Project overview

Nakshatra is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700005959. Nakshatra is located at Thane, 421503. This is a On-Going Project being developed by Harshal Navghare.

Nakshatra has 1, 1bhk, 1rk, 2bhk & shop Apartments with carpet areas ranging from 130 to 562 Sq.ft. Carpet. The Project has total 64 of which 46 are currently available for sale.

Nakshatra is being developed on a total land area of 23681 Sq.ft. out of which 7535 Sq.ft. i.e 32% is reserved for recreational purposes. Nakshatra has 3 Wings / Towers Krittika,Rohini,Vishakha

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Nakshatra
  • Location:
  • Thane, 421503
  • Const. Stage:
    On-Going Project
  • Possession:
    31 May 2019
Developer Details

  • Developer:
    Harshal Navghare
  • Phone:
  • Address:
  • A107, Shivangi Apartment, Pune Link Road, Santoshi Mata Mandir, Vijay Nagar, 421306
Project RERA Details
MAHA REARA No: P51700005959
Project Type Residential
RERA Project Status On-Going Project
Funding Bank syndicate bank
Proposed Possession 31 May 2019
Revised Possession 31 May 2019
Extended Possession
Litigations No Litigations
Last Modified 31 Jul 2017
Last Retrived 28 Jul 2025
Nakshatra QR Code
Nakshatra
MahaRERA - P51700005959
Apartment Details & Configuration
TypeArea
2bhk76.28 Sq.mts. ( 821 Sq.ft. )
2bhk90.3 Sq.mts. ( 972 Sq.ft. )
3bhk110.65 Sq.mts. ( 1191 Sq.ft. )
1bhk53.24 Sq.mts. ( 573 Sq.ft. )
1bhk53.89 Sq.mts. ( 580 Sq.ft. )
2bhk63.18 Sq.mts. ( 680 Sq.ft. )
144.34 Sq.mts. ( 477 Sq.ft. )
1bhk44.36 Sq.mts. ( 477 Sq.ft. )
1bhk45.57 Sq.mts. ( 491 Sq.ft. )
1bhk45.8 Sq.mts. ( 493 Sq.ft. )
1bhk48.45 Sq.mts. ( 522 Sq.ft. )
1bhk35.79 Sq.mts. ( 385 Sq.ft. )
1bhk38.42 Sq.mts. ( 414 Sq.ft. )
1bhk40.02 Sq.mts. ( 431 Sq.ft. )
1bhk42.11 Sq.mts. ( 453 Sq.ft. )
1bhk43.12 Sq.mts. ( 464 Sq.ft. )
1rk31.45 Sq.mts. ( 339 Sq.ft. )
2bhk48.87 Sq.mts. ( 526 Sq.ft. )
2bhk52.24 Sq.mts. ( 562 Sq.ft. )
shop33.64 Sq.mts. ( 362 Sq.ft. )
shop12.08 Sq.mts. ( 130 Sq.ft. )
shop12.17 Sq.mts. ( 131 Sq.ft. )
shop12.36 Sq.mts. ( 133 Sq.ft. )
shop12.87 Sq.mts. ( 139 Sq.ft. )
shop12.92 Sq.mts. ( 139 Sq.ft. )
shop13.89 Sq.mts. ( 150 Sq.ft. )
shop14.13 Sq.mts. ( 152 Sq.ft. )
shop14.96 Sq.mts. ( 161 Sq.ft. )
shop15.78 Sq.mts. ( 170 Sq.ft. )
shop15.84 Sq.mts. ( 171 Sq.ft. )
shop17.28 Sq.mts. ( 186 Sq.ft. )
shop23.32 Sq.mts. ( 251 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nakshatralast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
0
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
0
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting10% completed
10% Complete
Few Trees Planted
Open Parking
0
Sewerage (Chamber, Lines, Septic Tank , STP)30% completed
30% Complete
Tank Built Drainage System Remaining
Solid Waste Management And Disposal
0
Storm Water Drains
0
Street Lighting5% completed
5% Complete
Flood Lights Installed
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
0
Water Supply10% completed
10% Complete
Two Borewells With Submersible Pump
Buildings / Wings in Nakshatra
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nakshatra by Harshal Navgharelast updated on 28 Jul 2025 as per information obtained from MARA RERA.

23681 Sq. ft.

Project Area

7535 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

64 apartments in total
Total
64
Booked
18
Available
46

Saleable Area Statistics (Sq. ft.)

33022 Total
Total
33022
Booked
9093
Available
23928
Total 64 apartments in project. 18 apartments booked. 28% apartments booked.
Total 33022 Sq.ft. saleable area. 9093 saleable area booked.
28% area booked.

Krittika

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
KrittikaJan 19004400400040
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2bhk76.28 Sq.mts. ( 821 Sq.ft. )3
3 Booked100% Booked
100% Booked
2bhk90.3 Sq.mts. ( 972 Sq.ft. )6
3bhk110.65 Sq.mts. ( 1191 Sq.ft. )3
None Booked0% Booked
0% Booked
12 total apartments / 4 apartments booked. 33% apartments booked.
Work Description in Building KrittikaCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress23% done
23% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
work-in-progress50% done
50% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress80% done
80% Booked
X number of Podiums
X number of Slabs of Super Structure

Rohini

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
RohiniJan 19004360360036
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1bhk53.24 Sq.mts. ( 573 Sq.ft. )6
None Booked0% Booked
0% Booked
1bhk53.89 Sq.mts. ( 580 Sq.ft. )3
1 Booked33% Booked
33% Booked
2bhk63.18 Sq.mts. ( 680 Sq.ft. )3
3 Booked100% Booked
100% Booked
12 total apartments / 4 apartments booked. 33% apartments booked.
Work Description in Building RohiniCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress45% done
45% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
work-in-progress50% done
50% Booked

Vishakha

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
VishakhaJan 190036600000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
144.34 Sq.mts. ( 477 Sq.ft. )1
None Booked0% Booked
0% Booked
1bhk44.34 Sq.mts. ( 477 Sq.ft. )2
None Booked0% Booked
0% Booked
1bhk44.36 Sq.mts. ( 477 Sq.ft. )1
None Booked0% Booked
0% Booked
1bhk45.57 Sq.mts. ( 491 Sq.ft. )2
1 Booked50% Booked
50% Booked
1bhk45.8 Sq.mts. ( 493 Sq.ft. )2
None Booked0% Booked
0% Booked
1bhk48.45 Sq.mts. ( 522 Sq.ft. )2
None Booked0% Booked
0% Booked
1bhk35.79 Sq.mts. ( 385 Sq.ft. )1
None Booked0% Booked
0% Booked
1bhk38.42 Sq.mts. ( 414 Sq.ft. )2
1 Booked50% Booked
50% Booked
1bhk40.02 Sq.mts. ( 431 Sq.ft. )2
None Booked0% Booked
0% Booked
1bhk42.11 Sq.mts. ( 453 Sq.ft. )2
2 Booked100% Booked
100% Booked
1bhk43.12 Sq.mts. ( 464 Sq.ft. )1
None Booked0% Booked
0% Booked
1rk31.45 Sq.mts. ( 339 Sq.ft. )2
1 Booked50% Booked
50% Booked
2bhk48.87 Sq.mts. ( 526 Sq.ft. )2
None Booked0% Booked
0% Booked
2bhk52.24 Sq.mts. ( 562 Sq.ft. )2
None Booked0% Booked
0% Booked
shop33.64 Sq.mts. ( 362 Sq.ft. )1
None Booked0% Booked
0% Booked
shop12.08 Sq.mts. ( 130 Sq.ft. )2
None Booked0% Booked
0% Booked
shop12.17 Sq.mts. ( 131 Sq.ft. )1
None Booked0% Booked
0% Booked
shop12.36 Sq.mts. ( 133 Sq.ft. )1
None Booked0% Booked
0% Booked
shop12.87 Sq.mts. ( 139 Sq.ft. )1
1 Booked100% Booked
100% Booked
shop12.92 Sq.mts. ( 139 Sq.ft. )1
None Booked0% Booked
0% Booked
shop13.89 Sq.mts. ( 150 Sq.ft. )1
None Booked0% Booked
0% Booked
shop14.13 Sq.mts. ( 152 Sq.ft. )2
1 Booked50% Booked
50% Booked
shop14.96 Sq.mts. ( 161 Sq.ft. )2
1 Booked50% Booked
50% Booked
shop15.78 Sq.mts. ( 170 Sq.ft. )1
None Booked0% Booked
0% Booked
shop15.84 Sq.mts. ( 171 Sq.ft. )1
None Booked0% Booked
0% Booked
shop17.28 Sq.mts. ( 186 Sq.ft. )1
1 Booked100% Booked
100% Booked
shop23.32 Sq.mts. ( 251 Sq.ft. )1
1 Booked100% Booked
100% Booked
40 total apartments / 10 apartments booked. 25% apartments booked.
Work Description in Building VishakhaCompletion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Harshal Navghare
for Project
Nakshatra
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation