naiks Central PlazaClean Construction Co.Opp Gaondevi Ground31-12-2018 00:00:00
GopaldhamShree Hari DevelopersPlot No 26 Sector 5, Ulwe31-12-2018 00:00:00
Seasons EliteSai Mahavir DevelopersSurvey No. 3 Hissa No. 7A And Survey No. 55 Hissa No. 831-08-2019 00:00:00
Amar PushpakunjAvighna Redevelopers2014-A/1B, Sector No.1 Of Mouje Kopari31-07-2026 00:00:00
Navkamal Pushpa ChsDream RealtorsCts No.-109 ,Tika No.-22, Sector-231-05-2026 00:00:00
Yashwant NiwasVijayraj Developers Llp71/A Tika No. 1631-03-2027 00:00:00
Project Details
  • Project:
    New Kirtikar Proposed
  • Location:
  • 400602
  • Const. Stage:
    On-Going Project
  • Possession:
    01 Jul 2025
Developer Details

  • Developer:
    Chaturthi Developers
  • Phone:
  • Address:
  • A/201, Chaturthi Arcade, Sant Namdev Path, Near Dns Bank, Gogras Wadi, 421201
Project RERA Details
MAHA REARA No: P51700004963
Project Type Residential
RERA Project Status On-Going Project
Funding Bank Kalyan Janta sahakari bank
Proposed Possession 01 Jul 2025
Revised Possession 01 Jul 2026
Extended Possession
Litigations No Litigations
Last Modified 26 Feb 2024
Last Retrived 28 Jul 2025
New Kirtikar Proposed QR Code
New Kirtikar Proposed
MahaRERA - P51700004963
Apartment Details & Configuration
TypeArea
resedential588.85 Sq.mts. ( 6338 Sq.ft. )
resedential and offi837.47 Sq.mts. ( 9015 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of New Kirtikar Proposedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
As Per Electrical Department
Energy management50% completed
50% Complete
As Per Tmc Norms
Fire Protection And Fire Safety Requirements50% completed
50% Complete
As Per Fire Fighting Norms
Landscaping & Tree Planting
Na
lift50% completed
50% Complete
As Per Pwd
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
As Per Tmc Norms
Solar water50% completed
50% Complete
14 Solar Pannels For Building B
Solid Waste Management And Disposal50% completed
50% Complete
As Per Tmc Norms
Storm Water Drains
Na
Street Lighting
As Per Tmc Norms
Treatment And Disposal Of Sewage And Sullage Water50% completed
50% Complete
As Per Tmc Norms
Water Conservation, Rain water Harvesting50% completed
50% Complete
As Per Tmc Norms
Water Supply
As Per Tmc Norms
Buildings / Wings in New Kirtikar Proposed
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of New Kirtikar Proposed by Chaturthi Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

10064 Sq. ft.

Project Area

6598 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

33 apartments in total
Total
33
Booked
24
Available
9

Saleable Area Statistics (Sq. ft.)

270718 Total
Total
270718
Booked
202968
Available
67750
Total 33 apartments in project. 24 apartments booked. 72% apartments booked.
Total 270718 Sq.ft. saleable area. 202968 saleable area booked.
75% area booked.

New Kirtikar Building A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
New Kirtikar Building AJan 190061010012
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
resedential588.85 Sq.mts. ( 6338 Sq.ft. )10
5 Booked50% Booked
50% Booked
10 total apartments / 5 apartments booked. 50% apartments booked.
Work Description in Building New Kirtikar Building ACompletion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

New Kirtikar Proposed Building B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
New Kirtikar Proposed Building BJan 19008101008
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
resedential and offi837.47 Sq.mts. ( 9015 Sq.ft. )23
19 Booked82% Booked
82% Booked
23 total apartments / 19 apartments booked. 82% apartments booked.
Work Description in Building New Kirtikar Proposed Building BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress99% done
99% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Chaturthi Developers
for Project
New Kirtikar Proposed
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation