Project overview

Nakshatra Greens is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000005051. Nakshatra Greens is located at S. No. 351, Hissa No. 4A/4B/6. This is a Ongoing being developed by Jsb Buildcon Llp.

Nakshatra Greens has Residential Apartments with carpet areas ranging from 182 to 247 Sq.ft. Carpet. The Project has total 416 of which 51 are currently available for sale.

Nakshatra Greens is being developed on a total land area of 67975 Sq.ft. Nakshatra Greens has 4 Wings / Towers 6A,6B,6C,6E

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Nakshatra Greens
  • Location:
  • S. No. 351, Hissa No. 4A/4B/6
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2018
Developer Details

  • Developer:
    Jsb Buildcon Llp
  • Phone:
  • Address:
  • Pratiek Plaza
Project RERA Details
MAHA REARA No: P99000005051
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Encon Project Consultants For Architectural & Structural Work
Funding Bank UNION BANK OF INDIA
Proposed Possession 30 Jun 2018
Revised Possession 30 Jun 2018
Extended Possession 30 Jun 2019
Litigations No Litigations
Last Modified 04 Jul 2018
Last Retrived 28 Jul 2025
Nakshatra Greens QR Code
Nakshatra Greens
MahaRERA - P99000005051
Apartment Details & Configuration
TypeArea
Residential18.59 Sq.mts. ( 200 Sq.ft. )
Residential23.88 Sq.mts. ( 257 Sq.ft. )
Residential17.1 Sq.mts. ( 184 Sq.ft. )
Residential22.3 Sq.mts. ( 240 Sq.ft. )
Residential22.49 Sq.mts. ( 242 Sq.ft. )
Residential22.58 Sq.mts. ( 243 Sq.ft. )
Residential22.68 Sq.mts. ( 244 Sq.ft. )
Residential22.77 Sq.mts. ( 245 Sq.ft. )
Residential17.47 Sq.mts. ( 188 Sq.ft. )
Residential22.4 Sq.mts. ( 241 Sq.ft. )
Residential22.96 Sq.mts. ( 247 Sq.ft. )
Residential16.91 Sq.mts. ( 182 Sq.ft. )
Residential22.88 Sq.mts. ( 246 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nakshatra Greenslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
0
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
0
Landscaping & Tree Planting100% completed
95% Complete
0
Open Parking100% completed
95% Complete
0
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
0
Solid Waste Management And Disposal100% completed
95% Complete
0
Storm Water Drains100% completed
95% Complete
0
Street Lighting100% completed
95% Complete
0
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
0
Water Conservation, Rain water Harvesting100% completed
95% Complete
0
Water Supply100% completed
95% Complete
Municipal Water Connection To Be Obtained.
Buildings / Wings in Nakshatra Greens
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nakshatra Greens by Jsb Buildcon Llplast updated on 28 Jul 2025 as per information obtained from MARA RERA.

67975 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

416 apartments in total
Total
416
Booked
365
Available
51

Saleable Area Statistics (Sq. ft.)

102403 Total
Total
102403
Booked
89959
Available
12444
Total 416 apartments in project. 365 apartments booked. 87% apartments booked.
Total 102403 Sq.ft. saleable area. 89959 saleable area booked.
88% area booked.

6A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
6AJan 19001510101021
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Residential18.59 Sq.mts. ( 200 Sq.ft. )1
1 Booked100% Booked
100% Booked
Residential23.88 Sq.mts. ( 257 Sq.ft. )110
105 Booked95% Booked
95% Booked
111 total apartments / 106 apartments booked. 95% apartments booked.
Work Description in Building 6ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

6B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
6BJan 1900151010815
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Residential17.1 Sq.mts. ( 184 Sq.ft. )1
1 Booked100% Booked
100% Booked
Residential22.3 Sq.mts. ( 240 Sq.ft. )27
22 Booked81% Booked
81% Booked
Residential22.49 Sq.mts. ( 242 Sq.ft. )14
13 Booked92% Booked
92% Booked
Residential22.58 Sq.mts. ( 243 Sq.ft. )13
11 Booked84% Booked
84% Booked
Residential22.68 Sq.mts. ( 244 Sq.ft. )14
13 Booked92% Booked
92% Booked
Residential22.77 Sq.mts. ( 245 Sq.ft. )14
11 Booked78% Booked
78% Booked
83 total apartments / 71 apartments booked. 85% apartments booked.
Work Description in Building 6BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

6C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
6CJan 19001510101219
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Residential17.47 Sq.mts. ( 188 Sq.ft. )1
1 Booked100% Booked
100% Booked
Residential22.4 Sq.mts. ( 241 Sq.ft. )28
26 Booked92% Booked
92% Booked
Residential22.58 Sq.mts. ( 243 Sq.ft. )14
13 Booked92% Booked
92% Booked
Residential22.68 Sq.mts. ( 244 Sq.ft. )54
47 Booked87% Booked
87% Booked
Residential22.96 Sq.mts. ( 247 Sq.ft. )14
14 Booked100% Booked
100% Booked
111 total apartments / 101 apartments booked. 90% apartments booked.
Work Description in Building 6CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

6E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
6EJan 19001510101021
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Residential16.91 Sq.mts. ( 182 Sq.ft. )1
1 Booked100% Booked
100% Booked
Residential22.4 Sq.mts. ( 241 Sq.ft. )53
39 Booked73% Booked
73% Booked
Residential22.58 Sq.mts. ( 243 Sq.ft. )1
1 Booked100% Booked
100% Booked
Residential22.68 Sq.mts. ( 244 Sq.ft. )54
44 Booked81% Booked
81% Booked
Residential22.88 Sq.mts. ( 246 Sq.ft. )1
1 Booked100% Booked
100% Booked
Residential22.96 Sq.mts. ( 247 Sq.ft. )1
1 Booked100% Booked
100% Booked
111 total apartments / 87 apartments booked. 78% apartments booked.
Work Description in Building 6ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Jsb Buildcon Llp
for Project
Nakshatra Greens
last updated on 28 Jul 2025 as per information obtained from MARA RERA.