Project overview

Namdev Vihar is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700015782. Namdev Vihar is located at S.No. 121 H.No. 7A2 7A3. This is a Ongoing being developed by Namdev Construction.

Namdev Vihar has 1 BHK & 2 BHK Apartments with carpet areas ranging from 451 to 654 Sq.ft. Carpet. The Project has total 32 of which 11 are currently available for sale.

Namdev Vihar is being developed on a total land area of 7685 Sq.ft. out of which 5199 Sq.ft. i.e 68% is reserved for recreational purposes. Namdev Vihar has 2 Wings / Towers A Wing,C Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Namdev Vihar
  • Location:
  • S.No. 121 H.No. 7A2 7A3
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Namdev Construction
  • Phone:
  • Address:
  • E Wing White Field
Project RERA Details
MAHA REARA No: P51700015782
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Santosh R Madan
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2021
Revised Possession 30 Dec 2021
Extended Possession 31 Dec 2023
Litigations No Litigations
Last Modified 08 Feb 2023
Last Retrived 26 Jul 2025
Namdev Vihar QR Code
Namdev Vihar
MahaRERA - P51700015782
Apartment Details & Configuration
TypeArea
Shop14.32 Sq.mts. ( 154 Sq.ft. )
Shop25.21 Sq.mts. ( 271 Sq.ft. )
Shop25.87 Sq.mts. ( 278 Sq.ft. )
Shop28.75 Sq.mts. ( 309 Sq.ft. )
1 BHK41.92 Sq.mts. ( 451 Sq.ft. )
2 BHK52.94 Sq.mts. ( 570 Sq.ft. )
2 BHK60.64 Sq.mts. ( 653 Sq.ft. )
2 BHK60.72 Sq.mts. ( 654 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Namdev Viharlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completetd
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management100% completed
95% Complete
Completetd
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking100% completed
95% Complete
Completetd
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completetd
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completetd
Buildings / Wings in Namdev Vihar
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Namdev Vihar by Namdev Constructionlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

7685 Sq. ft.

Project Area

5199 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

32 apartments in total
Total
32
Booked
21
Available
11

Saleable Area Statistics (Sq. ft.)

17305 Total
Total
17305
Booked
12004
Available
5301
Total 32 apartments in project. 21 apartments booked. 65% apartments booked.
Total 17305 Sq.ft. saleable area. 12004 saleable area booked.
69% area booked.

A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A WingMar 20184100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Shop14.32 Sq.mts. ( 154 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop25.21 Sq.mts. ( 271 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop25.87 Sq.mts. ( 278 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop28.75 Sq.mts. ( 309 Sq.ft. )1
None Booked0% Booked
0% Booked
4 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingMar 20228103033
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK41.92 Sq.mts. ( 451 Sq.ft. )7
6 Booked85% Booked
85% Booked
2 BHK52.94 Sq.mts. ( 570 Sq.ft. )7
6 Booked85% Booked
85% Booked
2 BHK60.64 Sq.mts. ( 653 Sq.ft. )7
5 Booked71% Booked
71% Booked
2 BHK60.72 Sq.mts. ( 654 Sq.ft. )7
4 Booked57% Booked
57% Booked
28 total apartments / 21 apartments booked. 75% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Namdev Construction
for Project
Namdev Vihar
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation