Nakoda Viluro is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000046338. Nakoda Viluro is located at 233/A/1/2/2. This is a New being developed by Vivek Patrick Pimenta.

Nakoda Viluro has Bungalow Apartments with carpet areas ranging from 1542 to 1542 Sq.ft. Carpet. The Project has total 15 of which 15 are currently available for sale.

Nakoda Viluro is being developed on a total land area of 17312 Sq.ft. Nakoda Viluro has 16 Wings / Towers Proposed Row House No 10,Proposed Row House No 11,Proposed Row House No 12,Proposed Row House No 13,Proposed Row House No 14,Proposed Row House No 15,Proposed Row House No 16,Proposed Row House No 9,Row House No 1,Row House No 2,Row House No 3,Row House No 4,Row House No 5,Row House No 6,Row House No 7,Row House No 8

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Nakoda Viluro
  • Location:
  • 233/A/1/2/2
  • Const. Stage:
    New
  • Possession:
    31 Dec 2024
Developer Details

  • Developer:
    Vivek Patrick Pimenta
  • Phone:
  • Address:
  • Pimplabhat
Project RERA Details
MAHA REARA No: P99000046338
Project Type Residential / Group Housing
RERA Project Status New
Architect One Source
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 31 Dec 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 22 Jun 2022
Last Retrived 28 Jul 2025
Nakoda Viluro QR Code
Nakoda Viluro
MahaRERA - P99000046338
Apartment Details & Configuration
TypeArea
Bungalow190 Sq.mts. ( 2045 Sq.ft. )
Bungalow114.15 Sq.mts. ( 1229 Sq.ft. )
Bungalow175.87 Sq.mts. ( 1893 Sq.ft. )
Bungalow190.12 Sq.mts. ( 2046 Sq.ft. )
Bungalow159.63 Sq.mts. ( 1718 Sq.ft. )
Bungalow150.72 Sq.mts. ( 1622 Sq.ft. )
Bungalow151.35 Sq.mts. ( 1629 Sq.ft. )
Bungalow140.43 Sq.mts. ( 1512 Sq.ft. )
Bungalow143.24 Sq.mts. ( 1542 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Nakoda Vilurolast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
0
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
0
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
0
Solid Waste Management And Disposal
0
Storm Water Drains
0
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
0
Water Conservation, Rain water Harvesting
0
Water Supply
0
Buildings / Wings in Nakoda Viluro
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Nakoda Viluro by Vivek Patrick Pimentalast updated on 28 Jul 2025 as per information obtained from MARA RERA.

17312 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 16

Wings / Towers in Project

Apartments Statistics

15 apartments in total
Total
15
Booked
0
Available
15

Saleable Area Statistics (Sq. ft.)

28324 Total
Total
28324
Booked
0
Available
28324
Total 15 apartments in project. 0 apartments booked. 0% apartments booked.
Total 28324 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Proposed Row House No 10

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 10Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 10Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Proposed Row House No 11

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 11Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 11Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Proposed Row House No 12

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 12Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 12Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Proposed Row House No 13

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 13Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 13Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Proposed Row House No 14

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 14Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 14Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Proposed Row House No 15

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 15Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 15Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Proposed Row House No 16

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 16Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 16Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Proposed Row House No 9

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Proposed Row House No 9Dec 20242101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190 Sq.mts. ( 2045 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Proposed Row House No 9Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Row House No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 1Dec 20241100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow114.15 Sq.mts. ( 1229 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Row House No 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Row House No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 2Dec 20243101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow175.87 Sq.mts. ( 1893 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Row House No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Row House No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 3Dec 20243101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow190.12 Sq.mts. ( 2046 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Row House No 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Row House No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 4Dec 20241100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow159.63 Sq.mts. ( 1718 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Row House No 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Row House No 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 5Dec 20241100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow150.72 Sq.mts. ( 1622 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Row House No 5Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Row House No 6

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 6Dec 20241100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow151.35 Sq.mts. ( 1629 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Row House No 6Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Row House No 7

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 7Dec 20243101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow140.43 Sq.mts. ( 1512 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Row House No 7Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Row House No 8

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Row House No 8Dec 20241100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow143.24 Sq.mts. ( 1542 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Row House No 8Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress25% done
25% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Vivek Patrick Pimenta
for Project
Nakoda Viluro
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation